Design build contract for the repair and alteration, tenant improvements for the roybal federal building and courthouse.

Ended Definitive Contract Awarded Last action

Contract number
GS09P16KTC7017
Awardee
Awarding agency
Obligated
$18,798,798

Award facts

Opportunity
Contract value 100% obligated
$18,798,797.77 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Los Angeles, CA 90012, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS50 · This bilateral firm-fixed price modification is issued to definitize PC47 for $11,960.88 for all the labor, time, equipment, material, and cost for the requests… $0
Supplemental Agreement for work within scope PS49 $0
Supplemental Agreement for work within scope PS48 · This bilateral, no-cost modification is to extend the contract completion date to november 30, 2018. This modification provides a full equitable adjustment… $0
Change Order PC47 · This unilateral modification is issued to provide an equitable adjustment for: 1) the request for equitable adjustment submitted on july 17, 2018 for "edward… $11,961
Supplemental Agreement for work within scope PS46 · This bilateral firm-fixed price modification is for all the labor, material, equipment, cost, and time for two days' of general conditions for work associated… $2,911
Supplemental Agreement for work within scope PS45 -$44,690
Supplemental Agreement for work within scope PS44 · This bilateral firm-fixed price modification is for all the labor, equipment, material, cost, and time for the contractor to provide a power supply for the… $1,975
Supplemental Agreement for work within scope PS43 · This bilateral firm-fixed price modification is for all the labor, materials, equipment, time, and cost for the contractor to replace fan coil units as… $29,746
Supplemental Agreement for work within scope PS42 · This bilateral, firm-fixed price modification is for all the labor, equipment, materials, cost, and time for the contractor to provide cabling for voice/data… $16,141
Supplemental Agreement for work within scope PS41 · Alteration to reception area countertop at the edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA $3,331
Supplemental Agreement for work within scope PS40 · Dumpster fees, wallpaper replacement, and differing site conditions at the edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA. -$41,290
Supplemental Agreement for work within scope PS39 · Tenant improvements, restroom acoustic panels, new door and frame, demountable partitions modifications, revision of locksets, and relocation of floor light… $589,330
Change Order PC38 · Differing site conditions allowance for phase 5 of the design build prospectus project at the edward R. Roybal federal building and U.S. Courthouse. $50,000
Supplemental Agreement for work within scope PS37 · Door closure and hardware for the edward R. Roybal federal building and courthouse in LOS angeles, CA $3,201
Change Order PC36 · Contract extension for the design build contract at the edward R. Roybal federal building and courthouse in LOS angeles, CA $32,275
Supplemental Agreement for work within scope PS35 · Cabling, window film, signage and door hardware for the edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA $25,773
Supplemental Agreement for work within scope PS34 · Wall framing modifications and additional data lines on level 9 of the edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA $15,596
Change Order PC33 · Restroom sound panels, finishes modifications, new door and frame for edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA $282,712
Supplemental Agreement for work within scope PS32 · Relocate keypad, relocate floor cores, data closets ceiling work, replace mirror, paint doors and frames, electrical metering, and cabling at the edward R.… $41,705
Supplemental Agreement for work within scope PS31 · Differing site conditions and fire sprinkler line bracing for the edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA -$42,618
Change Order PC30 · IGE::E additional and relocated exit signs on levels 6, 9, 11 at the edward R. Roybal federal building and U.S. Courthouse. $6,000
Supplemental Agreement for work within scope PS29 · Fill in flooring GAP; install suspended ceilings, aluminum trim, electric hardware, and locksets; patch and paint outlets; relocate thermostats; remove… $59,493
Supplemental Agreement for work within scope PS28 · Power and data supplies and outlets, new door, window shades, HVAC controllers, electrical boxes, removal and reinstallation of furniture, and modify wall… $129,796
Supplemental Agreement for work within scope PS27 · IT/data pathways, core cylinders for doors, counter backsplash, seismic sprinkler line bracing, installation of electrical floor boxes, and plumbing changes for… $58,803
Change Order PC26 · Allowance for differing site conditions for the phase 4 of construction at the edward R. Roybal federal building and U.S. Courthouse $75,000
Change Order PC25 · Electrical floor boxes for the edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA $11,000
Supplemental Agreement for work within scope PS24 · Finishes, electrical changes, storage closet, bathroom upgrades, and credits for deleted scope for the edward R. Roybal federal building and U.S. Courthouse. $35,112
Definitize Change Order PS23 · Definitize allowance for differing site conditions in phase 1 of the construction of the edward R. Roybal federal building and courthouse design build… -$65,007
Supplemental Agreement for work within scope PS22 · Flooring, telephone and data lines, changes to demountable partitions, drywall, and seismic bracing for the edward R. Roybal federal building and courthouse… $55,234
Supplemental Agreement for work within scope PS21 · Installation of IT room equipment, installation and relocation of data outlets, and installation of additional lighting, installation of aluminum trim at… $16,043
Change Order PC20 · Allowance for differing site conditions for phase 3 of the prospectus repair and alteration project at the edward R. Roybal federal building and U.S. Courthouse… $100,000
Supplemental Agreement for work within scope PS19 · Bracing of fire sprinkler lines for phase 1 construction of the repair and alteration prospectus project at the edward R. Roybal federal building and U.S.… $20,386
Change Order PC18 · Increased allowance for electrical boxes on 7TH floor at the edward R. Roybal federal building and U.S. Courthouse. $1,984
Change Order PC17 · Increase allowance to address differing plumbing site condition for the repair and alteration project at edward R. Roybal federal building and U.S. Courthouse… $10,000
Supplemental Agreement for work within scope PS16 · Furnish, install, and relocate library shelving, restroom enhancements, remove signage, refinish doors, and wage adjustment for the repair and alteration of the… $135,696
Change Order PC15 · Modification to relocate wall in the edward R. Roybal federal building and courthouse in LOS angeles, CA $2,500
Change Order PC14 · Plumbing work related to the repair and alteration prospectus project for the edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA $10,000
Supplemental Agreement for work within scope PS13 · Cleats for demountable partitions, wall finishes and installation and relocation of data outlets and electrical outlets for the repair and alteration of the… $32,828
Supplemental Agreement for work within scope PS12 · Power supply to cameras, and repair of damaged wall for the edward R. Roybal federal building and courthouse in LOS angeles, CA. $8,945
Change Order PC11 · Installation of electrical boxes for the roybal federal building and courthouse in LOS angeles, CA $4,950
Supplemental Agreement for work within scope PS10 · Replace locks on doors in the edward R. Roybal federal building and courthouse in LOS angeles, CA. $1,285
Supplemental Agreement for work within scope PS09 · Intake window film for usbc, data closets' power, electrical grounding, demountable mullion and gypsum board, data closet modifications, and cable rings for the… $58,184
Change Order PC08 · Differing site conditions allowance for phase 2 of the edward R. Roybal federal building and U.S. Courthouse prospectus design build contract in LOS angeles, CA $100,000
Supplemental Agreement for work within scope PS07 · Credit for deletion of some new lights from required scope for the edward R. Roybal federal building and U.S. Courthouse in LOS angeles, CA. -$13,566
Supplemental Agreement for work within scope PS06 · Acoustical upgrades, furniture disposal, low-voltage cabling, and carpet updates for the edward R. Roybal federal building and courthouse in LOS angeles, CA $589,179
Change Order PC05 · Increase of allowance for unforeseen conditions for the design build tenant improvement project at the edward R. Roybal federal building in LOS angeles, CA $50,000
Supplemental Agreement for work within scope PS04 · Swing space power plan, wage order adjustment, and electrical/data infrastructure design for tenant improvement project for the edward R. Roybal federal… $155,962
Change Order PC03 · Differing site conditions allowance for the tenant improvement design-build contract for the edward R. Roybal federal building in LOS angeles, CA. $75,000
Supplemental Agreement for work within scope PS02 · Furniture design for the bankruptcy court and low voltage cabling for swing space for the edward R. Roybal federal building and courthouse design build tenant… $172,289
Supplemental Agreement for work within scope PS01 · Credit for deletion of work in bankruptcy court space, and charge for additional other work related to construction support for workspace changes for the design… -$73,485
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a definitive firm fixed-price contract awarded by the General Services Administration (GSA) Region 9 to Stronghold Engineering Inc., a minority-owned, for-profit, woman-owned, and Asian-Pacific American-owned small business. The $18,798,797.77 contract is for the design, repair, alteration, and tenant improvements to the Roybal Federal Building and Courthouse in Los Angeles, CA. The contract has an ultimate completion date of December 19, 2018 and was awarded on March 25, 2016. Stronghold Engineering Inc. has experience performing construction and engineering services for various federal agencies, including the Department of the Interior, Army Corps of Engineers, Department of Veterans Affairs, and Department of the Navy.

Quick answers

Who was awarded contract GS09P16KTC7017?

GS09P16KTC7017 was awarded to Stronghold Engineering Inc. by Region 9 (Public Buildings Service) on March 25, 2016.

How much is contract GS09P16KTC7017 worth?

The government has obligated $18,798,798 on GS09P16KTC7017.

Was contract GS09P16KTC7017 competed?

The extent of competition for GS09P16KTC7017 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award