Design-build of central utility plant expansion (CUP2), ST elizabeths west campus, SE, wash., DC

Ended Definitive Contract Awarded Last action

Contract number
GS11P17MMC0002
Awardee
Awarding agency
Obligated
$79,385,175

Award facts

Contract value 100% obligated
$79,385,175.00 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20032, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA40 · To change the contracting officer assigned bonnie echoles to marquida gaskins ( $0
Supplemental Agreement for work within scope PS37 · Credit for errors discovered in prior executed and approved pricing proposals. -$100,017
Change Order PS36 · Provide a credit of MSI (west addition, bldg 37) funds remaining on the contract -$47,732
Supplemental Agreement for work within scope PS35 · Provide labor, materials supervision and equipment to complete the requirement for shoring. Inclusion of heavy labor category. $60,992
Supplemental Agreement for work within scope PS34 · Compensation for cancelled coop exercise $35,000
Supplemental Agreement for work within scope PS33 · Section 889 $0
Supplemental Agreement for work within scope PS32 · CE 0640 MSI schedule delay impacts RCO127R1, CE 0696 smokestack monitoring RCO139 and CE 0712 contaminated soil removal RCO0712 $206,200
Change Order PS31 · Credit for work completed by gdit related to installation of a sliding gate in the temporary v fence, credit for half of the cost of guard services during… -$24,829
Supplemental Agreement for work within scope PS30 · Generator delays and manhole examination $63,619
Other Administrative Action PA29 · POP extension only for the completion of 2.5MW and 3.5MW generator paralleling gear programming and ATS start signal scope, as awarded. $0
Change Order PS28 · Contaminated soil removal $161,642
Other Administrative Action PA27 · Correct building numbers and accounting on clins 44 to 47 $0
Supplemental Agreement for work within scope PS26 · Provide labor, materials, supervision for additional equipment, initial urea and fuel oil fill, automatic transfer scheme for unit substations, DOC a… $1,451,253
Supplemental Agreement for work within scope PS25 · Contractor to provide all labor, materials, and equipment to remove 2627.17 cubic yards of contaminated soils from the project site for delivery to an… $290,118
Other Administrative Action AA24 · Contract no GS-11-p-17-MM-c-0002 central utility plant (cup 2) no cost admin MOD AA24 for extension of services to 08/19/1019. Effective with this… $0
Other Administrative Action PA23 · The purpose for the mass MOD is to change the current local billing office address to the new designated billing office address of bcfa. Approval of the mass… $0
Supplemental Agreement for work within scope PS22 · GS-11-p-17-MM-c-0002 , DB of central utility plant expansion CUP2, ST elizabeths west campus, SE, wash., DC MOD PS22 various CES and credits the contractor's… $731,661
Supplemental Agreement for work within scope PS21 · Contract no. GS-11-p-17-MM-c-0002 central utility plant 2 (CUP2) MOD PS21 - contaminated soil the contractor's signature in block 15B indicates his agreement to… $83,402
Change Order PS20 $364,678
Change Order PC19 $1,176,464
Change Order PC18 $4,574,181
Change Order PC17 · Contract number- GS-11-p-17-MM-c-0002, CUP2, ST elizabeths west campus, SE, wash., DC unilateral directive MOD PC17: removal of contaminated soils NTE… $2,209,719
Change Order PC16 · CO directive for revised design for space between CUP2 and building 56.57 and contaminated soils disposal $741,588
Other Administrative Action PO15 · Directive letter: provide heating and cooling to the center building, per base contract documents $0
Change Order PC14 · Four additional heat exchangers $2,056,060
Change Order PS13 · To provide various scope additions campus loop separation schematic design contaminated soils soil testing additional title v permit expediting $946,435
Change Order PS12 · Contaminated soil removal $977,087
Supplemental Agreement for work within scope PS11 · To provide campus loop separation- DOC a design costs, misc CES $810,912
Change Order PC09 · PDL NTE $90,000.00 to provide design work to complete the heat exchanger design option in order to separate the DOC a building from the campus loops $90,000
Supplemental Agreement for work within scope PS08 · MUP/MSI credit to c-0041 center building MSI costs and other various scope additions $377,932
Supplemental Agreement for work within scope PS07 · MOD PS07 to provide all labor, supervision, material, and equipment for an additional cooling tower including associated piping startup and commissioning… $572,129
Supplemental Agreement for work within scope PS06 · MOD PS06 to provide all labor, supervision, material, and equipment to provide 3.5MW generators inside the CUP2 in lieu of the 3MW generators as an add to the… $1,726,125
Supplemental Agreement for work within scope PS05 · Upgrade 2 hurst water fire tube boilers in ultra low NOX (9 PPM)gas #2 oil modal UCM600-go-30 burners $178,460
Other Administrative Action PA04 · Correction of function code $0
Exercise an Option PS03 · Master system integrator for the campus building management system (BMS) - option 4 $1,395,000
Funding Only Action PA02 · Reob base contract funds $4,185,678
Funding Only Action PA01 · Funding action only - deobligation of construction funds -$4,185,678
Original award $58,277,096
Show all 38

About this award

This is a $79,385,175.00 firm fixed price design-build contract awarded by the National Capital Region of the General Services Administration (GSA) to Balfour Beatty Construction, LLC for the design and construction of a central utility plant expansion at the St. Elizabeths West Campus in Washington, D.C. The contract does not have a set-aside designation, indicating it was competitively awarded on an unrestricted basis. Balfour Beatty Construction is a foreign-owned, for-profit construction company that holds several Indefinite Delivery/Indefinite Quantity (IDIQ) contracts with federal agencies, including the U.S. Army Corps of Engineers and Naval Facilities Engineering Command, for construction and renovation services at military installations. This contract supports the GSA's facilities management and construction program, as the agency oversees the development and operations of federal buildings and properties.

Quick answers

Who was awarded contract GS11P17MMC0002?

GS11P17MMC0002 was awarded to Balfour Beatty Construction, LLC by National Capital Region (Public Buildings Service) on December 6, 2016.

How much is contract GS11P17MMC0002 worth?

The government has obligated $79,385,175 on GS11P17MMC0002.

Was contract GS11P17MMC0002 competed?

The extent of competition for GS11P17MMC0002 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award