Definitive Contract INR06CC308070
Award Date 9/25/06
Potential Completion Date 4/18/07
Potential Value $1.3M
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Not listed Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Parker Dam, CA 92267, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
6
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Department of the Interior's Bureau of Reclamation awarded a firm fixed price delivery order to Hartman-Walsh Painting Company, a nationwide industrial painting and coatings contractor, for the Upper Arizona Penstock Spot Coating at Hoover Dam. This work is being performed under a larger 5-year, $12 million indefinite-delivery/indefinite-quantity (IDIQ) contract for protective coating services at Hoover Dam, Parker Dam, and Davis Dam facilities along the Lower Colorado River. The current...
- This is a $5,700,159.57 firm fixed-price delivery order contract awarded by the Bureau of Reclamation, a civilian agency within the U.S. Department of the Interior, to Hartman-Walsh Painting Company, a subsidiary of Hartman-Walsh Corp. The contract is for the Lower Arizona Penstock Recoating project at the Hoover Dam in White Hills, Arizona, with a performance period through June 27, 2025. Hartman-Walsh Painting Company has extensive experience performing specialized coating and rehabilitation...
- The Department of the Interior's Bureau of Reclamation awarded a firm fixed price delivery order to Hartman-Walsh Painting Company, doing business as Hartman Walsh Painting Co., for protective coating services at the Hoover Dam in Arizona. This delivery order was issued under an Indefinite-Delivery/Indefinite-Quantity (IDIQ) contract vehicle with a potential value of $12 million for protective coating services at the Hoover Dam, Parker Dam, and Davis Dam facilities along the Lower Colorado...
- Hartman-Walsh Painting Company, operating as Hartman Walsh Industrial Services, was awarded a definitive firm fixed-price contract by the Bureau of Reclamation valued at $7.51M for river outlet works pipe relining services at the Glen Canyon Power Plant in Page, Arizona. This contract, awarded on April 8, 2024, with an ultimate completion date of October 5, 2025, represents specialized infrastructure maintenance work critical to the facility's operational integrity. The award was made without...
- The U.S. Army Corps of Engineers, Los Angeles District awarded a $522,502 firm fixed price delivery order to Taylor Engineering, PLLC. The order is for repair work to the downstream weir at Painted Rock Dam in Maricopa County, Arizona, with performance required between October 2021 through May 2022. As the prime, Taylor Engineering will complete the requested repairs to infrastructure that is part of the Corps' broader flood risk management program in the region. No subcontractors or set aside...
- This federal contract award was issued by the Bureau of Reclamation, a civilian agency within the U.S. Department of the Interior, to Hartman-Walsh Painting Company, a subsidiary of Hartman-Walsh Corp. The contract is for the Tailbay Stoplog Coating project at the Hoover Dam in Arizona, with a total ceiling value of $406,761.94 and a period of performance through October 31, 2025. The contract is a firm-fixed-price delivery order, without any set-aside designation. Hartman-Walsh Painting Company...
- The Bureau of Reclamation, an agency within the U.S. Department of the Interior, has awarded a $1,284,862.10 firm-fixed-price contract to Basler Services LLC, a for-profit limited liability company, for the digital front-end upgrade of four 30-megawatt hydroelectric generating units at the Parker Dam in California. The contract is for the retrofit of the current Basler ECS-2100 voltage regulators with Basler DECS-2100 voltage regulators, including all labor, parts, and equipment to install,...
- The Department of the Interior's Bureau of Reclamation awarded a firm fixed price delivery order to Hartman-Walsh Painting Company, doing business as Hartman Walsh Painting Co., for protective coating application services at the Hoover Dam in Arizona. This order, valued at $441,141, was issued under a larger 5-year indefinite-delivery/indefinite-quantity (IDIQ) contract for protective coating services at multiple Reclamation dam facilities along the Lower Colorado River, which has a potential...
- This is a $1,107,598.50 firm fixed-price definitive contract awarded by the U.S. Bureau of Reclamation, a civilian agency, to Walker River Construction, Inc., a minority-owned, self-certified small disadvantaged business. The contract is for generator cooling piping work at the Parker Dam in Parker, California. The contract has an 8(a) sole source set-aside designation, which provides contracting opportunities for small, disadvantaged businesses. Walker River Construction is a woman-owned,...
- This is a definitive contract awarded by the U.S. government to a prime contractor for the repair of painted surfaces on the lower Arizona penstock at the Hoover Dam's Boulder Canyon Project, located in Boulder City, Nevada. The contract is a firm fixed-price award with a ceiling value of $366,292.35 and an ultimate completion date of December 29, 2005. The contract was not set aside for any specific designation. Without additional information, the prime contractor, major subcontractors, and...
PAINTING FIXED-WHEEL PENSTOCK GATES AND REFURBISHING FIXED-WHEEL ASSEMBLIES, PARKER DAM AND POWERPLANT, PARKER - DAVIS PROJECT, ARIZONA - CALIFORNIA
Posted 9/25/06
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 3 | Supplemental Agreement for work within scope | $6.7k | 7/16/07 | |
| 2 | Change Order | $0 | 3/20/07 | |
| 1 | Other Administrative Action | $0 | 9/26/06 | |
| Not listed | Not listed | $678.9k | 9/25/06 |