Construction of utilities for the corn creek field station future visitor center

Ended Definitive Contract Awarded Last action

Contract number
INF11PC00025
Awardee
Awarding agency
Obligated
$1,314,198

Award facts

Opportunity
Contract value 100% obligated
$1,314,198.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237110 Water and Sewer Line and Related Structures Construction
PSC
Not on record
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Las Vegas, NV, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order 13 · Corn creek site utilities construct $7,716
Change Order 12 · Adds funds for the 6" collar pipe for the site utilities at corn creek NWR $1,381
Other Administrative Action 10 · Admin MOD for fbms conversion $0
Other Administrative Action 9 · Administrative modification to correct contract completion date. No increase in total contact price. $0
Supplemental Agreement for work within scope 8 · Supplemental agreement for work within scope. Total price increase of $48,879.00. New contract total: $1,305,101.00. $48,879
Supplemental Agreement for work within scope 7 · Supplemtnal agreement and change order to relocate telephone switch gear and for requirement by the telecommunications providor for additional telecom lengths… $17,752
Supplemental Agreement for work within scope 6 · Supplemental agreement for work within scope. Expansion of existing leach field installed by the contractor to support future peak visitor flows at the proposed… $50,693
Supplemental Agreement for work within scope 5 · Combination of change order and supplemental agreement for additional work within scope. Change order for supply and installation of plants at constructed… $12,999
Supplemental Agreement for work within scope 4 · Modification to specificaitons resulted in an increased cost incurred by the contractor. Additional work is within the general scope of the contract and is… $77,426
Supplemental Agreement for work within scope 3 · Modification for changes to water line and electrical lines near the service building and for removal of the old existing septic tank at the project site. $54,948
Change Order 2 · Modificaiton to existing contract. Change order issued by the government for RE-alignment of sewer lines in the amount of $17,182.00 $17,182
Supplemental Agreement for work within scope 1 · Supplemental agreement for revisions to work related to a waste filtration system $33,262
Original award $991,960
Show all 13

Quick answers

Who was awarded contract INF11PC00025?

INF11PC00025 was awarded to JBM Construction, Inc. by DOI Fish and Wildlife Service Region 1 (Fish and Wildlife Service) on October 22, 2010.

How much is contract INF11PC00025 worth?

The government has obligated $1,314,198 on INF11PC00025.

Was contract INF11PC00025 competed?

The extent of competition for INF11PC00025 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award