Professional design services for the modernization of the lafayette building, wash., DC

Ended Definitive Contract Awarded Last action

Contract number
GS11P05MKC0061
Awardee
Awarding agency
Obligated
$13,816,354

Award facts

Contract value 100% obligated
$13,816,353.74 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541310 Architectural Services
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20407, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out PA91 · Contractor: dmjm/aecom project: a/E professional design services for the lafayette modernization, located in washington DC [DC0020ZZ]. Modification PA91: this… -$1,154
Supplemental Agreement for work within scope PS90 · Modification PS90: contract number GS-11P-05-MKC-0061 for a/E services for the VA tenant improvement at the lafayette building 811 vermont AVE NW washington… $0
Other Administrative Action PA89 · This administrative modification hereby transfers this contract from: contracting officer, mary E. Pineda to: contracting officer, bonnie E. Echoles, office… $0
Supplemental Agreement for work within scope PS88 · Modification PS88: contract number: GS-11P-05-MKC-0061 for a/E services for the VA tenant improvement at the lafayette building, 811 vermont AVE NW washington… $0
Supplemental Agreement for work within scope PS87 · The purpose of this modification is to extend the contract's POP to august 31, 2018. $0
Supplemental Agreement for work within scope PS86 · This modification adds: clin 0103 as an addition to the contract in the amount of $37,880.00 for additional design services for replacement of dry cooler crac… $37,880
Supplemental Agreement for work within scope PS85 · Modification PS85 adds clin 0102 for a/E design of crac unit systems. No extension to the POP. $48,344
Supplemental Agreement for work within scope PS84 · Modification PS84 extends the POP to february 28, 2018 to provide additional a/E services for the VA tenant fit-out at the lafayette building. $0
Supplemental Agreement for work within scope PS83 · Modification PS83 increases the contract by $75,762.00 for aecom to provide AE services for the pccs building manager and health unit fit out. $75,762
Supplemental Agreement for work within scope PS82 · Modification PS82 increases the contract by $31,663.00 for aecom to make adjustments to the VA TI design. The period of performance remains unchanged. $31,663
Supplemental Agreement for work within scope PS81 · Modification PS81 increases the contract by $15,986.00 for aecom to provide concept design for 1ST floor studio changes. The POP remains unchanged. $15,986
Supplemental Agreement for work within scope PS80 · MOD PS80 for AE professional design services for the modernization of lafayette building, washington, DC original csuite PR WPC-05-0326 for $51,586.00 POP… $51,586
Supplemental Agreement for work within scope PS79 · Modification PS79 to provide post construction contract service (PCCS) for VA tenant improvement service to include attendance at meeting, RFI and submittal ,… $417,772
Supplemental Agreement for work within scope PS78 · The purpose of this modification is to provide MER sump pump for the lafayette modernization project. $15,222
Supplemental Agreement for work within scope PS77 · Arra funded MOD: AE professional design services for the modernization of lafayette building, washington, DC: deobligate remaining arra funding. All… -$4,329
Other Administrative Action PA76 · Transfer of contracting office authority $0
Supplemental Agreement for work within scope PS74 · Arra aecom PS74 phase 1 PCCS REA (value = $57,932). PS47 exercised post construction contract services (PCCS) for phases 3A, 3B and 4. The purpose of this… $57,832
Supplemental Agreement for work within scope PS75 · Update health unit design the purpose of this change is to refresh the health unit design for the at the lafayette building. Phase 2 of the project was… $87,136
Supplemental Agreement for work within scope PS73 · Update package 3 CDS to incorporate the CFA and ncpc approved streetscape design $161,574
Supplemental Agreement for work within scope PS72 · Additional site visits during phase 2 $404,607
Funding Only Action PA71 · RWA B0903440 for $273,437.00 issued under PS33 - line item 0037 to provide additional design for the furnishings for the exim swing as well as final spaces is… -$5,426
Supplemental Agreement for work within scope PS70 · Provide supporting documents to obtain the DC water permit. $16,637
Other Administrative Action PA69 $0
Exercise an Option PO68 · Exercise options 2C, 2D and 3A. $397,019
Supplemental Agreement for work within scope PS67 · This modification is to add funding to the lafayette building modernization project in washington, DC. $47,135
Supplemental Agreement for work within scope PS66 · Contract modification to perform additional a/E design services for the lafayette building renovation project in washington, DC. $19,991
Supplemental Agreement for work within scope PS63 · Contract modification for additional a/E design services for the lafayette project in washington, DC. $18,068
Supplemental Agreement for work within scope PS64 · Exim proposed kitchen and pantry area changes. $17,835
Supplemental Agreement for work within scope PS65 · Exim - RE-purpose circuits $15,365
Other Administrative Action PA62 · Transfer of MOD from MM to DAC. $0
Supplemental Agreement for work within scope PS61 · Exim floors 8-12 additional electrical power elements and partitions $18,148
Supplemental Agreement for work within scope PS60 · Additional power and data requirements $36,728
Supplemental Agreement for work within scope PS57 · Exim final space $33,666
Supplemental Agreement for work within scope PS59 · Invoice purposes only $0
Supplemental Agreement for work within scope PS58 · Realign work - no change to line items appropriation numbers. $0
Supplemental Agreement for work within scope PS56 · VA final tenant improvement design $1,050,080
Supplemental Agreement for work within scope PS55 · Realignment of PS46 obligated funds - allowances $0
Supplemental Agreement for work within scope PS54 · Realignment of PS45 obligated funds - allowances $0
Supplemental Agreement for work within scope PS52 · Study for the design of tenant improvements for the VA portion. $56,716
Other Administrative Action PA53 · DC0026ZZ - lafayette : change CO authority to michele mailhot $0
Other Administrative Action PA51 · Contracting officer authority is transferred from: chrischanda S. Smith contracting officer general services administration/NCR 301 7TH ST., SW washington, DC… $0
Change Order PC50 · Recovery act contract is modified to include additional man hours for the design services for phase 1 and phase 2 of the lafayette building modernization. $249,812
Other Administrative Action PA49 · Recovery act this modification is for comprizon purpose only to correct a comprizon/pegasus variance. -$224,064
Other Administrative Action PA48 · Contract is modified to transfer contracting officer authority from vincent E. Matner, contracting officer to chrischanda S. Smith, contracting officer. $0
Supplemental Agreement for work within scope PS46 · Recovery act contract is modified to add supplemental a/E services for phase 1 construction. $508,796
Supplemental Agreement for work within scope PS47 · Recovery act the purpose of this modification is to provide equitable adjustment to option 2 pricing. $397,018
Supplemental Agreement for work within scope PS45 · Recovery act contract is modified to include additional post construction support services and site visits for phase 1 construction. $443,936
Supplemental Agreement for work within scope PS43 · Contract is modified to provide equitable adjustment for additional cost estimating services for the 95% design submission which resulted due to a change in… $61,004
Supplemental Agreement for work within scope PS44 · Contract is modified to add design services to provide specification sections for the new security components for the lafayette buidlling. $66,138
Supplemental Agreement for work within scope PS42 · TAS:47 4543::TAS contract is modified to add design services to split contract options 2 and 3 for possible inclusion into phase 1 construction duration per… $64,156
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This contract was awarded by the National Capital Region (NCR) division of the General Services Administration (GSA) to a joint venture between DMJM Design and McClier for professional design services to modernize the Lafayette Building in Washington, D.C. The $13,816,353.74 firm-fixed-price contract has a completion date of March 29, 2019 and was not set aside for any specific business type. As a civilian agency contract, this project likely supports the GSA's mission to manage and maintain federal properties and facilities.

Quick answers

Who was awarded contract GS11P05MKC0061?

GS11P05MKC0061 was awarded to Dmjm Design / Mcclier, A Joint Venture by National Capital Region (Public Buildings Service) on June 10, 2005.

How much is contract GS11P05MKC0061 worth?

The government has obligated $13,816,354 on GS11P05MKC0061.

Was contract GS11P05MKC0061 competed?

The extent of competition for GS11P05MKC0061 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award