Close Out
P00046 · MOD 46-incorporate settlement agreement. DE-obligate remaining funds of -($391,982.96) on the construction contract for the driwr VC
-$391,983
Other Administrative Action
P00045 · MOD 45-assess liquidated damages in the amount of -($324,000.00) on the construction contract for the driwr VC.
-$324,000
Supplemental Agreement for work within scope
P00044 · MOD 44-in scope work for addition of drywall control joints on the construction contract for the driwr VC.
$8,690
Supplemental Agreement for work within scope
P00043 · MOD 43-in scope work for a change to the reception desk lights on the construction contract for the driwr VC.
$1,968
Novation Agreement
42 · MOD 42-check the novation button for system purposes only to allow for correct invoicing procedures in IPP as a result of the TOA on the construction contract…
$0
Other Administrative Action
40 · MOD 40-vendor change per takeover agreement executed on 21 july 17 and remove the NOA from this contract per release letter dated 20 july 17 on the construction…
$0
Supplemental Agreement for work within scope
41 · MOD 41-incorporate exhibit c of the TOA and as a result extend the period of performance completion date to 18 NOV 17 on the construction contract for the driwr…
$0
Terminate for Default
39 · MOD 39-termination for default on the construction contract for the driwr VC.
$0
Supplemental Agreement for work within scope
35 · MOD 35-add'l in scope work for soil sampling and soil disposal and POP extension due to this work for the constr. Contract for the driwr VC.
$29,936
Supplemental Agreement for work within scope
36 · MOD 36-add'l in scope work for the naming event on 7 JAN 17 and POP extension due to this work for the constr. Contract for the driwr VC.
$7,643
Supplemental Agreement for work within scope
37 · MOD 37-add'l in scope work for the removal of the chrysler meter PIT and POP extension due to this work for the constr. Contract for the driwr VC.
$10,394
Supplemental Agreement for work within scope
38 · MOD 38-add'l in scope work for the faucet mixing valves and POP extension due to this work for the constr. Contract for the driwr VC.
$957
Supplemental Agreement for work within scope
34 · MOD 34-add'l in scope work for rock removal at the water and sanitary sewer mains and POP extension IAW FWS letter dated 16 FEB 17 for the constr. Contract…
$36,451
Supplemental Agreement for work within scope
32 · MOD 32-HVAC mixing valves for the constr. Contract for the driwr VC.
$7,584
Supplemental Agreement for work within scope
29 · MOD 29-video theater lighting change for the constr. Contract for the driwr VC.
$1,225
Supplemental Agreement for work within scope
30 · MOD 30-interior canopy revisions for the constr. Contract for the driwr VC.
$1,885
Supplemental Agreement for work within scope
33 · MOD 33-chemetal revisions, annunciator, relocate hand dryers, PRT 6 substitute, and pewabic tiles changes for the constr. Contract for the driwr VC.
$4,339
Supplemental Agreement for work within scope
31 · MOD 31-door hardware & electrical revisions for the constr. Contract for the driwr VC.
$8,957
Supplemental Agreement for work within scope
28 · MOD 28-change to 2X8 studs for the constr. Contract for the driwr VC.
$709
Supplemental Agreement for work within scope
27 · MOD 27-replace HVAC return air filters for the constr. Contract for the driwr VC.
$1,515
Supplemental Agreement for work within scope
26 · MOD 26-directional drilling thru limestone for the constr. Contract for the driwr VC.
$69,553
Supplemental Agreement for work within scope
25 · MOD 25-bid additive option #8 for the constr. Contract for the driwr VC.
$52,939
Supplemental Agreement for work within scope
24 · MOD 24-3 bike racks, custom color, and raise stone on columns for the constr. Contract for the driwr VC.
$9,579
Supplemental Agreement for work within scope
23 · MOD 23 add boulder retaining wall to the south side of the bldg. For the constr. Contract for the driwr VC.
$15,343
Supplemental Agreement for work within scope
21 · MOD 21 water line 22 degree bends to avoid pond for the constr. Contract for the driwr VC.
$1,751
Supplemental Agreement for work within scope
20 · MOD 20 geotextile fabric materials and installation at west pond for the constr. Contract for the driwr VC.
$10,793
Supplemental Agreement for work within scope
22 · MOD 22 RE-size two door frames for the constr. Contract for the driwr VC.
$715
Supplemental Agreement for work within scope
19 · MOD 19 H2OTEST, concrete/rebar at MH2/w pond, frac tank and DE-watering related costs, remedial foundation details, DE-OB LHB electrical design for the…
$109,772
Supplemental Agreement for work within scope
18 · MOD 18 for an administrative change to incorporate schedule focus dates for the construction contract for the driwr VC.
$0
Other Administrative Action
17 · MOD 17 for an administrative change to incorporate the notice of assignment for the construction contract for the driwr VC.
$0
Supplemental Agreement for work within scope
16 · MOD 15 for in scope work for changes to the sewer, water and gas lines on the construction contract for the driwr VC.
$221,477
Supplemental Agreement for work within scope
15 · MOD 15 for in scope work for a passive under slab vent system on the construction contract for the driwr VC.
$2,955
Supplemental Agreement for work within scope
13 · MOD 13 for in scope work for price escalation of 3% due to the numerous delays resulting from the unforeseen site conditions on the construction contract for…
$158,398
Supplemental Agreement for work within scope
14 · MOD 14 for in scope work for the storm water changes directed by michigan DEQ on the construction contract for the driwr VC.
$174,570
Supplemental Agreement for work within scope
11 · MOD 11 for in scope work for 1 week add'l heater rental/fuel, differing site conditions by footings, and hazwoper trng for 2 electricians for the construction…
$17,673
Supplemental Agreement for work within scope
12 · MOD 12 for in scope work for the countertop and casework finishes for the construction contract for the driwr VC.
$5,586
Supplemental Agreement for work within scope
10 · MOD 10 for in scope work for the revised entrance road as requested by wayne county for the construction contract for the driwr VC.
$57,839
Supplemental Agreement for work within scope
9 · MOD 9 for in scope work for revised strap footings due to the unforeseen exisiting foundation that was discovered for the construction contract for the driwr…
$8,133
Supplemental Agreement for work within scope
8 · MOD 8 for in scope work due to winter conditions for the construction contract for the driwr VC.
$91,622
Supplemental Agreement for work within scope
7 · MOD 7, for add'l in scope work to pump/haul foundation water, survey basement, 3 foundation test holes, fill e. Pond, and clean frac tank for the construction…
$99,988
Supplemental Agreement for work within scope
6 · MOD 6, for add'l in scope work to backfill the foundation and change the POP accordingly, and a net zero funding change to lines 10 and 90 for the…
$216,177
Supplemental Agreement for work within scope
5 · MOD 5, for add'l in scope work for clean fill to cover the berm and build the retention pond, and for additional water tests for the mdeq DE-watering permit…
$13,950
Supplemental Agreement for work within scope
4 · MOD 4, for add'l in scope work to change the electrical panelboards, remove the fill from the existing foundation (unknown at time of contract award) and…
$175,620
Supplemental Agreement for work within scope
3 · MOD 3, for add'l in scope exploratory work and to incorporate asis 03, 04, 05, 06 and 07, to the construction contract for the visitor center at detroit river…
$18,620
Supplemental Agreement for work within scope
2 · MOD 2, incorporate ASI 01 (revise pond outlet control structure elevations) and ASI 02 (revise stone veneer elevation in SE entrance of building) to the visitor…
$0
Supplemental Agreement for work within scope
1 · MOD 1, for add'l in scope work and to extend the POP to align with the NTP issuance, to a construction contract for visitor center at detroit river IWR
$311,350
Original award
$4,968,575
Show all 47
Quick answers
Who was awarded contract INF13PC00229?
INF13PC00229 was awarded to Western Surety Company by DOI Fish and Wildlife Service Region 3 (Fish and Wildlife Service) on September 17, 2013.
How much is contract INF13PC00229 worth?
The government has obligated $6,219,248 on INF13PC00229.
Was contract INF13PC00229 competed?
The extent of competition for INF13PC00229 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Total Small Business.