Critical function - this project include demolition and reconstruction of pumping plant masonry brick walls and steel superstrucure, reinforce concrete walls, roofing, modernization of elevator. North…

Ended Definitive Contract Awarded Last action

Contract number
INR12PC60146
Awardee
Awarding agency
Obligated
$3,920,161

Award facts

Opportunity
  • R12PS60146 Solicitation number
Contract value 100% obligated
$3,920,160.69 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Center, ND 58530, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 13 · Critical function - MOD 13 final deobligate converted excess funds. -$4,881
Supplemental Agreement for work within scope 12 · Critical function - MOD to document the contractor's consideration to the government for additional time to the contract completion. $0
Supplemental Agreement for work within scope 11 · Critical function - remove existing handrails above gate service room. Remove blowin batts insulation. $7,714
Supplemental Agreement for work within scope 10 · Critical function - this modification adjusts the bid schedule estimated quantity to the actual quantity measured in place (VEQ clean up modification). $27,648
Supplemental Agreement for work within scope 9 · Critical function - negotiated request for an equitable #2 - adjustment due to GOV't shutdown - this request covers the period from december 1, 2013 through… $89,344
Supplemental Agreement for work within scope 8 · Critical function - negotiated request for an equitable adjustment due to GOV't shutdown - this request covers the period october 1, 2013 through november 30,… $127,537
Supplemental Agreement for work within scope 7 · Critical function - definitize MOD 0005 - add concrete to the thickness of the wall. $2,500
Definitize Change Order 6 · Definitize MOD 003 - asbestos abatement. Snake creek pumping plant construction project. Adjustment in the fpds amount to match FFS amount. $0
Change Order 5 · Change order unilaterally directed to provide more concrete to construct wall 12" wide instead of 9" wide as per specs. $2,508
Supplemental Agreement for work within scope 4 · Modification to assemble, construct and install new gate hoistsat snake creek PP. The old gate hoists contained asbestos and they are being removed under a… $350,610
Change Order 3 · Critical functions - unilateral change order to remove asbestos and lead in the existing gate enclosures before removal from the existing structures. $89,000
Funding Only Action 2 · Critical function - reobligate funds with new cost authority. $0
Funding Only Action 1 · Critical functions - deobligation of funds due to change in cost authority. $0
Original award $3,228,180
Show all 14

Description

Critical function - this project include demolition and reconstruction of pumping plant masonry brick walls and steel superstrucure, reinforce concrete walls, roofing, modernization of elevator. North dakota.

Quick answers

Who was awarded contract INR12PC60146?

INR12PC60146 was awarded to Gracon Corporation by Bureau of Reclamation (Department of the Interior) on September 14, 2012.

How much is contract INR12PC60146 worth?

The government has obligated $3,920,161 on INR12PC60146.

Was contract INR12PC60146 competed?

The extent of competition for INR12PC60146 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award