Project: bawa 1(3), 2(3) the project consists of the resurfacing of approximately 0.54 miles of the NB/SB baltimore-washington parkway at the MD 197 interchange, as well as approximately 2.32 miles of…

Ended Definitive Contract Awarded Last action

Contract number
DTFH7115C00035
Awardee
Awarding agency
Obligated
$1,428,614

Award facts

Opportunity
Contract value 100% obligated
$1,428,614.25 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 2 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Greenbelt, MD 20770, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 4 · The purpose of this no cost administrative modification is to financially and contractually close this contract in the amount of $1,428,614.25. $0
Other Administrative Action 3 · PRA-bawa 1(3),2(3) CM#3 decrease contract amount by $6,110.43 no change to contract time finalize the existing quantities -$6,110
Other Administrative Action 2 · PRA-bawa 1(3),2(3) decrease contract amount by $19,819.68 add 76 calendar days to contract time $19,820
Other Administrative Action 1 · PRA-bawa 1(3),2(3) decrease contract amount by $5,000 add 19 calendar days to contract time -$5,000
Original award $1,419,905

About this award

This is a federal contract awarded by the Federal Highway Administration, a civilian agency, to Milani Construction LLC, a self-certified small disadvantaged business and DOT-certified Disadvantaged Business Enterprise (DBE). The $1,428,614.25 firm-fixed-price contract is for the resurfacing of approximately 0.54 miles of the northbound and southbound Baltimore-Washington Parkway at the MD 197 interchange, as well as approximately 2.32 miles of adjacent on/off ramps at the MD 197 and MD 193 interchanges. The work includes asphalt pavement milling, Superpave asphalt concrete pavement overlay, and other miscellaneous work. The contract is set aside for HUBZone businesses and has a completion date of February 29, 2016.

Description

Project: bawa 1(3), 2(3) the project consists of the resurfacing of approximately 0.54 miles of the NB/SB baltimore-washington parkway at the MD 197 interchange, as well as approximately 2.32 miles of adjacent on/off ramps at the MD 197 and MD 193 interchanges. The work includes asphalt pavement milling, superpave asphalt concrete pavement overlay, and other miscellaneous work.

Quick answers

Who was awarded contract DTFH7115C00035?

DTFH7115C00035 was awarded to Milani Construction LLC by Federal Highway Administration (Department of Transportation) on July 31, 2015.

How much is contract DTFH7115C00035 worth?

The government has obligated $1,428,614 on DTFH7115C00035.

Was contract DTFH7115C00035 competed?

The extent of competition for DTFH7115C00035 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: HUBZone.

On GovTribe