Fort george g. Meade rockenbach access control point project no.: fort meade rockenbach ACP this project is for the rockenbach access control point (ACP) into fort george g. Meade (fggm) in anne…

Ended Definitive Contract Awarded Last action

Contract number
DTFH7113C00033
Awardee
Awarding agency
Obligated
$9,607,851

Award facts

Opportunity
Contract value 93% obligated
  • $9,607,850.76 Current, with exercised options
  • $10,347,659.76 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 12 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Cape St Claire, MD 21401, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00014 · The purpose of this no cost administrative modification is to financially and contractually close this contract in the amount of $9,607,850.76. $0
Other Administrative Action P00013 · FT meade rockenbach CM #13 no change to contract amount no change to contract time extend period of performance to december 31, 2022 $0
Funding Only Action P00012 · FT meade rockenbach CM #12 decrease contract amount by $320,341.61 no change to contract time finalize the existing quantities -$320,342
Other Administrative Action P00011 · FT meade rockenbach CM #11 no change to contract amount extend contract time by 381 calendar days $0
Other Administrative Action P00010 · FT meade rockenbach CM #10 no change to contract amount no change to contract time period of performance $0
Funding Only Action P00009 · FT meade rockenbach CM #9 decrease contract amount by $105,000.00 no change to contract time -$105,000
Funding Only Action P00008 · FT meade rockenbach CM #8 no change to contract amount no change to contract time $0
Funding Only Action 7 · FT meade rockenbach CM #7 increase contract amount by $475,000.00 no change to contract time $475,000
Funding Only Action 6 · FT meade rockenbach CM #6 increase contract amount by $22,625.59 no change to contract time $22,626
Funding Only Action 5 · FT meade rockenbach CM #5 increase contract amount by $575,000.00 add 59 calendar days to contract time $575,000
Other Administrative Action 4 · FT meade rockenbach CM #4 no change to contract amount extend contract completion date to june 18, 2020 $0
Other Administrative Action 3 · FT meade rockenbach CM #3 decrease contract amount by $124,214.19 no change to contract time -$124,214
Other Administrative Action 2 · FT meade rockenbach no change to contract amount add 368 calendar days to contract time $0
Other Administrative Action 1 · FT meade rockenbach increase contract amount by $1,000,736.97 add 533 calendar days to contract time $1,000,737
Original award $8,084,044
Show all 15

Description

Fort george g. Meade rockenbach access control point project no.: fort meade rockenbach ACP this project is for the rockenbach access control point (ACP) into fort george g. Meade (fggm) in anne arundel county, maryland, and includes the design and construction of a new ACP at the intersection of rockenbach road and clark road, and other security improvements.

Quick answers

Who was awarded contract DTFH7113C00033?

DTFH7113C00033 was awarded to Slone Associates Inc. by Federal Highway Administration (Department of Transportation) on May 9, 2013.

How much is contract DTFH7113C00033 worth?

The government has obligated $9,607,851 on DTFH7113C00033. Its potential value, with all options, is $10,347,660.

Was contract DTFH7113C00033 competed?

The extent of competition for DTFH7113C00033 was full and open competition. The government received 12 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award