A/e services new mental health building 101, parking structure and correction of seismic deficiencies building 100

Ended Definitive Contract Awarded Last action

Contract number
VA101CFMP0051
Awardee
Awarding agency
Obligated
$23,937,321

Award facts

Contract value 74% obligated
  • $23,937,321.38 Current, with exercised options
  • $32,328,369.38 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
NAICS code
541310 Architectural Services
PSC
C114 Hospital Buildings
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price
Place of performance
Seattle, WA 98108, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order P00055 · This modification P00055 is to DE-obligate funds for contract closeout. -$156,205
Supplemental Agreement for work within scope P00054 · This modification P00054 is to authorize a time extension through december 31, 2022, at no additional cost, to allow VA to rewrite HVAC solution scope. $0
Definitize Change Order P00047 · This modification is to definitize P00043 for additional service for user-requested laboratory changes. $0
Supplemental Agreement for work within scope P00053 · CPS services for correction/completion of miscellaneous items for the parking structure and MHR facility, contract no. VA101CFM-p-0051, correct seismic… $48,326
Supplemental Agreement for work within scope P00052 · Additional a/e analysis is required to analyze MHR HVAC system for issues related to ventilation and steam at basement floor sink. $71,810
Supplemental Agreement for work within scope P00050 · This modification is to designate a new architect of record and project manager. $0
Supplemental Agreement for work within scope P00051 · This modification is to authorize additional architectural efforts due to DD phase delay and CD phase extension, and mechanical efforts due to HVAC redesign and… $339,884
Supplemental Agreement for work within scope P00048 · This modification is to provide additional services for radiation protection physicist report. $1,700
Supplemental Agreement for work within scope P00049 · This modification is to extend CPS for 4 months from april 1 to july 31, 2018 and add 30 site visits. $345,960
Other Administrative Action P00046 · This modification is to extend funding obligation end date to 9/30/18. $0
Supplemental Agreement for work within scope P00045 · This modification is to authorize late start escalation of base construction period services for parking structure and mental health and research facility. $119,753
Supplemental Agreement for work within scope P00044 · This modification is to authorize additional services to provide detailed cost estimate for MHR cup mechanical revision. $14,250
Supplemental Agreement for work within scope P00041 · This change order is to authorize CPS extension thru march 31, 2018 and definitize modification P00038, P00039 and P00040. $690,237
Supplemental Agreement for work within scope P00042 · This change order is to authorize additional design and CPS for closeout and warranty items for parking structure. $147,800
Change Order P00043 · This change order is to authorize design services for user-requested laboratory changes. $17,000
Change Order P00040 $247,699
Change Order P00039 $247,700
Change Order P00038 · This change order is to authorize additional 60 calendar days for construction period services from march 9 to may 7, 2017. $247,700
Supplemental Agreement for work within scope P00037 · This supplemental agreement is to authorize a/e to purchase twelve (12) additional months for tririga system license for the 2017 calendar year. $2,532
Supplemental Agreement for work within scope P00036 · This supplemental agreement is to authorize additional MHR site visits during construction for seven months from august, 2016 to february, 2017. $180,960
Supplemental Agreement for work within scope P00035 · This supplemental agreement is to authorize additional architectural and structural services under CPS for MH and research facility and demolition project. $56,705
Supplemental Agreement for work within scope P00033 · This supplemental agreement is to authorize additional construction period services thru october 7, 2016 and definitize modification P00031 and P00032 for… $90,075
Supplemental Agreement for work within scope P00034 · This supplemental agreement is to authorize additional 90 calendar days for CPS from april 2, 2016 to june 30, 2016 for correct seismic deficiencies B100… $27,000
Change Order P00032 $115,450
Change Order P00031 · This supplemental agreement is to authorize additional 60 calendar days for CPS from november 20, 2015 to january 19, 2016 for parking structure. $115,450
Supplemental Agreement for work within scope P00030 · This supplemental agreement is to authorize additional 7-month construction period services extension and definitization of modification NOS. P00017, P00021,… $122,192
Change Order P00029 · This supplemental agreement is to authorize 60 calendar days for seismic CPS from october 2, 2015 to december 2, 2015. $40,000
Supplemental Agreement for work within scope P00027 · This supplemental agreement is to authorize additional design services for chiller resize and cup redesign. $205,000
Change Order P00028 · This change order is to authorize additional 60 calendar days for seismic CPS from august 3, 2015 to october 2, 2015. $40,000
Other Administrative Action P00026 · This administrative change is to update the end date from june 2, 2015 to october 6, 2017, for ecms and FMS purposes only. $0
Supplemental Agreement for work within scope P00025 · This supplemental agreement is to correct modification P00015 by obligating funds for adjustment of site visit fee during construction period services for… $140,637
Definitize Change Order P00023 · This supplemental agreement is to definitize change order P00022 for design of early ambulance access road to allow uninterrupted access to emergency… $4,100
Change Order P00024 · This change order is to direct AE to provide CPS services for additional 60 calendar days from june 3 - august 2, 2015 for project no. 663-406, correct… $40,000
Change Order P00022 · This change to direct AE to provide design services for early ambulance access road to allow uninterrupted access to emergency department, for project no.… $10,000
Change Order P00021 · This change to direct AE to provide CPS for additional 60 calendar days for 663-406, correct seismic deficiencies. $40,000
Supplemental Agreement for work within scope P00020 · This change to exercise firm-fixed priced options for CPS under SA-003 (item no. 6) and SA-006 (item no. 2) for phase 2 only. $95,850
Supplemental Agreement for work within scope P00019 · This is to exercise firm-fixed priced options for construction period services for 24 months for 663-405B, phase 2 MHR(line item no. 8 for $2024028 and line… $2,290,512
Supplemental Agreement for work within scope P00018 · This change to authorize AE to print and deliver bid document drawings and specifications for phase 2, MHR facility and demolition, to the senior resident… $10,500
Change Order P00017 · This change order is to direct AE to provide construction period services for additional 60 calendar days from february 1, 2015 to april 2, 2015. $40,000
Supplemental Agreement for work within scope P00015 · This is to adjust the site visit fee for B101 mental health services parking structure (MOD P00006, option item no. 10) and B101 MHS (option no. 8) at no… $0
Supplemental Agreement for work within scope P00016 · This is to authorize additional structural engineer support for B101 mental health services parking structure project. $23,500
Supplemental Agreement for work within scope P00014 · This is for AE to provide additional services for emergency power modifications to MH & r documents and recalculation of emergency power capabilities. $12,000
Supplemental Agreement for work within scope P00013 · This is to exercise firm-fixed priced option for extra MHR bid services under modification P00002 (item no. 1C). $72,550
Supplemental Agreement for work within scope P00009 · This is to exercise firm-fixed priced options for construction period services under SA-003 (item no. 6) and SA-006 (item no. 2) for phase 1, parking structure,… $682,413
Supplemental Agreement for work within scope P00008 · This is to require AE to purchase two (2) tririga system licenses, one for project 663-405 and one for project 663-406, for twenty months from march 1, 2014… $8,440
Supplemental Agreement for work within scope P00006 · This is to exercise firm-fixed priced option line item 10 for construction period services and site visits. $536,210
Supplemental Agreement for work within scope P00007 $8,400
Supplemental Agreement for work within scope P00005 · This is to add vaar clause 852.232-72, electronic submission of payment requests (NOV. 2012) and far clause 52.204-10, reporting executive compensation and… $0
Supplemental Agreement for work within scope P00004 · This is to authorize reimbursement to print conformed set documents and to publish final fonsi notice of availability. $6,650
Supplemental Agreement for work within scope P00002 · A/e to provide additional services to repackage the current CD-1 documents as separate CD-2 documents. This is to obligate $559,930, with the government… $559,930
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

Quick answers

Who was awarded contract VA101CFMP0051?

VA101CFMP0051 was awarded to Stantec Consulting Services Inc. by VA Office of Construction and Facilities Management (Headquarters) on August 31, 2009.

How much is contract VA101CFMP0051 worth?

The government has obligated $23,937,321 on VA101CFMP0051. Its potential value, with all options, is $32,328,369.

Was contract VA101CFMP0051 competed?

The extent of competition for VA101CFMP0051 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award