Design/build renovations at the GT "mickey" leland federal building in houston, texas. Renovations include replacement of the exterior building envelope, HVAC upgrades, lighting controls to maximize…

Ended Definitive Contract Awarded Last action

Contract number
GS07P09UYC0008
Awardee
Awarding agency
Obligated
$88,169,712

Award facts

Opportunity
Contract value 100% obligated
$88,169,712.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 8 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Houston, TX 77010, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS40 · Arra: modification for various space modifications, fire protection, security equipment, furniture, architectural and elevator modifications at the GT… -$27,714
Supplemental Agreement for work within scope PS39 · Arra: modification for various mechanical, plumbing, lighting and additional cleaning, and furniture for eeoc at the GT "mickey" leland federal building in… $39,751
Supplemental Agreement for work within scope PS38 · Modification for various mechanical, electrical, plumbing, data, HVAC, signage, fire sprinkler, and structural changes. $29,963
Supplemental Agreement for work within scope PS37 · Modification to revise the mickey leland story wall display for the renovations at the GT "mickey" leland federal building in houston, TX. $0
Supplemental Agreement for work within scope PS36 · Modification to convert the guaranteed maximum price portion of this contract to a firm-fixed price for the renovations at the GT "mickey" leland federal… $0
Supplemental Agreement for work within scope PS35 · Department of state modifications for the 5TH floor furnishings, add cable trays, electrical revisions and phone jacks at the GT "mickey" leland federal… $115,619
Change Order PC34 · Recovery: changes to the eeoc floor plan on levels 6 and 7 for the design/build renovations at the GT "mickey" leland federal building in houston, TX. $377,472
Supplemental Agreement for work within scope PS33 · Recovery: HVAC structural and plumbing changes for the design/build renovations at the GT "mickey" leland federal building in houston, TX. $183,052
Supplemental Agreement for work within scope PS32 · Recovery: various IT, plumbing, electrical and architectural changes for the design/build renovations at the GT "mickey" leland federal building in houston, TX. $34,401
Change Order PC31 · Recovery: redesign the saw-tooth mast climber connection due to the edge condition on the 21ST floor for the design/build renovation project at the GT… $66,658
Other Administrative Action PA30 · Recovery: administrative change to correct accounting codes. $0
Supplemental Agreement for work within scope PS29 · Recovery: extend contract completion date for the design/build renovations at the GT "mickey" leland federal building in houston, TX. $0
Supplemental Agreement for work within scope PS28 · Add two bathrooms, electrical changes, voip power changes and miscellaneous IT items for the department of state at the GT "mickey" leland federal building in… $92,402
Supplemental Agreement for work within scope PS27 · Remove and dispose of high density lockers for the department of state. Other changes include upgrade to security system, plumbing, telephone & IT support,… $3,967
Supplemental Agreement for work within scope PS26 · Recovery: unforseen structural conditions, construction and furniture changes for HHS, unforseen foundation conditions at the leland federal building in… $0
Supplemental Agreement for work within scope PS2S · 4TH floor renovations as requested by the department of state at the GT "mickey" leland federal building in houston, TX. $322,465
Change Order PC24 · Department of state furniture and installation at the GT "mickey" leland federal building in houston, TX. $347,222
Supplemental Agreement for work within scope PS23 · Recovery: elevator service, hardware, furniture removal, painting, restroom drains, plumbing, manbars. $0
Supplemental Agreement for work within scope PS22 · Recovery: build out the 5TH floor for final relocation of the department of state consular affairs at the leland federal building in houston, TX $661,336
Change Order PC21 · Recovery: per office of chief architect, revise size, density and length of fins on the face of the building. $371,976
Supplemental Agreement for work within scope PS20 · Recovery: security system, unforseen conditions at rotunda, corridor upgrades, grout beneath anchor plates, prepare and paint rooftop penthouse, additional… $925,687
Supplemental Agreement for work within scope PS18 · Recovery: structural repairs, plumbing changes, furnish electronic building directory, signage, wall shaft for generator exhaust, unforseen conditions above… $1,343,278
Supplemental Agreement for work within scope PS19 · Recovery: building out of plumb. $765,342
Supplemental Agreement for work within scope PS17 · Recoverly: unforseen conditions at ceilings, electrical work, security requirements, elevator CAB work, signage, remove/reinstall walls, painting, air… $481,772
Supplemental Agreement for work within scope PS16 · Recovery: deobligate undefinitized balance from modification PS05. -$4,006,376
Supplemental Agreement for work within scope PS15 · Recovery: changes in scope of work for cabling, electrical work, tenant move coordination, plumbing, ABA door hardware, account for discrepancies in bridging… -$2,407
Other Administrative Action PA14 · Recovery: administrative modification to correct line item amounts. $0
Supplemental Agreement for work within scope PS13 · Recovery: work for CES 021-design and install additional roof steel required to support existing roof parapets and curtain-wall due to as built structure… $0
Supplemental Agreement for work within scope PS12 · Recovery: incorporate GFP clauses, definitize CE #005, CE #46 (PCO#001), and CO#051 (PCO#015) from modification PS05. $0
Supplemental Agreement for work within scope PS11 · Recovery: definitize CE#s 003, 004, 013, 015, 020, 034 & 023 from modification PS05. $0
Supplemental Agreement for work within scope PS10 · Recovery: definitize CE #009 (CES043, 047) and pcos #003 & 018 (CES 040, 044) from modification PS05. $0
Supplemental Agreement for work within scope PS09 · Recovery: work includes requirements for ABA compliant restrooms, eliminate chemical free water treatment for cooling towers, implement the 2010 p-100 for the… $115,084
Supplemental Agreement for work within scope PS08 · Recovery: deobligate -$115,084.00 from CE#009 (electrical changes from central office reviews and arra lighting corrections) in order to fund federal protective… -$115,084
Supplemental Agreement for work within scope PS07 · Recovery: definitize design only of CES 006, 007, 009, 010, 016 & 018 from modification PS05. Work includes new fire suppression specification, BAS, arra… $0
Supplemental Agreement for work within scope PS06 · Recovery: definitize work for the design portion only (not construction) of the leland FB parking lot to reflect new needs and requirements. $0
Supplemental Agreement for work within scope PS05 · Recovery: various security, electrical, structural, mechanical, and architectural changes. $5,826,916
Supplemental Agreement for work within scope PS04 · Add architectural louvers on the side of the new breezeway and to add the green screen elements on the side of the new lobby extension. Add the new cost… $178,978
Supplemental Agreement for work within scope PS03 · Recovery: design structural repairs to cantilevered double tees. $16,313
Supplemental Agreement for work within scope PS02 · Recovery: provide glass mock-UPS on 2ND floor of the existing building and add new buy american act clauses. $19,472
Other Administrative Action PA01 · Recovery: design/build renovations at the GT "mickey" leland federal building in houston, TX. Administrative modification to correct accounting code. $0
Original award $80,002,167
Show all 41

About this award

This is a $88,169,712.00 firm fixed price definitive contract awarded by the General Services Administration (GSA) Region 7 to Gilbane Building Company for design and construction renovations of the G.T. "Mickey" Leland Federal Building in Houston, Texas. The renovations include replacing the building envelope, upgrading the HVAC system, and installing lighting controls to improve energy efficiency. This contract does not have a set-aside designation. Gilbane Building Company is the prime contractor, and there is no information provided about any major subcontractors.

Description

Design/build renovations at the GT "mickey" leland federal building in houston, texas. Renovations include replacement of the exterior building envelope, HVAC upgrades, lighting controls to maximize energy efficiency, etc.

Quick answers

Who was awarded contract GS07P09UYC0008?

GS07P09UYC0008 was awarded to Gilbane Building Company by Region 7 (Public Buildings Service) on March 22, 2010.

How much is contract GS07P09UYC0008 worth?

The government has obligated $88,169,712 on GS07P09UYC0008.

Was contract GS07P09UYC0008 competed?

The extent of competition for GS07P09UYC0008 was full and open competition. The government received 8 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award