The project consists of the resurfacing of approximately 0.7 miles of forest highway 30 (choctaw lake road) between choctaw lake and forest highway 29 (webster road) in tombigbee national forest.…

Ended Definitive Contract Awarded Last action

Contract number
DTFH7110C00011
Awardee
Awarding agency
Obligated
$570,026

Award facts

Opportunity
Contract value 100% obligated
$570,025.51 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 7 offers Sealed Bid
Pricing
Fixed Price Incentive
Place of performance
Ackerman, MS 39735, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 4 · MS PFH 030-1(002) the purpose of this no cost modification is to financially and contractually close thiscontract. $0
Change Order 3 · Change award date MS PFH 030-1(002) the contract is decreased by $45,393.59. Add 22 calendar days to contract time. -$45,454
Other Administrative Action 2 · Add additional funding to base contract cost. Add 59 calendar days to contract time. $74,929
Other Administrative Action 1 · No change to base contract cost. Add 60 calendar days to contract time. $0
Modification $109,779
Funding Only Action A01 · Recovery, the project consists of the resurfacing of approximately 0.7 miles of forest highway 30 (choctaw lake road) between choctaw lake and forest highway 29… $430,771

About this award

This federal contract was awarded by the Federal Highway Administration, a civilian agency, to Ausbern Construction Co Inc., a self-certified small disadvantaged business, for the resurfacing of approximately 0.7 miles of Forest Highway 30 (Choctaw Lake Road) in Tombigbee National Forest. The $570,025.51 fixed-price incentive contract includes roadway excavation, aggregate base, Superpave hot asphalt concrete pavement, and other miscellaneous work. The project is part of the Tombigbee National Forest major program. The contract has a completion date of October 18, 2011 and was awarded on January 27, 2010. No set-aside was used for this award.

Description

The project consists of the resurfacing of approximately 0.7 miles of forest highway 30 (choctaw lake road) between choctaw lake and forest highway 29 (webster road) in tombigbee national forest. The work includes roadway excavation, aggregate base, superpave hot asphalt concrete pavement, and other miscellaneous work.

Quick answers

Who was awarded contract DTFH7110C00011?

DTFH7110C00011 was awarded to Ausbern Construction Company, Inc. by Federal Highway Administration (Department of Transportation) on January 27, 2010.

How much is contract DTFH7110C00011 worth?

The government has obligated $570,026 on DTFH7110C00011.

Was contract DTFH7110C00011 competed?

The extent of competition for DTFH7110C00011 was full and open competition. The government received 7 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award