Recovery--installation of new cast-in-place concrete barrel siphons at the weber branch siphon and the weber coulee siphon. This award is funded with monies made available to reclamation under the…

Ended Definitive Contract Awarded Last action

Contract number
INR09PC10R03
Awardee
Awarding agency
Obligated
$28,181,160

Award facts

Opportunity
  • 09SP101729 Solicitation number
Contract value 100% obligated
$28,181,159.94 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 11 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Moses Lake, WA 98837, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 57 · Close-out action project tracking #7.000 -$578,429
Definitize Change Order 56 · Modification to resolve all outstanding issues. Project tracking #7.000 $0
Definitize Change Order 53 · Modification to definitize change order 15, decommissioning wells. Project tracking #7.000 $0
Definitize Change Order 55 · Modification to definitize change order modification 17, carbon fiber wrap. Project tracking #7.000 $0
Definitize Change Order 54 · Modification to definitize change order 7, supplemental dewatering. Project tracking #7.000 $0
Definitize Change Order 52 · Project #7.000 definitize change order 23 - french drains $0
Definitize Change Order 51 · To definitize change order 024 - emergency siphon repairs. Tracking #7.000 $0
Definitize Change Order 50 · Definitizes change order 038 - I90 repairs. Tracking #7.000 $0
Definitize Change Order 49 · Project #7.000 definitizes costs associated with partial suspension $0
Definitize Change Order 48 · Project #7.000 to definitize REA for mix design change $0
Definitize Change Order 47 · Project tracking #7.000 to definitize change order 14, weko seals $0
Definitize Change Order 46 · Arra tracking #7.000 modification to definitize change order 13 to remove sediment under I-90. $0
Definitize Change Order 45 · Tracking #7.000 definitize change order $0
Definitize Change Order 44 · This modification definitizes change order 036 to provide new stoplogs. Project tracking #7.000 $0
Definitize Change Order 43 · To definitize change order modification 032, remove stoplogs. Project tracking #7.000 -$2,840
Definitize Change Order 42 · Definitizes change order 034 project tracking #7.000 $0
Definitize Change Order 41 · Definitize change order 26. Project tracking #7.000 $0
Definitize Change Order 40 · To definitize change order 18. Project tracking #7.000 $0
Definitize Change Order 39 · Definitizes change order 037, GPR support project tracking #7.000 $0
Change Order 38 · Arra project tracking #7.000 change order for I90 repairs and to correct funding error under modification 037. $350,000
Change Order 37 · Arra project tracking #7.000 change order for GPR under I90 $50,000
Change Order 36 · Arra project tracking #7.000 change order for precast stoplogs in lieu of using existing. $50,000
Funding Only Action 33 · Project tracking #7.000 funding MOD $36,000
Definitize Change Order 35 · Project tracking #7.000 MOD to definitize change order 9 -$2,257
Change Order 34 · Project tracking #7.000 change order $0
Change Order 32 · Arra tracking & 7.000; change order to remove stoplogs $30,000
Definitize Change Order 31 · Arra project tracking # 7.000; equitable adjustment for repairing coupon. $5,100
Definitize Change Order 30 · Project tracking #7.00 definitizes change order modification 004, internet based const. DOC. Sys. -$18,877
Definitize Change Order 29 · Project tracking # 7.00 definitizes change order modification 005 dewatering $0
Definitize Change Order 28 · Project tracking # 7.00 to definitize change order modification 012 $0
Definitize Change Order 27 · Project tracking #7.00 modification to the contract for corrective action on concrete form systems. $0
Change Order 26 · Modification needed to direct contractor to provide quarry spalls. Arra project tracking #7.000. $0
Funding Only Action 25 · Project #7.000 fundig MOD to cover inefficiencies REA; additional dewatering effortts. $2,000,000
Change Order 24 · Project #7.000 change order: change in compaction percentage. $200,000
Definitize Change Order 22 · Project #7.000 removal of scrap;surveying of MIS-aligned existing siphon; blow-off repairs. $0
Change Order 23 · Project #7.000 change order/funding MOD for french drain $300,000
Change Order 21 · Arra project tracking #7.000 change order to correct specification 01452 $35,000
Definitize Change Order 20 · Arra project tracking #7.000 reimbursement for relocation of utilities $0
Funding Only Action 19 · Arra project tracking #7.000; funding modification: to increase funds for supplemental dewatering. $200,000
Change Order 18 · Arra project tracking #7.000; change order to accelerate concrete repairs $6,000
Change Order 17 · Project ID #7.000 change order for carbon filter repairs to concrete siphons $0
Definitize Change Order 16 · Project ID #7.000 this supplemental agreement corrects MOD 8 and extend the term of the contract. $0
Change Order 15 · Project tracking #7.000; change order--decommissioning wells $522,000
Change Order 14 · Project tracking #7.000; change order--weko seals $130,000
Change Order 13 · Project tracking #7.000; change order for removing sediment in pipe under I-90. $21,000
Change Order 12 · Project tracking #7.000; change order for core drilling. $10,000
Funding Only Action 11 · Project tracking #7.000; additional funding for dewatering effort. $750,000
Change Order 9 · Project tracking #7.000; change order to repair she-bolts $50,000
Supplemental Agreement for work within scope 10 · Project tracking #7.000; this supplemental agreement definitizes price increases to six contract line items and a price decrease to one contract line item as… $0
Change Order 7 · Project tracking #7.000; dewatering wells $650,000
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $28,181,159.94 firm fixed price definitive contract awarded by the Bureau of Reclamation, a civilian federal agency, to Mowat Construction Company for the installation of new cast-in-place concrete barrel siphons at the Weber Branch Siphon and the Weber Coulee Siphon. The contract is funded through the American Recovery & Reinvestment Act of 2009 and has an ultimate completion date of March 31, 2012. The contract does not have a set-aside designation. Key aspects of the requested work include the installation of the new siphons, which are part of the Bureau of Reclamation's larger project work.

Description

Recovery--installation of new cast-in-place concrete barrel siphons at the weber branch siphon and the weber coulee siphon. This award is funded with monies made available to reclamation under the american recovery & reinvestment act of 2009. Bureau project identification number: 7.000.

Quick answers

Who was awarded contract INR09PC10R03?

INR09PC10R03 was awarded to Mowat Construction Company by Bureau of Reclamation (Department of the Interior) on September 30, 2009.

How much is contract INR09PC10R03 worth?

The government has obligated $28,181,160 on INR09PC10R03.

Was contract INR09PC10R03 competed?

The extent of competition for INR09PC10R03 was full and open competition. The government received 11 offers.

On GovTribe