New construction of visitor contact station, administrative headquarters, and service building for the SAN diego national wildlife refuge complex, chula vista, CA.

Ended Definitive Contract Awarded Last action

Contract number
INF10PC76719
Awardee
Awarding agency
Obligated
$4,823,606

Award facts

Opportunity
  • 80181RR220 Solicitation number
Contract value 100% obligated
$4,823,605.84 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Chula Vista, CA 91910, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change PIID 13A $0
Other Administrative Action 13 · Recovery project # R8AA construction SAN diego nwrc visitor center. Administrative MOD for migration to new financial and procurement system - fbms. $0
Change Order 12 · Recovery TAS::14 1613:: FWS accepted change order proposal of construction contractor for SAN diego nwrc visitor center $0
Change Order 11 · Change order. No change in total contract price. $0
Supplemental Agreement for work within scope 10 · Supplemental agreement to modify concrete support structures for future interpretive displays. Contract price does not change. Adjustment to residual credit… $0
Supplemental Agreement for work within scope 9 · Modification to accept contractors proposal(S) for sink changes and access panels. Substantial completion date extends by 13 additional calendar days. No change… $0
Other Administrative Action 8 · Administrative modification to correct clerical error within MOD007. No change in total contract price or terms and conditions. Total price remains at… $0
Supplemental Agreement for work within scope 7 · Change order to accept contractors proposal for a bench and concrete entrance adjsutment at the visitor center building. Total amount of the contract remains… $0
Change Order 6 · Modification to issues change order for lighting flange kits. No change in total olbigation of contract. $0
Change Order 5 · Modification issued to accept contractors proposal for electrical service to the service building and for alternate counter tops in room #210 of the building.… $0
Change Order 4 · Change order for work within scope. $0
Change Order 3 · Change order within scope $0
Change Order 2 · Change order issued to accept contractors proposals for changes required to provide wastewater treatment alarms/monitoring, incorporate a new 4" riserthe… $0
Supplemental Agreement for work within scope 1 · Supplemental agreement for work within scope and for sttelement of changed conditions. $257,860
Original award $4,565,746
Show all 15

About this award

This is a federal contract awarded by the U.S. Department of the Interior (DOI) Fish and Wildlife Service Region 1 to PCL Construction Services, Inc. for the new construction of a visitor contact station, administrative headquarters, and service building for the San Diego National Wildlife Refuge Complex in Chula Vista, California. The contract is a definitive, firm-fixed price contract with a ceiling value of $4,823,605.84 and a completion date of October 31, 2011. The contract does not have a set-aside designation. PCL Construction Services, Inc. is the prime contractor for this project.

Quick answers

Who was awarded contract INF10PC76719?

INF10PC76719 was awarded to PCL Construction Services, Inc. by DOI Fish and Wildlife Service Region 1 (Fish and Wildlife Service) on May 26, 2010.

How much is contract INF10PC76719 worth?

The government has obligated $4,823,606 on INF10PC76719.

Was contract INF10PC76719 competed?

The extent of competition for INF10PC76719 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award