Foothills parkway PRA-foot 8E14, 8E16, 8E18, 8E19, 8E20, 8E22, and 8E12(1) is located in blount county, tennessee, northeast of the city of townsend. The proposed project is for the design and…

Ended Definitive Contract Awarded Last action

Contract number
DTFH7110C00037
Awardee
Awarding agency
Obligated
$48,287,038

Award facts

Opportunity
Contract value 100% obligated
$48,287,037.52 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Two Step
Pricing
Firm Fixed Price
Place of performance
Gatlinburg, TN 37738, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action 20 · The purpose of this no cost administrative modification is to financially and contractually close this contract in the amount of $48,287,037.52. $0
Close Out 19 · Total amount for this modification: -$440,962.22 new total amount for this award: $48,287,037.52 PRA-foot 8E14,16,18 CM #19 decrease contract amount by… -$440,962
Other Administrative Action 18 · GF:: PRA-foot 8E14,16,18 CM #18 no change to contract amount add 50 calendar days to contract time $0
Other Administrative Action 17 · GF:: PRA-foot 8E14-22 CM #17 decrease contract amount by $0.26 add 31 calendar days to contract time -$0
Other Administrative Action 16 · GF:: PRA-foot 8E14-22 CM #16 administrative no change to contract amount no change to contract time $0
Other Administrative Action 15 · GF:: PRA-foot 8E14-22 CM #15 no change to contract amount no change to contract time $0
Other Administrative Action 14 · GF:: PRA-foot 8E14-22 CM #14 no change to contract amount add 21 calendar days to contract time $0
Other Administrative Action 13 · GF:: PRA-foot 8E14-22 increase contract by $126,330.87 no change to contract time $126,331
Other Administrative Action 12 · GF:: PRA-foot 8E14-22 increase contract by $18,669.13 no change to contract time $18,669
Other Administrative Action 11 · GF:: PRA-foot 8E14-22 no change to contract amount no change to contract time $0
Other Administrative Action 10 · GF:: PRA-foot 8E14-22 no change to contract amount increase contract time by 548 calendar days $0
Other Administrative Action 9 · PRA-foot 8E14,16,18 no change to contract amount add 42 calendar days to contract time. 6125 tyvola centre drive charlotte, NC 28217 $0
Other Administrative Action 7 · PRA-foot 8E14,16,18 increase contract amount by $100,000.00 no change to contract time $100,000
Other Administrative Action 8 · PRA-foot 8E14,16,18 no change to contract amount no change to contract time $0
Other Administrative Action 6 · PRA-foot 8E14,16,18 the purpose of this modification is to correct the completion date on modification 005. Period of performance end date is corrected from… $0
Exercise an Option 5 · PRA-foot 8E14,16,18 DTFH71-10-C-00037 increase contract amount by $450,000.00. No change to contract time $7,416,000
Exercise an Option 3 · Recovery. Foothills parkway PRA-foot 8E14, 8E16, 8E18, 8E19, 8E20, 8E22, and 8E12(1) is located in blount county, tennessee, northeast of the city of… $6,335,000
Other Administrative Action 4 · PRA-foot 8E14,16,18 DTFH71-10-C-00037 increase contract amount by $450,000.00. No change to contract time $900,000
Funding Only Action 2 · Recovery. Increase arra funds by $221,754.10 in line item 0001 and decrease funds in F17E by the same amount. -$221,754
Funding Only Action A02 · Increase arra funds and decrease F17E fund cite. $221,754
Exercise an Option 1 · Recovery. Foothills parkway PRA-foot 8E14, 8E16, 8E18, 8E19, 8E20, 8E22, and 8E12(1) is located in blount county, tennessee, northeast of the city of… $6,189,275
Modification $20,181,459
Other Administrative Action A01 · This design build project consists of the design and construction of roads and five bridges on a new alignment. $7,461,266
Show all 23

About this award

This is a $48,287,037.52 firm fixed-price definitive contract awarded by the Federal Highway Administration, a civilian agency, to The Lane Construction Corporation, a subsidiary of the Italian company Webuild S.P.A. The contract is for the design and construction of a new road and five new bridges, as well as the removal of existing curb and installation of bridge rail on two existing bridges, and the construction of a stone masonry guardwall, for the Foothills Parkway project in Blount County, Tennessee. The terrain in the project area is described as mountainous and extremely difficult to access. This contract does not have a small business set-aside designation.

Description

Foothills parkway PRA-foot 8E14, 8E16, 8E18, 8E19, 8E20, 8E22, and 8E12(1) is located in blount county, tennessee, northeast of the city of townsend. The proposed project is for the design and construction of a new road and five new bridges. Additional work includes the removal of existing curb and installation of bridge rail on bridges 9 and 10 and the construction of stone masonry guardwall between bridges 7 and 8. The terrain is mountainous and extremely difficult to access with any vehicles.

Quick answers

Who was awarded contract DTFH7110C00037?

DTFH7110C00037 was awarded to The Lane Construction Corporation by Federal Highway Administration (Department of Transportation) on September 9, 2010.

How much is contract DTFH7110C00037 worth?

The government has obligated $48,287,038 on DTFH7110C00037.

Was contract DTFH7110C00037 competed?

The extent of competition for DTFH7110C00037 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award