Recovery fish screen structure phase 3, contra costa canal arra project no. 19.000
Ended Definitive Contract Awarded Last action
- Contract number
- INR10PC20R32
- Awardee
-
Flatiron West, Inc. UEI FD8GL9SJAP93
- Awarding agency
-
Bureau of Reclamation
Department of the Interior
- Obligated
- $14,025,512
Award facts
- Opportunity
-
- R10PS20R32 Solicitation number
- RECOVERY CONTRA COSTSA CANAL FISH SCREEN PHASE 3TAS::14 0681::TAS ARRA Project No. 19. 000 Award Notice · Posted Jan 12, 2010
- Contract value 100% obligated
- $14,025,511.66 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y299 Contruct/All Other Non-Bldg Facs
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 9 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Oakley, CA 94561, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Close Out | $0 | |
| Supplemental Agreement for work within scope | $47,702 | |
| Supplemental Agreement for work within scope | $83,786 | |
| Definitize Change Order | $22,768 | |
| Supplemental Agreement for work within scope | $77,518 | |
| Definitize Change Order | $20,940 | |
| Supplemental Agreement for work within scope | $111,072 | |
| Change Order | $38,000 | |
| Change Order | $37,454 | |
| Supplemental Agreement for work within scope | $82,236 | |
| Supplemental Agreement for work within scope | $63,847 | |
| Change Order | $99,637 | |
| Change Order | $249,402 | |
| Supplemental Agreement for work within scope | $69,617 | |
| Supplemental Agreement for work within scope | $262,072 | |
| Supplemental Agreement for work within scope | $8,727 | |
| Supplemental Agreement for work within scope | $68,478 | |
| Original award | $12,682,255 |
Show all 18
About this award
This is a $14,025,511.66 firm fixed-price definitive contract awarded by the U.S. Bureau of Reclamation, a civilian federal agency, to Flatiron West, Inc. for the RECOVERY FISH SCREEN STRUCTURE PHASE 3, CONTRA COSTA CANAL ARRA PROJECT NO. 19.000 - TAS::14 0681::TAS. The contract does not have a set-aside designation. The work is to be performed in Oakley, California, with an ultimate completion date of March 1, 2012. Flatiron West, Inc. is the prime contractor for this award.
Quick answers
Who was awarded contract INR10PC20R32?
INR10PC20R32 was awarded to Flatiron West, Inc. by Bureau of Reclamation (Department of the Interior) on May 6, 2010.
How much is contract INR10PC20R32 worth?
The government has obligated $14,025,512 on INR10PC20R32.
Was contract INR10PC20R32 competed?
The extent of competition for INR10PC20R32 was full and open competition. The government received 9 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award