SAN luis demonstration treatment plant

Ended Definitive Contract Awarded Last action

Contract number
INR13PC20508
Awardee
Awarding agency
Obligated
$24,756,153

Award facts

Opportunity
  • R12PS20107 Solicitation number
Contract value 100% obligated
$24,756,153.46 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Y1NE Construction Of Water Supply Facilities
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Dos Palos, CA 93620, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 20 · R13PC20508 - modification no. 0020- SAN luis unit demonstration treatment plant. The purpose of this modification is to definitize outstanding reas, claims,… -$1,120,898
Change Order 19 · R13PC20508 - modification no. 0019 - SAN luis unit demonstration treatment plant $1,015,000
Change Order 18 · R13PC20508 - modification no. 0018 - SAN luis unit demonstration treatment plant $359,763
Supplemental Agreement for work within scope 17 · R13PC20508 - modification no. 0017 - SAN luis unit demonstration treatment plant $145,509
Change Order 16 · R13PC20508 - modification no. 0016 - SAN luis unit demonstration treatment plant $800,000
Supplemental Agreement for work within scope 14 · R13PC20508 - bilateral modification no. 0014 - SAN luis unit demonstration treatment plant $72,518
Other Administrative Action 15 · R13PC20508 - modification no. 0015 - SAN luis unit demonstration treatment plant $0
Change Order 13 $400,000
Change Order 12 · SAN luis unit demonstration treatment plant - unilateral modification no. 0012- $65,000
Supplemental Agreement for work within scope 11 $407,456
Supplemental Agreement for work within scope 10 · SAN luis unit demonstration treatment plant - bilateral modification no. 0010 - the purpose of this modification is to negotiate a bilateral agreement based… $44,042
Other Administrative Action 9 · SAN luis unit demonstration treatment plant - admin MOD 0009 for fbms data cleansing IAW RAC 14-15 $0
Supplemental Agreement for work within scope 8 · This modification provides compensation for rfps 001-008 and RFC 029 $143,264
Change PIID 7 $0
Change Order 6 · This unilateral modification changes the realignment of lateral no. 1 and revised contract specifications and drawings. $5,500
Change Order 5 · This unilateral modification adds 14 grounding rods to the concrete foundations. $4,000
Change Order 4 · This modification relocates the booster pump station and revises the concrete foundation drawings. This modification will revise and replace section 33 16 50… $7,000
Change Order 3 · This modification will direct the contractor to make piping changes to accomodate both HCL and H2SO4 in the treatment process system. $29,000
Funding Only Action 2 · Funding action only, this admin. MOD. Will fully fund contract value. $6,166,900
Supplemental Agreement for work within scope 1 · Changes to included computer document management system, section B, C, F, H $12,100
Original award $16,200,000
Show all 21

Quick answers

Who was awarded contract INR13PC20508?

INR13PC20508 was awarded to Slayden Construction Group, Inc. by Bureau of Reclamation (Department of the Interior) on September 21, 2012.

How much is contract INR13PC20508 worth?

The government has obligated $24,756,153 on INR13PC20508.

Was contract INR13PC20508 competed?

The extent of competition for INR13PC20508 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award