Recovery pre-design and design stage CMC construction services for the mechanical, electrical and plumbing replacement project at the BH whipple federal building in FT. Snelling, minnesota.
Additional Work (new agreement, FAR part 6 applies)
PSK8
$0
Supplemental Agreement for work within scope
PSK5
$1,892
Supplemental Agreement for work within scope
PSK4
$0
Supplemental Agreement for work within scope
PSK6
$0
Supplemental Agreement for work within scope
PSK7 · Mechanical, electrical and plumbing (MEP) replacement at the bishop henry whipple federal building located in FT. Snelling, minnesota, contract number…
$2,867
Supplemental Agreement for work within scope
PSK2
$619
Supplemental Agreement for work within scope
PSK3 · The purpose of this modification is to incorporate scope changes under CE5382R or the immmigration & customs enforcement (ICE) agency offices in the B.H.…
$0
Supplemental Agreement for work within scope
PSK1 · The purpose of this modification is to finalize the pricing for work associated with request number 5368 as originally awarded under modification PCJ5 for floor…
-$6,848
Supplemental Agreement for work within scope
PSJ9 · The purpose of this modification is to incorporate scope changes under requests CE5375, CE5379, CE5380, CE5381 and CE5389 for the immigration and customs…
$22,526
Other Administrative Action
PAJ8 · The purpose of this modification PAJ8 is to administratively correct the accounting stream data included in modification PCJ5 to reflect the appropriate…
$0
Supplemental Agreement for work within scope
PSJ7
$2,368
Supplemental Agreement for work within scope
PSJ6 · Mechanical, electrical and plumbing (MEP) replacement for the bishop henry whipple federal building located in FT. Snelling, minnesota, contract number…
-$500
Funding Only Action
PSJ4 · Mechanical, electrical and plumbing (MEP) replacement at the bishop henry whipple federal building located in FT. Snelling, minnesota, contract number…
-$1,173
Change Order
PCJ5 · Mechanical, electrical and plumbing (MEP) replacement for the bishop henrywhipple federal building located in FT. Snelling, minnesota, contract number…
$20,889
Supplemental Agreement for work within scope
PSJ2 · Mechanical, electrical and plumbing (MEP) replacement at the bishop henry whipple federal building located in FT. Snelling, minnesota, contract number…
$75,510
Supplemental Agreement for work within scope
PSJ1 · Various changes for tenant; RWA funded items.
$110,627
Supplemental Agreement for work within scope
PSJ3 · Modification issued to make changes to tenant space - tenant eoir directed changed.
$850
Supplemental Agreement for work within scope
PSI9 · Mechanical, electrical and plumbing renovation at the bishop h. Whipple federal building - modification issued for final settlement.
$0
Supplemental Agreement for work within scope
PSI8 · Mechanical, electrical and plumbing (MEP) replacement at the bishop henry whipple federal building located in FT. Snelling, minnesota, contract number…
$56,219
Supplemental Agreement for work within scope
PSI7 · The purpose of this modification is to delete funds associated with contract line item number (clin) 0257 for request CE5336 under modification PSI1. Award of…
-$9,178
Supplemental Agreement for work within scope
PSI6 · The purpose of this modification is to incorporate changes under request CE5367 for changes and repairs to the solar hot water system at the bishop henry…
$0
Supplemental Agreement for work within scope
PSI4 · The purpose of this modification is to incorporate the scope changes under requests CE5302R & CE5362 for the federal protective service offices at the B.H.…
$5,170
Supplemental Agreement for work within scope
PSI5 · The purpose of this modification is to incorporate scope changes under requests CE5289, CE5319, CE5322, CE5357R, and CE5361 for the immigration and customs…
$18,723
Supplemental Agreement for work within scope
PSI2 · The purpose of this modification is to add additional work per request CE5353 for the removal and relocation of a keypad at U.S. Navy offices at the B.H.…
$1,540
Supplemental Agreement for work within scope
PSI1 · The purpose of this modification is to incorporate the scoped changes under request CE5336 for the U.S. Marines offices in the B.H. Whipple federal building,…
$9,178
Supplemental Agreement for work within scope
PSH9 · The purpose of this modification is to incorporate changes to the scope of work under requests CE5263R, CE5312 and CE5325 for the executive office of…
$6,157
Supplemental Agreement for work within scope
PSI3 · The purpose of this modification is to incorporate additional work under request CE5352 to add a handicap door operator for the veteran's administration (VA)…
$5,748
Supplemental Agreement for work within scope
PSH8 · The purpose of this modification is to incorporate requests CE5308, 5339, 5344 and 5355 for various scope changes for the U.S. Army offices at the B.H.…
$12,860
Supplemental Agreement for work within scope
PSH7 · The purpose of this modification is to incorporate the scope of work changes under CE5296, CE5313, CE5327, CE5328, CE5329, CE5330, CE5335 and CE5343 for…
$14,897
Supplemental Agreement for work within scope
PSH6 · The purpose of this modification is to incorporate scope of work changes under request CE5358 for various changes for the veteran s administration (VA)…
$23,265
Supplemental Agreement for work within scope
PSH4
$2,352
Supplemental Agreement for work within scope
PSH3 · The purpose of this modification is to incorporate various scope of work changes under requests CE5318, CE5326 and CE5351 for the military entrance processing…
$20,619
Supplemental Agreement for work within scope
PSH5 · The purpose of this modification is to incorporate scope of work changes under request CE5336 for various changes for the U.S. Marine corps offices at the…
$9,178
Supplemental Agreement for work within scope
PSG4 · The purpose of this modification is to incorporate the scope of work changes CE5349 for additional fuzz wall in the tenant veteran s administration offices on…
$12,873
Supplemental Agreement for work within scope
PSH1
$19,260
Supplemental Agreement for work within scope
PSH2 · The purpose of this modification is to incorporate various scope of work changes under CE5311 for changes to the signage requested and awarded under PSD1 for…
-$10,843
Supplemental Agreement for work within scope
PSG9 · The purpose of this modification is to incorporate requests CE5324C, CE5337C, CE5338C and CE5345C funded form the CMC project contingency and debited from the…
$0
Supplemental Agreement for work within scope
PSG6 · The purpose of this modification is to incorporate the scope of work changes CE5346 for automatic door operators for tenant veteran s benefit administration…
$10,570
Supplemental Agreement for work within scope
PSG8 · The purpose of this modification is to incorporate various scope of work changes under CE5264, CE5265, CE5272, CE5276, CE5288, CE5303, CE5306, CE5316, CE5320…
$36,721
Supplemental Agreement for work within scope
PSG7
-$239
Supplemental Agreement for work within scope
PSG5 · The purpose of this modification is to incorporate the scope of work changes under CE5294 for adding a circuit for the federal protective services (FPS) offices…
$1,737
Supplemental Agreement for work within scope
PSG3 · The purpose of this modification is to incorporate additional work under CE5340 for the material and work associated with the installation of one card reader…
$11,599
Supplemental Agreement for work within scope
PSG1 · The purpose of this modification is to incorporate scope changes under CE5286 for the veteran's administration offices at the bishop henry whipple federal…
$3,054
Supplemental Agreement for work within scope
PSG2 · The purpose of this modification is to incorporate the scope of work changes under CE5268 for podium level signage for the veteran's administration (VA) offices…
$2,529
Supplemental Agreement for work within scope
PSF8 · The purpose of this modification is to incorporate scope changes under CE5281 and CE5298 for the immigration and customs enforcement (ICE) offices at the bishop…
$4,337
Supplemental Agreement for work within scope
PSF7 · The purpose of this modification is to incorporate the scope changes under CE5262 and CE5280 for the executive office of immigration review (eoir) offices at…
$3,029
Supplemental Agreement for work within scope
PSF9
$8,344
Supplemental Agreement for work within scope
PSF6
$19,390
Supplemental Agreement for work within scope
PSF5 · The purpose of this modification is to incorporate scope changes under CE5241 for the veteran's administration offices at the bishop henry whipple federal…
This is a definitive contract awarded by the General Services Administration (GSA) - Public Buildings Service (PBS) to Ryan Companies US Inc., a for-profit Subchapter S Corporation, for $164,480,909.79. The contract is for TAS Recovery Pre-Design and Design Stage CMC Construction Services for the Mechanical, Electrical and Plumbing Replacement Project at the BH Whipple Federal Building in Ft. Snelling, Minnesota. The contract is a firm fixed-price agreement with a period of performance ending on December 31, 2014. There is no set-aside designation noted for this award.
Quick answers
Who was awarded contract GS05P09GBC0027?
GS05P09GBC0027 was awarded to Ryan Companies US Inc. by Region 5 (Public Buildings Service) on November 13, 2009.
How much is contract GS05P09GBC0027 worth?
The government has obligated $164,480,700 on GS05P09GBC0027. Its current value, with exercised options, is $164,480,910.
Was contract GS05P09GBC0027 competed?
The extent of competition for GS05P09GBC0027 was full and open competition. The government received 6 offers.