Award of construction project at canyon ferry reservoir, riverside campground development, montana - firm-fixed price

Ended Definitive Contract Awarded Last action

Contract number
INR11PC60026
Awardee
Awarding agency
Obligated
$944,858

Award facts

Opportunity
Contract value 100% obligated
$944,858.02 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record
Set-aside
No set-aside
Competition
Full and Open Competition · 10 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Helena, MT, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Definitize Change Order 13 · Definitize MOD 003 - repair to be boat ramp - additional aggregate. -$3,730
Supplemental Agreement for work within scope 12 · Modification definitizes unilateral MOD 0005 for the replacement of CMP culvert, speed control DIP, raise fire hydrant at CF riverside campground project. $0
Funding Only Action 11 · This modification deobligates excess funds which were obligated under unilateral MOD 0005 - -$7,848
Funding Only Action 10 · Critical functions - this modification adjusts the funds in FFS by deobligating MOD 8 and obligating MOD 9 - actions from ideas-PD did not interface with FFS. $0
Supplemental Agreement for work within scope 8 · Critical functions - this modification provides consideration to the government for the fine aggregate inadequate placement of the gravel at different thickness… -$5,174
Funding Only Action 6 · Critical function - this modification is a funding action only to adjust the incorrect amount obligated under MOD 2. $315
Definitize Change Order 9 · Critical function - this modification definitizes MOD 02 as negotiated with the contractor based on actual time and material documentation, plus mark UPS and… $157
Supplemental Agreement for work within scope 7 · Critical function - this modification is to adjust the estimated bid schedule quantity versus the measured in place actual quantity (VEQ) -$8,780
Change Order 5 · Closely associated the contractor shall furnish labor, material and equipment to 1) remove and replace CMP culvert; 2) place additional speed control DIP; and… $39,000
Supplemental Agreement for work within scope 4 · This modification is needed to provide the contractor with equitable adjustment under a RFP to fill abandoned well at the riverside campground - canyon ferry,… $1,336
Change Order 3 · Unilateral directed modification to place non-plastic aggregate base material and fine walkway at the boat ramp, canyon ferry. $5,000
Change Order 2 · Place contech C-80 or equivalent GEO-grid per manufacturer S instructions such that IT completely covers the floor of the additional excavation that will be… $1,035
Other Administrative Action 1 · This modification replaces 6 drawings in the contract with updated drawings showing the coordinates and additional control points necessary to stake the site.… $0
Original award $923,549
Show all 14

Quick answers

Who was awarded contract INR11PC60026?

INR11PC60026 was awarded to Helena Sand & Gravel, Inc. by Bureau of Reclamation (Department of the Interior) on May 6, 2011.

How much is contract INR11PC60026 worth?

The government has obligated $944,858 on INR11PC60026.

Was contract INR11PC60026 competed?

The extent of competition for INR11PC60026 was full and open competition. The government received 10 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award