Recovery*design excellence services for the repairs and alterations to the prince jonah kuhio kalanianaole federal building and U. S. Courthouse located at 300 ALA moana boulevard, honolulu, hawaii

Ended Definitive Contract Awarded Last action

Contract number
GS09P09KTC0061
Awardee
Awarding agency
Obligated
$35,419,388

Award facts

Opportunity
Contract value 100% obligated
$35,419,387.78 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541310 Architectural Services
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price
Place of performance
San Francisco, CA 94105, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS58 · This modification is being issued to provide for the following change: modification no. PS54 dated july 27, 2015 is being reduced by deobligating $7,900.00… -$7,902
Supplemental Agreement for work within scope PS56 · This modification is being issued to provide for additional services for cost analysis as related to the CMC REA and final costs for the entire pjkk project. $13,653
Supplemental Agreement for work within scope PS55 · This modification is being issued to provide for cost analysis as related to swinerton request for equitable adjustment (REA) for payment applications 64 -… $25,839
Supplemental Agreement for work within scope PS54 · This modification is being issued to provide for construction documents and cost estimate for the U. S. Marshal service (USMS) prisoner elevator work at the… $16,453
Supplemental Agreement for work within scope PS53 · This modification is being issued to provide for additional construction administration services for U. S. Marshal service (USMS) scope of work in the pjkk U.… $60,185
Supplemental Agreement for work within scope PS52 · This modification is being issued to provide for project closeout scanning and shipping of project documents from the construction administration office in… $25,699
Supplemental Agreement for work within scope PS51 · This modification is being issued to provide for extended cost accounting services as outlined in the attached scope of work dated october 10, 2014 (1 page). $64,272
Supplemental Agreement for work within scope PS50 · This modification is being issued to deobligate funds for unused hours for the a/E consultants under the construction administration (CA) phase services… -$79,869
Supplemental Agreement for work within scope PS47 · This modification is being issued to provide for the deletion from the scope of work for the acoustical sub-consultant to perform services for audio visual (AV)… -$20,000
Supplemental Agreement for work within scope PS48 · This modification is being issued to provide for cost estimating services to review scope of work changes for the usms as outlined in the scope of work dated… $9,822
Supplemental Agreement for work within scope PS49 · This modification is being issued to provide for continued construction administration services associated with the usms build out for the month of november… $26,111
Supplemental Agreement for work within scope PS46 · This modification is being issued to provide for additional mechanical design and construction administration services as outlined in the scope of work dated… $39,000
Supplemental Agreement for work within scope PS45 · This modification is being issued to provide monies for additional schedule and cost analysis needed to review and assist in preparing the pre-negotiation… $195,157
Supplemental Agreement for work within scope PS44 · This modification is being issued to provide for phase 8 pre-trial RE-design as outlined in the scope of work dated february 11, 2014 and annotated pre-trial… $26,765
Supplemental Agreement for work within scope PS43 · This modification is being issued to provide for additional design services for consolidated phasing coordination, energy model record documentation, design… $380,612
Supplemental Agreement for work within scope PS40 -$800
Supplemental Agreement for work within scope PS42 -$3,200
Supplemental Agreement for work within scope PS41 · This modification is being issued to provide for a deobligation of monies due to the change of the mechanical engineer of record as requested by the… -$8,800
Supplemental Agreement for work within scope PS39 · This modification is being issued to delete the scope of work for charles M. Salter and associates to measure and document noise levels of construction work… -$49,215
Supplemental Agreement for work within scope PS38 · This modification is being issued to provide monies for additional schedule and cost analysis needed to review the construction manager as constructor (CMC)… $25,944
Supplemental Agreement for work within scope PS37 · This modification is being issued to delete from the scope of work the procurement phase services for part 2 - pjkk federal building. This work is no longer… -$380,612
Other Administrative Action PA36 · This administrative modification is being issued to attach the accounting line to line item no. 0001 in comprizon. $0
Supplemental Agreement for work within scope PS35 · This modification is being issued for electrical design services for revisions to the usms task force suite's new furniture on FB02. This work is to included… $17,468
Supplemental Agreement for work within scope PS34 · This modification is being issued to provide for additional schedule and cost analysis services in accordance with the attached scope of work dated june 5, 2013… $179,139
Supplemental Agreement for work within scope PS32 · Provide for design for the U.S. Courts audio visual (AV) infrastructure, wiring and equipment installation in the following areas: CH01 jury lounge/jury… $99,989
Supplemental Agreement for work within scope PS31 · Provide for design documentation for the final design of the 3RD floor server room in the pjkk U.S. Courthouse, honolulu, hawaii. $6,000
Supplemental Agreement for work within scope PS30 · Provide for mechanical and plumbing design and construction administration services as outlined in scope of work dated 10/25/2012. $358,167
Supplemental Agreement for work within scope PS29 · Provide for design services for AV for the judicial conference room, 4TH floor of the pjkk U. S. Courthouse, honolulu, hawaii. $7,985
Supplemental Agreement for work within scope PS28 · Development of furniture specifications for the furniture procurement of the usms suite at the pjkk federal building and U. S. Courthouse, honolulu, hawaii. $62,000
Supplemental Agreement for work within scope PS27 · Provide for design services for relocation of the district courtroom AV racks to the 5TH floor telecom rooms in the pjkk courthouse, honolulu, hawaii. $30,400
Supplemental Agreement for work within scope PS25 · Design services for usms holding cells and sallyport at the pjkk U. S. Courthouse, honolulu, hawaii. $418,000
Supplemental Agreement for work within scope PS26 · Design services for HVAC design for RE-heat at the district courtrooms at the pjkk U. S. Courthouse, honolulu, hawaii. $33,500
Other Administrative Action PA22 · Administrative change to correct work item numbers on modification NOS. PO01, PS05, PS10, PS12, PS15, PS18 and PS21 from 129 or 292 to 290. $0
Supplemental Agreement for work within scope PS23 · Design services for 1ST floor jury assembly and jury lounge renovations at the pjkk U. S. Courthouse, honolulu, hawaii. $100,000
Supplemental Agreement for work within scope PS24 · Design services for renovation of IT and finance spaces in the pjkk courthouse, honolulu, hawaii. $60,000
Supplemental Agreement for work within scope PS21 · Provide for additional consulting engineer services and leed consulting in support of the design for the phase II pjkk renovation. $135,000
Other Administrative Action PA20 · This administrative modification is being issued to correct modification no. PS11 dated december 16, 2010 on line item no. 0012 the fund code is incorrect and… $0
Supplemental Agreement for work within scope PS18 · Additional staff in support of construction administration services for the repair and alterations to the pjkk U. S. Courthouse (part I), honolulu, hawaii. $1,151,832
Supplemental Agreement for work within scope PS19 · Additional design services for tenant space and common areas, acoustic report and npds permit. $869,904
Supplemental Agreement for work within scope PS16 · Provide for a food service consultant for revisions to the cafeteria on the 5TH floor, a traffic engineer to assess driveway exit and entry lanes and additional… $191,414
Other Administrative Action PA17 · Administrative modification to correct appropriation lines for fund code and budget codes. $0
Supplemental Agreement for work within scope PS12 · This modification is to provide for landscape design services for the part 2 portion of the design services for the repair and alteration of the pjkk federal… $143,050
Supplemental Agreement for work within scope PS15 · This modification is being issued to provide for the including of lighting mockups as part of the design of the repair and alteration of the pjkk U. S.… $35,765
Supplemental Agreement for work within scope PS14 · This modification to provide for coordination needed for probation furniture and equipment specifications and furniture and equipment installation for the… $59,144
Supplemental Agreement for work within scope PS13 · This modification is being issued to provide for design and documentation required to convert to upgrade the swing bridge courtroom at the pjkk U. S. Courthouse… $101,223
Supplemental Agreement for work within scope PS10 · This modification is for design and documentation of existing furniture layouts and for planning for tenant agencies swing and permanent moves occuring during… $522,169
Supplemental Agreement for work within scope PS11 · This modification is to provide for the holding of oaca meetings, including any associated design, throughout the duration of repair and alteration of the… $455,783
Supplemental Agreement for work within scope PS09 · Design services for snack shop bar to be relocated from the first floor to the rear of the fountain at the federal building, 300 ALA moana boulevard,… $67,000
Supplemental Agreement for work within scope PS08 · Provide for design, construction documents and consulting work for the fire alarm replacement and upgrade project in the pjkk federal building including… $237,912
Supplemental Agreement for work within scope PS07 · Provide for a study to document acoustical measurements of rail systems similar to the rail system being proposed in honolulu, hawaii adjacent to the pjkk U. S.… $51,785
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a definitive contract awarded by the General Services Administration (GSA) Region 9 to M Arthur Gensler JR & Associates Inc., doing business as Gensler, a global architecture and design firm. The $35,419,387.78 contract is for design excellence services to support repairs and alterations to the Prince Jonah Kuhio Kalanianaole Federal Building and U.S. Courthouse in Honolulu, Hawaii. The contract has a period of performance ending on September 30, 2016 and is a firm fixed-price contract. Gensler is the prime contractor and there is no set-aside designation for this award. The contract is part of Gensler's portfolio of federal work, which includes multiple indefinite delivery vehicle (IDV) contracts with agencies such as the GSA, U.S. Army Corps of Engineers, and Department of State, demonstrating the government's confidence in Gensler's ability to provide high-quality architectural, engineering, and consulting services across various federal projects and locations.

Quick answers

Who was awarded contract GS09P09KTC0061?

GS09P09KTC0061 was awarded to M Arthur Gensler JR & Associates Inc. by Region 9 (Public Buildings Service) on July 24, 2009.

How much is contract GS09P09KTC0061 worth?

The government has obligated $35,419,388 on GS09P09KTC0061.

Was contract GS09P09KTC0061 competed?

The extent of competition for GS09P09KTC0061 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award