Recovery - arra modernization project - renovation of the M.C. Smith federal building in bangor, me.

Ended Definitive Contract Awarded Last action

Contract number
GS01P09BZC0028
Awardee
Awarding agency
Obligated
$41,259,814

Award facts

Opportunity
Contract value 100% obligated
$41,259,814.07 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Negotiated Proposal / Quote
Pricing
Fixed Price Incentive
Place of performance
Bangor, ME 04401, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS41 · Recovery modification PS41 deletes the monetary value for contract line item 0252 added on modification PS36 for building automation system for the generation… -$5,484
Supplemental Agreement for work within scope PS40 · Recovery - equitable adjustment due the contractor for changes within scope for the renovation of the MC smith FB in bangor, maine. $5,894
Supplemental Agreement for work within scope PS38 · Recovery - equitable adjustment for work within scope for the modernization of the MC smith federal building in bangor, maine. $23,575
Supplemental Agreement for work within scope PS39 · Recovery - additional work to assist with the building automation system and mechanical systems at the M.C. Smith federal building in bangor, maine. $86,189
Supplemental Agreement for work within scope PS36 · Recovery equitable adjustment due the contractor for changes within scope for construction services for the alteration and modernization of the MC smith federal… $5,143
Supplemental Agreement for work within scope PS35 · Equitable adjustment to the construction contract for the building plaque at the M.C. Smith FB in bangor, maine. $7,374
Supplemental Agreement for work within scope PS34 · Recovery -- modification to convert the CMC contract to a fixed price contract and to deobligate the government's portion of the shared savings. MC smith FB… -$215,966
Supplemental Agreement for work within scope PS33 · 1. Contract GS-01P-09-BZ-C-0028, modernization of the M.C. Smith federal building in bangor, maine, is modified as set forth in the schedule. 2. The contract… $9,868
Supplemental Agreement for work within scope PS32 · M.C. Smith federal building in bangor, maine, is modified, in scope, as follows to increase contract by $51,037.00 to the guaranteed maximum price of… $51,037
Supplemental Agreement for work within scope PS31 · 1. Contract GS-01P-09-BZ-C-0028, modernization of the M.C. Smith federal building in bangor, maine, is modified to extend the contract completion date to… $0
Supplemental Agreement for work within scope PS29 · Equitable adjustment due the contractor for changes within scope during the modernization of the M.C. Smith federal building in bangor, me. $5,188
Supplemental Agreement for work within scope PS30 · Equitable adjustment due the contractor for changes requested by social security administration during the modernization of the M.C. Smith federal building in… $3,317
Supplemental Agreement for work within scope PS28 · Margaret chase smith U.S. Federal building, bangor, maine, construction manager as constructer services. RWA clins 0234 to 0239 for miscellaneos work within… $10,433
Supplemental Agreement for work within scope PS27 · Margaret chase smith federal building, bangor, maine, modernization. Clin 0214 to clin 0233 - various work within scope. $36,801
Supplemental Agreement for work within scope PS26 · This supplemental agreement is for changes within scope to the construction contract for the renovation and modernization of the margaret chase smith federal… $121,586
Supplemental Agreement for work within scope PS24 $90,351
Supplemental Agreement for work within scope PS25 · Supplemental agreement for changes within scope to the construction contract for the renovation of the M.C. Smith federal building in bangor, maine. $98,179
Supplemental Agreement for work within scope PS23 · Modification of contract GS-01P-09-BZ-C-0028, modernization of the M.C.smith federal building in bangor, me for equitable adjustments due the contractor for… -$594,257
Supplemental Agreement for work within scope PS22 · Allowance reconcilation and changes within scope for the renovation of the M.C. Smith FB in bangor, me. $0
Supplemental Agreement for work within scope PS21 · Court requested changes to their space during the renovation of the M.C. Smith federal building in bangor, me. $13,343
Supplemental Agreement for work within scope PS20 · Reconciliation of courts RWA for work in association of the modernization of the MC smith FB in bangor, maine. $0
Supplemental Agreement for work within scope PS19 · Equitable adjustments for within scope changes for the modernization of the MC smith federal building in bangor, maine. $0
Supplemental Agreement for work within scope PS18 · Equitable adjustment due the contractor for agency (courts and SSA) requested changes within scope in the for the moderization project at the MC smith federal… $4,747
Supplemental Agreement for work within scope PS17 · Modification to incorporate work within scope, to include the final reconcilation of the security allowance within the GMP. The security allowance includes… $0
Supplemental Agreement for work within scope PS16 · Courts tenant improvements for the M.C. Smith federal building, i.e. millwork, audio/visual equipment, and dedicated power supply to TEL/data and a/V room.… $801,793
Supplemental Agreement for work within scope PS15 · Recovery - equitable adjustment due the contractor for changes within scope for the modernization of the M.C. Smith federal building. $8,960
Supplemental Agreement for work within scope PS14 · Credit for work not performed and equitable adjustment for changes within scope for the renovation of the M.C. Smith federal building in bangor, me. $0
Supplemental Agreement for work within scope PS13 · Supplemental agreement for changes within scope, specifically TEL/data wiring and conduit for the courts. Also, new millwork for court's kitchenette and VCT… $155,625
Supplemental Agreement for work within scope PS11 · Equitable adjustments due the contractor for changes within scope. Reconcilation of allowance for front pavilion. $0
Supplemental Agreement for work within scope PS12 · Definitization of 'not-to-exceed' price for damage caused by a burst pipe on the third floor of the M.C. Smith federal building. Burst pipe unrelated to… -$8,640
Supplemental Agreement for work within scope PS10 · Labor and materials necessary to repair water damage to the newly renovated united states marshall service tenant spaces which was caused by a burst pipe on the… $72,000
Supplemental Agreement for work within scope PS09 · Changes within scope for the modernization of the MC smith FB in bangor, me. $0
Supplemental Agreement for work within scope PS08 · Renovation and modernization of MC smith FB in bangor, maine. Modification adds ballistic window glazing to third floor court areas. $85,271
Supplemental Agreement for work within scope PS07 · The purpose of this modification is to incorporate the following drawings and bulletins into the contract: * issued for construction drawings and specifications… $2,032
Supplemental Agreement for work within scope PS05 · Increase existing allowances for the front entry pavilion due to revised drawings and the water handling for geothermal well drilling due to higher than… $1,899,968
Supplemental Agreement for work within scope PS04 · Provide equitable adjustment for changes within scope, i.e. asbestos abatement of existing boilers and needed exploratory work and storm drain repair associated… $28,221
Other Administrative Action PA03 · Administrative modification to assign PGH funding codes. $0
Supplemental Agreement for work within scope PS01 · Modification to increase the guaranteed maximum price (GMP) to reflect changes in scope from 95% design development to 100% construction documents. $1,942,466
Supplemental Agreement for work within scope PS02 · Recovery - modification to increase the guaranteed maximum price (GMP)to reflect changes in scope of work from 95% design development to 100% construction… $2,634,217
Original award $33,880,583
Show all 40

About this award

This is a $41,259,814.07 fixed price incentive contract awarded by the General Services Administration (GSA) Region 1 to Consigli Construction Co., Inc. for the renovation of the M.C. Smith Federal Building in Bangor, Maine. The contract, designated as part of the American Recovery and Reinvestment Act (ARRA) Modernization Project, has an ultimate completion date of September 30, 2015. Consigli Construction Co., Inc. is a for-profit, Subchapter S Corporation construction company that has previously held prime federal contracts with agencies such as the Department of the Navy, Army Corps of Engineers, National Park Service, and GSA for a variety of construction and renovation projects. This contract was not set aside and was awarded directly to Consigli Construction Co., Inc. as the prime contractor, without the use of any Indefinite Delivery Vehicles (IDVs). The parent company, Consigli Building Group Inc., is also a registered federal contractor but does not appear to have any IDVs based on the information provided.

Quick answers

Who was awarded contract GS01P09BZC0028?

GS01P09BZC0028 was awarded to Consigli Construction Co., Inc. by Region 1 (Public Buildings Service) on March 25, 2010.

How much is contract GS01P09BZC0028 worth?

The government has obligated $41,259,814 on GS01P09BZC0028.

Was contract GS01P09BZC0028 competed?

The extent of competition for GS01P09BZC0028 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award