Definitive Contract INP15PC00085
Award Date 1/8/15
Potential Completion Date 6/15/16
Potential Value $8.5M
Federal Agency
Ultimate Awardee
Not listed PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Not Available for Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
New York, NY 10004, USA
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Not listed National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a definitive, firm-fixed-price contract awarded by the National Park Service (NPS), a civilian agency within the Department of the Interior, to Reilly Construction Inc. (doing business as Capitol Roofing), a minority-owned, service-disabled veteran-owned small business. The contract, valued at $432,781.00, is for the design and rehabilitation of the water and wastewater systems on Liberty Island. This contract was awarded as an 8(a) sole-source set-aside and has an ultimate completion...
- The National Park Service Northeast Region awarded a $147,400 definitive contract to Hance Construction for water main repairs at Miller Field, Gateway National Recreation Area, Staten Island, New York, on August 4, 2026, under a total small business set-aside. The awardee is a service-disabled veteran-owned small business. Work comprises replacement of four existing gate valves at meter pits (two 6-inch and two 8-inch), location and repair of a leaking 8-inch water main section, and...
- This is a $5,347,724.25 firm-fixed-price definitive contract awarded by the National Park Service (NPS) to APS Contractors Inc. for the stabilization of the powerhouse on Ellis Island, part of the Statue of Liberty National Monument in New York and New Jersey. The contract, referred to as STLI PMIS #125742, does not have a set-aside designation. The award date was May 4, 2010, with a final completion date of June 27, 2011. As the prime contractor, APS Contractors Inc. is responsible for...
- This is a $1,430,020.84 firm-fixed price contract awarded by the National Park Service to Cutting Edge Group, LLC, a minority-owned small business, to install power and communications infrastructure improvements on Liberty and Ellis Islands. The project consists of installing electrical and communication conduits, wires, and fiber optics, as well as providing a backup power supply, around the historic and culturally sensitive structures on both islands. This contract is part of the National Park...
- The National Park Service (NPS) Northeast Region awarded a $304,462.06 firm-fixed-price bridge contract to C & S Building Services Inc., a small business subchapter S corporation, to provide uninterrupted utility operations and maintenance services at the Statue of Liberty National Monument (STLI) in Jersey City, New Jersey. This 3-month bridge contract was awarded under unusual and compelling urgency due to the need for continued mission-critical support while the follow-on competitive...
- Pullman Sst, Inc., a subsidiary of Structural Group, Inc., was awarded a $26.5 million firm fixed-price contract by the National Park Service on April 14, 2023, to rehabilitate the exterior systems of the Main Immigration Building at Statue of Liberty National Monument on Ellis Island, New York. The contract, designated STLI 312431 and funded through the Civilian branch of the federal government, encompasses a comprehensive restoration effort scheduled for completion by September 26, 2026. The...
- The National Park Service awarded a $14.6 million definitive contract to Blue World Construction Inc. for design-build rehabilitation of potable water distribution and wastewater collection systems at Fort Hancock in the Gateway National Recreation Area, New Jersey, on April 20, 2023. The contract carries firm fixed price terms with an ultimate completion date of October 9, 2026. Blue World Construction Inc. is a self-certified small disadvantaged business. Place of performance is Florham...
- This is a Definitive Contract awarded by the National Park Service, a civilian agency, to Phoenix Marine CO. Inc., a veteran-owned for-profit business, for $19,769,061.60 to perform stabilization work on the Statue of Liberty National Monument seawall on Ellis Island. The work includes installing steel sheet piling and concrete, steel H-piles, soil anchors, concrete beams, and repairing granite masonry. This is a Firm Fixed Price contract with no set-aside designation. The contract has a...
- This federal contract was awarded by the Department of the Interior National Park Service Northeast Region to C & S Building Services Inc., a for-profit small business subchapter S corporation, for the operation and maintenance of utilities at the Statue of Liberty National Monument and Ellis Island in Jersey City, New Jersey. The 5-month bridge contract has a firm-fixed price of $877,996.00. C & S Building Services Inc. has previously held similar utilities operation and maintenance...
- <p>This is a $21,500,000.00 firm fixed price design-build contract between the National Park Service and Jrcruz Corp. to rehabilitate the water, wastewater, and stormwater utility systems at Fort Wadsworth in Staten Island, New York. The contract was awarded on July 22, 2024 and has a completion date of December 20, 2026. The original solicitation was a sources sought notice posted on February 27, 2023 with a due date of March 16, 2023. No set-aside was used for this contract.</p>
REPLACE WATER/SEWER LINES TO LIBERTY ISLAND
Posted 1/8/15
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 3 | Supplemental Agreement for work within scope | $450.3k | 7/24/16 | |
| 2 | Supplemental Agreement for work within scope | $0 | 4/13/16 | |
| 1 | Supplemental Agreement for work within scope | $181.0k | 3/26/16 | |
| Not listed | Not listed | $7.9m | 1/8/15 |