Definitive Contract INPC2011101124
Award Date 5/13/10
Potential Completion Date 10/11/10
Potential Value $2M
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Not Competed
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Port Angeles, WA, USA
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a fixed-price level of effort contract awarded to HDR Engineering Inc. by the National Office of the National Park Service, a civilian federal agency. The contract, valued at $58,042.57, is for construction management services to support the Elwha River Ecosystem and Fisheries Program, which aims to maintain water quality at the Nippon Paper Mill as part of the larger river restoration effort. The contract was awarded under the Professional Engineering Services (PES) schedule and does...
- <p>This is a firm fixed-price delivery order contract awarded by the National Office of the Army Corps of Engineers to URS Group, Inc., a subsidiary of AECOM, to provide architect-engineer services during construction to maintain water quality at the Nippon Paper Mill in Port Angeles, Washington. The contract has a ceiling value of $55,176.72 and a period of performance ending on February 28, 2011. The contract is not a set-aside award.</p>
- This is a $776,416.00 firm fixed price definitive contract awarded by the National Park Service (NPS), a civilian federal agency, to Watershed Environmental Solutions LLC, a woman-owned small disadvantaged business, for the recovery, restoration, and griff creek culvert replacement project related to the Elwha River in Olympic National Park, Washington. The contract does not have a set-aside designation. The award date was May 5, 2010, with a completion date of September 12, 2010. Watershed...
- This is a $17,477,852.94 Firm Fixed Price definitive contract awarded by the Intermountain Region of the National Park Service, a civilian agency, to James W. Fowler CO. for the construction of a fish hatchery and related infrastructure on the Lower Elwha Klallam Indian Reservation near Port Angeles, Washington. The project consists of site improvements, water supply and drainage pipelines, water supply wells, two buildings, fish culture facilities including raceways, ponds, and adult holding...
- This federal contract award, with an ID of INP09PC60878|INPT2011101284, was issued by the National Park Service (NPS) to HDR Engineering Inc., a large engineering and environmental consulting firm. The $6,567.30 fixed-price incentive contract is for miscellaneous services associated with the Elwha River Restoration project in Port Angeles, Washington, including meetings and construction proposal review. This work was not set aside for small businesses. HDR Engineering Inc. is the prime...
- This federal contract award was made by the National Office, a civilian agency, to HDR Engineering Inc. (HDR) for recovery and restoration services related to the Elwha River in Washington. The $59,414.54 fixed-price delivery order includes architectural, engineering, and construction management services such as submittal review, request for information (RFI) review, office services, and site visits. The contract is not associated with a set-aside program. HDR, a large, employee-owned...
- <p>This is a federal contract award from the National Office of a civilian agency to Northwest Archaeological Associates Inc. for $12,055.11 to provide archeology services associated with the Griff Creek Culvert Replacement Project on the Lower Elwha Klallam Tribe Reservoir. The contract is a firm fixed price purchase order without a set-aside designation. The services are necessary to limit destruction of natural resources during the project.</p>
- This is a firm-fixed-price purchase order awarded by the National Park Service (part of the Department of the Interior) to Muir Contracting, Inc., an Emerging Small Business, for the repair of in-riverbank rock barbs using NPS-furnished sand and gravel, and contractor-furnished riprap and equipment with operator, including the use of biobased hydraulic fluid. The total ceiling value of the contract is $23,887. The work is to be performed in Stehekin, Washington, and the ultimate completion...
- This is a firm fixed-price definitive contract awarded by the Operations Center East, a civilian agency, to Edwin E. Thoreson, Inc., a self-certified small disadvantaged business. The contract is for the supply and installation of aquatic organism passage structures as part of a Recovery Project funded by the American Recovery and Reinvestment Act (ARRA). The contract has a ceiling value of $245,889.00 and a completion date of September 28, 2010. The contract is not associated with a set-aside...
- This is a firm fixed price delivery order contract awarded by the U.S. Department of the Interior Fish and Wildlife Service to Northern Management Services, Inc., a self-certified HUBZone joint venture, for the repair and replacement of water pumps, motors, and electrical switchgear at the Spring Creek National Fish Hatchery in Underwood, Washington. The contract has a ceiling value of $1,278,588.00 and a completion date of May 30, 2011. This contract is part of the broader Recovery Act (TAS...
This contract was awarded by the National Office of a civilian federal agency for the RECOVERY, TAS:: 14 1041:: RESTORE ELWHA RIVER RCOSYSTEM AND FISHERIES PROGRAM - MAINTAIN WATER QUALITY AT NIPPON PAPER MILL, CONSTRUCT NPI OUTFALL, PHASE 1 project. The fixed-price definitive contract, worth $2,044,402.00, was awarded to Harbor Offshore, Inc. on May 13, 2010 with a completion date of October 11, 2010. The contract did not have a set-aside designation.
Generated 4/2/25, 10:12 AM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 2 | Supplemental Agreement for work within scope | $161.4k | 9/29/10 | |
| 1 | Supplemental Agreement for work within scope | $20.0k | 9/29/10 | |
| Not listed | Not listed | $1.9m | 5/13/10 |