Base contract - survey, studies and concepts.

Ended Definitive Contract Awarded Last action

Contract number
GS11P02MQC0041
Awardee
Awarding agency
Obligated
$11,477,189

Award facts

Contract value 100% obligated
$11,477,188.64 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541310 Architectural Services
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20407, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PA64 · Arra funded: correct accounting classification fund code $0
Supplemental Agreement for work within scope PS62 · Arra project: contract modification to return unused arra funds -$2,494
Other Administrative Action PA63 · This MOD transfer the contract from vince matner to mary pineda as the contracting officer $0
Other Administrative Action PA62 · This administrative modification hereby transfers this contract from: contracting officer, mary E. Pineda to: contracting officer, vince E. Matner, office of… $0
Supplemental Agreement for work within scope PS61 · The purpose of this modification is to provide additional funding for archaeological investigation of site and hpgb geothermal wells borings $3,497
Supplemental Agreement for work within scope PS60 · Provide a full structural analysis of the roof to support photovoltaic array / inverters in accordance with CE57 $2,852
Supplemental Agreement for work within scope PS59 · The purpose of this modification is to provide for green building certification institute design credits in accordance with CE56.1. $14,000
Other Administrative Action PA58 · Admin modification to correct accounting strings. $0
Supplemental Agreement for work within scope PS57 · The purpose of this modification is to provide for CE#44.2, additional a/E services that were not included in the original site work concept. The services… $83,870
Supplemental Agreement for work within scope PS56 · This modification is to provide for the definitization of PC48, BBG generator relocation study, at a settled cost of $80,000.00. $20,000
Change Order PC58 · Provide architectural and MEP design changes and coordination for the work room and press rooom for the PTT. $37,000
Supplemental Agreement for work within scope PS55 · The purpose of this modification is to provide additional design services for 7TH floor high roof skylight motorized shading devices in accordance to hntb's… $4,219
Supplemental Agreement for work within scope PS53 · This modification provides for design services, engineering CA services, and a reimbursable allowance for areas to be occupied by PTT, PIC, and afic in the mary… $300,000
Supplemental Agreement for work within scope PS52 · This modification is being executed for hntb(and their subs) to provide space planning services for area to be occupied by PTT, PIC, and afic in accordance to… $562,336
Supplemental Agreement for work within scope PS51 · The purpose of this modification is to provide labor, materials, and supplies in for CE 49.3, archaeological investigation and studies, in support of the mary… $26,830
Change Order PC50 · The purpose of this modification is to provide labor, materials, and equipment for GEO-archeological services in support of the mary E. Switzer modernization. $60,829
Other Administrative Action PA49 · This modification is to correct an accounting string with an error awarded in a previous modification to this contract. $0
Change Order PC48 · This modification is to provide for all labor, materials and equitment for the BBG generator relocation study on the switzer project. $60,000
Supplemental Agreement for work within scope PS47 · This modification is to provide labor, material, and supplies for design servives of tenant UPS system in support of the mary E. Switzer modernization project $8,000
Supplemental Agreement for work within scope PS45 · This modification provides labor, materials, and supplies for CE45, design services for propposed doed tenant changes in support of the mary E. Switzer… $360,000
Other Administrative Action PA46 · Correction of obligated funding for PS27 modification $0
Supplemental Agreement for work within scope PS44 · "recovery" this arra funded modification to contract is to definitize MOD PC43, in accordance with CE#44 for additional design services and project coordination… $325,000
Change Order PC43 · "recovery" this arra funded modification to contract is to provide for additional design services and project coordination for the 3RD & C street site… $500,000
Supplemental Agreement for work within scope PS42 · Recovery* this modification is to incorporate language into line item 0035 of this contract. Hntb shall not be allowed to invoice for any work under line item… $0
Other Administrative Action PA41 · MOD PA41 corrects the project number in the previous MOD PS40. $0
Supplemental Agreement for work within scope PS40 · Recovery* this is a recovery act MOD to add funding for the AE design services for phase 2 for the mary E. Switzer modernization. $1,700,000
Supplemental Agreement for work within scope PS39 · Incorporate arra clauses into contract since they will be issued tasking under recovery funding for phase 2 under a separate MOD. Period of performance is… $0
Supplemental Agreement for work within scope PS37 · PS37 is for the "lessons learned" in phase 1. $58,985
Supplemental Agreement for work within scope PS38 · PS38 is for the additional design services for the IBB tenant space on the 1ST floor. $42,345
Other Administrative Action PA36 · PA36 corrected an incorrect funding code in PS30. $0
Other Administrative Action PA35 · PA35 changed the senior project manager on the project and included new contact information. $0 cost. $0
Other Administrative Action PA34 · Adminimstrative MOD to change the act number as required by finance. This is for the mary E. Switzer modernization project. $0
Other Administrative Action PA32 · Change pdocno from PJ9N01559 to 1B3N0312 $0
Other Administrative Action PA31 · Changing CO's $0
Supplemental Agreement for work within scope PS30 · DOE test fits for switzer building $56,909
Other Administrative Action PA29 $0
Supplemental Agreement for work within scope PS28 $29,097
Supplemental Agreement for work within scope PS27 $42,909
Change Order PC25 $50,000
Change Order PC26 $25,000
Supplemental Agreement for work within scope PA24 $0
Change Order PC23 $30,000
Supplemental Agreement for work within scope PS22 $18,800
Change Order PC19 $122,632
Other Administrative Action PO20 $215,021
Other Administrative Action PA21 $0
Supplemental Agreement for work within scope PS18 $12,662
Supplemental Agreement for work within scope PS16 $391,532
Supplemental Agreement for work within scope PS17 $49,637
Supplemental Agreement for work within scope PS15 $28,121
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a federal contract award to HNTB District of Columbia Architecture, P.C., a subchapter S corporation, by the National Capital Region of the General Services Administration (GSA). The contract is for "Survey, Studies and Concepts" with a ceiling value of $11,477,188.64 and a definitive contract type with firm fixed pricing. The contract was awarded on October 1, 2003 with a completion date of October 30, 2015. The contract does not have a set-aside designation. HNTB District of Columbia Architecture, P.C. is a child company of the parent company HNTB Holdings LTD, which has been awarded other federal contract vehicles.

Quick answers

Who was awarded contract GS11P02MQC0041?

GS11P02MQC0041 was awarded to Hntb District Of Columbia Architecture, P.C. by National Capital Region (Public Buildings Service) on October 1, 2003.

How much is contract GS11P02MQC0041 worth?

The government has obligated $11,477,189 on GS11P02MQC0041.

Was contract GS11P02MQC0041 competed?

The extent of competition for GS11P02MQC0041 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities