Construct a 40-foot wide fire control line, approximately 29 acres; and thin approximately 103.5 acres of forested area at PEA ridge national military park.

Ended Definitive Contract Awarded Last action

Contract number
INP11PC61356
Awardee
Awarding agency
Obligated
$90,226

Award facts

Opportunity
  • P11PS61094 Solicitation number
Contract value 100% obligated
$90,226.33 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
561730 Landscaping Services
PSC
F014 Natural Resources/Conservation- Tree Thinning
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 8 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Garfield, AR 72732, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope 7 · "other functions" MOD 0007 - no-cost modification to extend completion date to july 31, 2012 due to prolonged and extreme heat conditions. $0
Supplemental Agreement for work within scope 6 · "other functions" MOD 0006 - no-cost modification to extend completion date to july 25, 2012 due to operational and financial hardship through no fault of the… $0
Supplemental Agreement for work within scope 5 · MOD 0005: on or about april 23,2012, one piece of the contractor's equipment caught on fire while performing work at the contract site and was deemed a total… $0
Other Administrative Action 4 · MOD 0004: unilateral modification to make administrative changes to contract for fbms conversion: include start date of 9/22/2011 on lines 0001 thru 0003… $0
Supplemental Agreement for work within scope 3 · MOD 0003: due to circumstances through no fault of the contractor, inclement weather and unsafe ground conditions restricted contractor from completing the work… $0
Supplemental Agreement for work within scope 2 · MOD 0002: BI-lateral no-cost modification. At the request of the contractor, CO extends contractor's working hours from sunrise to 6:00 P.M. Or 30 minutes prior… $0
Supplemental Agreement for work within scope 1 · MOD 0001: due to poor weather conditions and to maintain work progress while ensuring safety to the park's and contractor's personnel, equipment, property,… $0
Original award $90,226

Quick answers

Who was awarded contract INP11PC61356?

INP11PC61356 was awarded to Chris A Maples by Midwest Region (National Park Service) on September 22, 2011.

How much is contract INP11PC61356 worth?

The government has obligated $90,226 on INP11PC61356.

Was contract INP11PC61356 competed?

The extent of competition for INP11PC61356 was full and open competition after exclusion of sources. The government received 8 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award