Construction contract to rewind generator 1 and generator 2 at flatiron powerplant, loveland, colorado

Ended Definitive Contract Awarded Last action

Contract number
INR13PC60500
Awardee
Awarding agency
Obligated
$11,590,492

Award facts

Contract value 100% obligated
$11,590,492.13 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Loveland, CO 80537, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action P00042 · This modification checks a box in prism so that we are able to make a payment after the period of performance -$33,832
Other Administrative Action 41 · Extend the completion date of the contract to match the extended warranty completion date of generator 2 final maintenance. $0
Supplemental Agreement for work within scope 40 · Negotiated request for an equitable adjustment related to oil leaks G1 and G2 powerplant, loveland, colorado $33,121
Funding Only Action 39 · Funding action only to balance the obligate amount with the actual contract funding to complete the project. $9,808
Supplemental Agreement for work within scope 36 · Definitizes MOD 0019. $8,142
Supplemental Agreement for work within scope 38 · Definitize MOD 0024. $30,720
Supplemental Agreement for work within scope 37 · Definitize MOD 0018. $132,489
Supplemental Agreement for work within scope 35 · This modification definitizes unilateral MOD 0020, to install upper guide bearing support and refurbish jack screws on G2 + TE 34 C.days. $34,677
Supplemental Agreement for work within scope 34 · Liquidated damages assessment. -$318,969
Other Administrative Action 30 · Action to deobligate funds under contract 08CC603730. The funds will be reobligated under a new number, to meet fbms requirements of the numbering system. $0
Definitize Change Order 32 · This action definitizes unilateral directed MOD # 0025 and provides an equitable adjustment to the contractor in the amount of $9,267.68. $2,198
Change PIID 31 · Action to deobligate funds under contract 08CC603730. The funds will be reobligated under a new number, to meet fbms requirements of the numbering system. $0
Definitize Change Order 33 · This action definitizes unilateral modification 0017, negotiated for an equitable adjustment to the KTR $12,809.88. (unilateral was obligated for $13,500.00.… $0
Supplemental Agreement for work within scope 29 · Definitize modification no. 0015 - $0
Supplemental Agreement for work within scope 27 · Critical functions - this modification provide an equitable adjustment to the contractor for work completed under the contract related to the repair of the… $51,538
Definitize Change Order 28 · Critical functions - this modification definitized unilateral directed change order no. 0012 and provide an equitable adjustment for the work completed by MOD… -$33,832
Definitize Change Order 26 · Critical function - this modification definitizes unilateral modification 0011 to remove the turbine bearing at flatiron PP, bore to correct measurements and… $63,080
Change Order 25 · Critical function this modification directs the contractor to provide labor, material and equipment to eliminate the oil leak on the thrust tub; replace the… $7,100
Definitize Change Order 23 · Closely associated this modification definitizes unilateral MOD 0007 (11/12/2009)and provides an equitable adjustment to the contractor for work performed under… $39,874
Change Order 24 · Critical functions unilateral modification to correct the upper guide bearing heating and shoe alignment and replace leaking thrust tub blonze valve. $25,000
Definitize Change Order 22 · This modification definitizes MOD 008, issued as a unilateral change on 1/8/2010, to direct the contracto to perform abrasive blast and coating for generator… $32,292
Definitize Change Order 21 · Modification to definitize MOD 06 issued as a unilateral change to direct contractor to provide work on machining and grinding of the thrust runner upper… $9,698
Change Order 20 · Modification to direct the contractor to proceed with repair of the upper guide bearing support. Provide shop drawing of the jack screw. Manufacture upped guide… $30,000
Change Order 19 · Unilateral directed modification for changes to relocate the lower bearing bridge so the bottom vapor seals of the generator are concentric to the shaft. $7,500
Change Order 18 · By this modification, the contractor is directed to perform additional work necessary to make precision measurements of the unit 2 generator thrust collar,… $110,000
Change Order 17 · Unilateral modification to repair and machining the lower and upper guide bearing oil seals for flatiron unit 2 generator. $13,500
Supplemental Agreement for work within scope 16 · This modification provides for an equitable adjustment of time extension in lieu of working sundays, additional hours per day (GOV't does not have inspector)… $0
Change Order 15 · This not to exceed MOD is to direct the contractor to continue to work on the turbine bearing rebabbitting, machining, recoating of the thrust tub and collar,… $200,000
Supplemental Agreement for work within scope 14 · Modification for a 30-day time extension in lieu of accomodating a second work shift during the month of november. GOV't does not have the resources at this… $0
Change Order 12 · Obligate the not to exceed amount in preparation to negotiate the undefinitized modification 0012. $230,000
Change Order 11 · Modification issued unilaterally to direct emergency work on the turbine bearing for generator G1 at flatiron powerplant, not to exceed. EST. AMT not… $0
Other Administrative Action 13 · Include clause 52.204-11 deviation march 2010. Federal reporting clause (diapr 2010 amend 1 dated 3/10/10) $0
Exercise an Option 9 · This modification is to exercise optional schedule D prepriced and prenegotiated under the original contract. Option D authorizes the KTR to disassemble and… $585,920
Funding Only Action 10 · MOD 10 obligates the FY10 contract funding, under the limitation of funding clause FY10 (original contract award funds). $2,309,086
Change Order 8 · Modification to contract #08CC603730 - construction contract to rewind generator 1 and generator 2 at flatiron powerplant, loveland, colorado $20,000
Other Administrative Action 5 $0
Change Order 7 $0
Change Order 6 $0
Supplemental Agreement for work within scope 4 · Arra funded modification: bureau project number 55.000 - to contract #08CC603730 - construction contract to rewind generator 1 and generator 2 at flatiron… $324,383
Other Administrative Action 3 $0
Funding Only Action 2 $2,000,000
Funding Only Action 1 $2,500,000
Original award $3,167,000
Show all 43

About this award

This is a firm fixed-price construction contract awarded by the U.S. Bureau of Reclamation, a civilian federal agency, to National Electric Coil Inc. to rewind Generator 1 and Generator 2 at the Flatiron Powerplant in Loveland, Colorado. The contract has a ceiling value of $11,590,492.13 and a completion date of June 30, 2017. There is no set-aside designation for this award.

Quick answers

Who was awarded contract INR13PC60500?

INR13PC60500 was awarded to National Electric Coil Inc. by Bureau of Reclamation (Department of the Interior) on September 9, 2008.

How much is contract INR13PC60500 worth?

The government has obligated $11,590,492 on INR13PC60500.

Was contract INR13PC60500 competed?

The extent of competition for INR13PC60500 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award