Recovery, the project consists of the slope stabilization and rockfall mitigation of the slide area at lehigh GAP along the appalachian national scenic trail. The work includes rock excavation and…
Ended Definitive Contract Awarded Last action
- Contract number
- DTFH7110C00021
- Awardee
-
Janod Inc. UEI H3JXA8GKPST3
- Awarding agency
-
Federal Highway Administration
Department of Transportation
- Obligated
- $5,665,818
Award facts
- Opportunity
-
- DTFH7110R00011 Solicitation number
- RECOVERY - Appalachian National Scenic Trail, APPA - Lehigh Gap Award Notice · Posted Mar 9, 2010
- Contract value 100% obligated
- $5,665,817.90 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- C122 Highway, Roads, Streets, Bridges, A
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 3 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Palmerton, PA, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Close Out | $0 | |
| Other Administrative Action | -$164,684 | |
| Other Administrative Action | -$106,481 | |
| Other Administrative Action | $2,099,985 | |
| Other Administrative Action | $0 | |
| Original award | $3,836,998 |
About this award
This is a firm fixed-price definitive contract awarded by the Federal Highway Administration, a civilian agency, to Janod Inc. for the recovery, slope stabilization, and rockfall mitigation project along the Appalachian National Scenic Trail at Lehigh Gap in Palmerton, Pennsylvania. The $5,665,817.90 contract does not have a set-aside designation and includes rock excavation, blasting, slope scaling, rock bolting, grouting, shotcrete, rockfall protection, drainage improvements, and other miscellaneous work. The contract was awarded on May 13, 2010 with a ultimate completion date of November 20, 2014 under the Appalachian National Scenic Trail major program.
Description
Recovery, the project consists of the slope stabilization and rockfall mitigation of the slide area at lehigh GAP along the appalachian national scenic trail. The work includes rock excavation and blasting, slope scaling, rock bolting, grouting, shotcrete, rockfall protection, drainage improvements, and other miscellaneous work.
Quick answers
Who was awarded contract DTFH7110C00021?
DTFH7110C00021 was awarded to Janod Inc. by Federal Highway Administration (Department of Transportation) on May 13, 2010.
How much is contract DTFH7110C00021 worth?
The government has obligated $5,665,818 on DTFH7110C00021.
Was contract DTFH7110C00021 competed?
The extent of competition for DTFH7110C00021 was full and open competition. The government received 3 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award