Recovery*construction manager as constructor (CMC) services for the repair and alteration of the pjkk U. S. Courthouse (part I), 300 ALA moana boulevard, honolulu, hawaii

Ended Definitive Contract Awarded Last action

Contract number
GS09P09KTC0103
Awardee
Awarding agency
Obligated
$101,298,300

Award facts

Contract value 100% obligated
$101,298,300.17 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 8 offers Negotiated Proposal / Quote
Pricing
Fixed Price Incentive
Place of performance
Honolulu, HI 96850, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action PAP7 · Deobligation of remaining monies in contract. -$132,687
Supplemental Agreement for work within scope PSP6 · DE-obligation of remaining arra funds. -$238,522
Supplemental Agreement for work within scope PSP1 $52,253
Supplemental Agreement for work within scope PSO9 $49,605
Supplemental Agreement for work within scope PSO8 $35,367
Supplemental Agreement for work within scope PSO7 · This modification is being issued to provide for multiple changes (a total of 12 nocs) for the usms at the pjkk U. S. Courthouse, honolulu, hawaii. $45,329
Supplemental Agreement for work within scope PSO5 · This modification is being issued to delete the scope of work for renovations of the interior cabs of prisoner elevators 17 and 19 including interior security… -$176,279
Supplemental Agreement for work within scope PSO2 · This modification is being issued to provide for filling of GAP at ceiling wall cell B with new GMU wall as outlined in RFI 1435 response dated september 4,… $2,080
Supplemental Agreement for work within scope PSO1 · This modification is being issued to provide for furred out bathroom wall with security mesh in phase 6B as outlined in RFI 1394 response dated july 7, 2014… $8,847
Supplemental Agreement for work within scope PCO4 · This unilateral modification is being issued to direct swinerton builders to proceed with the work to provide for usms sallyport security changes as per ASI 338… $32,413
Supplemental Agreement for work within scope PSO3 · This modification is being issued to provide for purchase and install of compatible emergency power off button in the C328 server room in accordance with ASI… $2,749
Supplemental Agreement for work within scope PSN9 · This modification is being issued to provide for phase 8 door schedule revisions 12 outlined in asis 333 and 333R1 dated july 22, 2014 and august 28, 2014 and… $11,805
Supplemental Agreement for work within scope PSN7 · This modification is being issued to provide for usms front door leaf revisions and phase 8 door revisions as outlined in ASI 330 dated july 17, 2014 and ASI… $2,172
Supplemental Agreement for work within scope PSN8 · This modification is being issued to provide for an added phone/FAX line for the usms as outlined in ASI 341 dated september 4, 2014 at the pjkk U. S.… $1,055
Supplemental Agreement for work within scope PSN5 · This modification is being issued to provide for judge curren chamber revisions as outlined in ASI 174 dated november 8, 2011 at the pjkk U. S. Courthouse,… $1,745
Supplemental Agreement for work within scope PSN4 · This modification is being issued to provide for judge KAY chambers revisions including the correct carpet upcharge as outlined in ASI 167 dated october 17,… $7,311
Supplemental Agreement for work within scope PSN6 · This modification is being issued to provide for judge puglisi chamber revisions as outlined in ASI 0171 dated september 23, 2013 at the pjkk U. S.… $18,065
Supplemental Agreement for work within scope PSM8 · This modification is being issued to provide for courtrooms C234 and C240 AV rough-in as outlined in RFI 1434 and 1437 responses dated september 4, 2014 and… $2,335
Supplemental Agreement for work within scope PSN1 · This modification is being issued to provide for judge gillmor chamber revisions and correct carpet upcharge as outlined in ASI 169 dated october 9, 2011 at the… $33,666
Supplemental Agreement for work within scope PSM9 · This modification is being issued to provide for judge mollway chamber revisions and correct carpet upcharge as outlined in ASI 168 series dated october 9, 2011… $19,894
Supplemental Agreement for work within scope PSN2 · This modification is being issued to provide for judge ezra chamber revisions as outlined in ASI 170 dated november 8, 2011 at the pjkk U.S. Courthouse,… $21,431
Supplemental Agreement for work within scope PSN3 · This modification is being issued to provide for judge chang chambers revisions as outlined in ASI 0173 dated november 8, 2011 at the pjkk U. S. Courthouse,… $6,850
Supplemental Agreement for work within scope PSM7 · This modification is being issued to provide for detention grade access panel in cell M as outlined in RFI 1346 response dated april 29, 2014 at the pjkk U.… $1,657
Supplemental Agreement for work within scope PSM6 · This modification is being issued to install usms FF & E as outlined in rfis #845 and #845R1 responses dated september 20, 2012 and october 12, 2012… $1,433
Change Order PCM5 · This unilateral modification is being issued to direct swinerton builders to proceed with the work to provide for installation of a fan coil in AHU-01-03 (phase… $55,880
Supplemental Agreement for work within scope PSM3 · This modification is being issued to replace existing electrical code deficient outlet/wiring in phase 4A as outlined in RFI #853 response dated september 25,… $8,933
Supplemental Agreement for work within scope PSM4 · This modification is being issued to provide for changes to emergency generator basement room louvers as outlined in ASI 263 and ASI 263R1 REV 1 dated… $18,857
Supplemental Agreement for work within scope PSL7 · This modification is being issued to provide for additional electrical circuits associated with the movement of AV racks as outlined in ASI 209R3 dated july 16,… $6,737
Change Order PCM1 · This unilateral modification is being issued to direct swinerton builders to proceed with the work as issued for RE-support of existing AV infrastructure… $13,458
Supplemental Agreement for work within scope PSM2 · This modification is being issued to provide for added fire alarm devices as outlined on ASI 255-R1, R2, R3, and R4 dated july 17, 2013 for the IT, finance &… $27,525
Change Order PCL8 · This unilateral modification is being issued to direct swinerton builders to proceed with the work as issued to provide for an upgrade of U. S. Marshal… $10,226
Supplemental Agreement for work within scope PSL6 · This modification is being issued to provide for jury bench microphone rough in and phase 7 C112 light fixture and ceiling type as outlined in RFI #1385… $3,482
Supplemental Agreement for work within scope PSL9 · This modification is being issued to provide for revise locations of entry pavillion fire alarm pull stations and provide emergency power for auto door… $13,170
Supplemental Agreement for work within scope PSK9 · This modification is being issued to provide for temporary cooling to first floor secure equipment room and courthouse lobby space at the pjkk U. S. Courthouse,… $7,875
Supplemental Agreement for work within scope PSL2 · This modification is being issued to provide for mechanical and electrical costs for installation of fan coil units in the usms areas as outlined in ASI #294… $36,644
Supplemental Agreement for work within scope PSL4 · This modification is being issued to provide for removal of carpet to wall and prepare walls for paint in three (3) interview rooms in phase 6A as outlined in… $5,288
Supplemental Agreement for work within scope PSL3 · This modification is being issued to provide for installation of fan coil units for the usms areas as outlined in asis 294 and 294R1 dated september 13, 2013… $62,724
Supplemental Agreement for work within scope PSK8 · This modification is being issued to provide for an additional temporary space cooling units to accommodate splitting of work phases 6A and 6B to improve… $16,185
Change Order PCL5 · This unilateral modification is being issued to direct swinerton builders to proceed with the work to furnish and install TV monitors as outlined in ASI 326 and… $16,428
Supplemental Agreement for work within scope PSK7 · This modification is being issued to provide for air intake closure details as outlined in ASI 286 dated september 6, 2013 at the pjkk U. S. Courthouse,… $4,567
Supplemental Agreement for work within scope PSL1 · This modification is being issued to provide for temporary cooling by AHU06 as outlined in RFI #739 response dated july 9, 2012 at the pjkk U. S. Courthouse,… $13,412
Supplemental Agreement for work within scope PSK4 · This modification is being issued to install access panels for plumbing shutoff valves on the first floor as a result of response to RFI #1265 dated february… $2,185
Supplemental Agreement for work within scope PSK5 · This modification is being issued to provide for relocation of pipes in phase 6 toilet room (C-100B) to install electrical lines and lights as outlined in… $10,320
Other Administrative Action PAK6 · This administrative modification is being issued to correct the appropriation line under modification no. PSA1 dated august 29, 2013. The activity code is… $0
Change Order PCJ8 $45,728
Change Order PCK2 · This unilateral modification is being issued to direct swinerton builders to proceed with the work to provide for basement stairway #10 lighting as outlined… $3,568
Supplemental Agreement for work within scope PSJ9 · This modification is being issued to provide for access for maintenance to fan coil units FCU-04-01 and FCU-04-02 in response to RFI #1211 dated december 13,… $21,207
Supplemental Agreement for work within scope PSK3 · This modification is being issued to relocate electrical conduits conflicting with federal building chilled water loop system at the pjkk federal building and… $9,954
Supplemental Agreement for work within scope PSJ6 · This modification is being issued to relocate light fixtures in security pavilion as outlined in ASI #322 dated may 1, 2014 at the pjkk U. S. Courthouse,… $2,845
Change Order PCJ4 · This unilateral modification is being issued to direct swinerton builders to proceed with the work to provide for power and fire alarm connections to door… $3,301
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a federal contract award by the General Services Administration (GSA) Region 9 to Swinerton Builders for Construction Manager as Constructor (CMC) services for the repair and alteration of the Prince Jonah Kuhio Kalanianaole (PJKK) U.S. Courthouse in Honolulu, Hawaii. The contract has a fixed price incentive pricing type and has a ceiling value of $101,298,300.17. The contract has an ultimate completion date of May 5, 2014 and was awarded on November 20, 2009. The contract does not have a set-aside designation.

Quick answers

Who was awarded contract GS09P09KTC0103?

GS09P09KTC0103 was awarded to Swinerton Builders by Region 9 (Public Buildings Service) on November 20, 2009.

How much is contract GS09P09KTC0103 worth?

The government has obligated $101,298,300 on GS09P09KTC0103.

Was contract GS09P09KTC0103 competed?

The extent of competition for GS09P09KTC0103 was full and open competition. The government received 8 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award