This contract is being issued for construction services for the 450GG USACE tenant improvement project on the 4TH and 6TH floors located at the phillip j burton federal building and U.S. Courthouse in…

Ended Definitive Contract Awarded Last action

Contract number
GS09P17KTC0009
Awardee
Awarding agency
Obligated
$12,634,990

Award facts

Contract value 100% obligated
$12,634,990.17 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
San Francisco, CA 94102, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS30 · This modification is being issued for the attached RFP 089 for the USACE tenant improvement project located at the phillip j burton federal building and U.S.… $7,251
Supplemental Agreement for work within scope PS29 · This modification is being issued for the attached RFP 088 for the USACE tenant improvement project located at the phillip j burton federal building and U.S.… $28,171
Supplemental Agreement for work within scope PS28 · This modification is being issued for the attached RFP 086 and RFP 087 for the USACE tenant improvement project located at the phillip j burton federal building… $68,786
Supplemental Agreement for work within scope PS27 · This modification is being issued for the attached RFP 85.2 for the USACE tenant improvement project located at the phillip j burton federal building and U.S.… $64,645
Supplemental Agreement for work within scope PS26 · This modification is being issued for the attached RFP 71.1, 083, and 084 for the USACE tenant improvement project located at the phillip j burton federal… $26,401
Supplemental Agreement for work within scope PS25 · This modification is being issued for the attached RFP 078, 079, 080, 081, and 082 for the USACE tenant improvement project located at the phillip j burton… $61,494
Supplemental Agreement for work within scope PS24 · This modification is being issued for design, submittal, and installation of fire alarm speaker devices at all rooms designated at bid time as private offices… $113,181
Supplemental Agreement for work within scope PS23 · This modification is being issued for RFP 075 for the tenant improvement project at 450GG AVE in SAN francisco, california. $2,902
Supplemental Agreement for work within scope PS22 · This modification is being issued for RFP 036 for the USACE TI project at 450GG located in SAN francisco, california. $55,326
Supplemental Agreement for work within scope PS21 · This modification is being issued for RFP 065 and 073 for the 450GG USACE tenant improvement project in SAN francisco, california. $6,100
Supplemental Agreement for work within scope PS20 · This modification was issued for various changes to the USACE TI project at 450GG AVE in SAN francisco, CA $24,915
Supplemental Agreement for work within scope PS19 · This modification is being issued to exercise the option on the attached RFP 062 for the USACE tenant improvement project located at the phillip j burton… $600
Supplemental Agreement for work within scope PS18 · This modification is being issued to provide for miscellanious rfps for the USACE TI project at 450 golden gate avenue in SAN francisco, california $12,460
Supplemental Agreement for work within scope PS17 · This modification has been issued to provide various small changes to the USACE tenant improvement project at the phillip j burton federal building and U.S.… $33,503
Supplemental Agreement for work within scope PS16 · This modification is being issued for various small changes for the 450GG USACE TI project in SAN francisco, california. $7,769
Supplemental Agreement for work within scope PS15 · This modification was issued to provide for various changes and additions to the USACE TI project at the 450GG federal building and US courthouse in SAN… $50,958
Supplemental Agreement for work within scope PS14 · This modification is being issued to provide services for RFP 045 and RFP052 for the tenant improvement project located at the phillip j burton federal building… $45,076
Supplemental Agreement for work within scope PS13 · This modification is being issued to provide services for rfps 024, 032, 038, 041, 046, and 050 for the USACE TI project at the phillip j burton federal… $102,988
Supplemental Agreement for work within scope PS12 · This modification is being issued to provide various changes to the USACE TI project at the 450GG federal building in SAN francisco, CA $17,418
Supplemental Agreement for work within scope PS11 · Supply and install windows in these openings; including removing the sheetrock, two piece window frames with profile to match existing welded door jambs,… $32,294
Supplemental Agreement for work within scope PS09 · This modification is being issued to provide floor prep service beyond the standard service due to recently discovered deteriorated conditions below carpet $6,506
Supplemental Agreement for work within scope PS08 · This modification was issued to provide for the following changes: clin 0022 6TH FL - RFP 011 wireless access points $860.69 clin 0023 6TH FL - RFP 020 bulletin… $72,525
Supplemental Agreement for work within scope PS07 · The modification is being issued for RFP005, 013,022,027, and 031 for the USACE TI project located at phillip j burton federal building and U.S. Courthouse in… $127,065
Supplemental Agreement for work within scope PS06 · This modification is being issued for the RFP12, 14-18 for the 450GG USACE TI construction project at the phillip j burton federal building and U.S. Courthouse. $89,359
Definitize Change Order PS05 · This modification was issued to definitize PS02 -$4,217
Supplemental Agreement for work within scope PS04 · This modification is being issued for RFP007 through RFP010 for the 450 golden gate tenant improvement project in SAN francisco, CA. $124,897
Supplemental Agreement for work within scope PS03 · This modification is being issued for the attached RFP CE-004 for the removal of the column and beam and RFP CE-006 to relocate 4 electrical panels on the 6TH… $48,869
Supplemental Agreement for work within scope PS02 · In USACE district 4TH floor TI area, remove carpet tile and base of demolished walls and encapsulate, to include activities as described in trico proposed… $237,000
Supplemental Agreement for work within scope PS01 · This modification is being issued to include the 6TH floor west ACM remediation per the attached trico construction proposal COR no: 2R2.1 dated 8/8/2017… $149,159
Original award $11,021,589
Show all 30

About this award

This is a $12,634,990.17 firm fixed-price construction contract awarded by the General Services Administration (GSA) Public Buildings Service Region 9 to Galliera, Inc., a woman-owned small business. The contract is for tenant improvement work on the 4th and 6th floors of the Phillip J. Burton Federal Building and U.S. Courthouse in San Francisco, California. The contract has a completion date of May 31, 2019. Galliera, Inc. has experience as a prime contractor on federal construction, maintenance, and repair projects for various agencies, including the National Labor Relations Board, Department of Agriculture Food and Nutrition Service, and the GSA. This contract is set aside for small businesses.

Description

This contract is being issued for construction services for the 450GG USACE tenant improvement project on the 4TH and 6TH floors located at the phillip j burton federal building and U.S. Courthouse in SAN francisco, california.

Quick answers

Who was awarded contract GS09P17KTC0009?

GS09P17KTC0009 was awarded to Galliera, Inc. by Region 9 (Public Buildings Service) on June 12, 2017.

How much is contract GS09P17KTC0009 worth?

The government has obligated $12,634,990 on GS09P17KTC0009.

Was contract GS09P17KTC0009 competed?

The extent of competition for GS09P17KTC0009 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award