The project consists of the rehabilitation and resurfacing of bluff lake road, brooksville-louisville road, and section line road within the noxubee national wildlife refuge. The work on bluff lake…

Ended Definitive Contract Awarded Last action

Contract number
DTFH7109C00018
Awardee
Awarding agency
Obligated
$4,638,751

Award facts

Opportunity
Contract value 100% obligated
$4,638,750.55 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Sealed Bid
Pricing
Fixed Price Incentive
Place of performance
Jackson, MS 39272, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 9 · The purpose of this administrative modification is to financially and contractually close the subject contract in the amount of $4,638,750.55. $0
Change Order 8 · Finalized quantities; added 316 calendar days -$38,400
Change Order 7 · Added crack sealing, delinieators, fuel & asphalt price escalation and adjuested other pay item quantities. -$134,610
Change Order 6 · NXB 10(1) - add'l road stabilization/ added pavement rehab / added box culvert/ remove smoothness incentive/ added 60 CD $568,566
Other Administrative Action 5 · CM #5 corrects contract amount after CM#4 $0
Change Order 4 · NXB 10(1) - full depth reclamation / micro-cracking / reduce some item quantities -$658
Change Order 3 · Added arra reporting specification $0
Other Administrative Action 2 $0
Funding Only Action A01 · Recovery, , the project consists of the rehabilitation and resurfacing of bluff lake road, brooksville-louisville road, and section line road within the noxubee… $1,416,557
Funding Only Action 1 -$28,688
Original award $2,855,983
Show all 11

About this award

This is a federal contract awarded by the Federal Highway Administration (FHWA), a civilian agency, to Superior Asphalt, Inc. for the rehabilitation and resurfacing of roads within the Noxubee National Wildlife Refuge. The $4,638,750.55 fixed-price incentive contract includes selective full-depth pavement reconstruction, asphalt pavement milling, and Superpave asphalt concrete pavement overlay on Bluff Lake Road and Brooksville-Louisville Road, as well as aggregate surface reconditioning and widening on Section Line Road. The contract also includes drainage improvements and other miscellaneous work. The contract does not have a set-aside designation and was awarded on June 29, 2009 with a final completion date of September 20, 2011.

Description

The project consists of the rehabilitation and resurfacing of bluff lake road, brooksville-louisville road, and section line road within the noxubee national wildlife refuge. The work on bluff lake road and brooksville-louisville road includes selective full-depth pavement reconstruction, asphalt pavement milling, and superpave asphalt concrete pavement overlay. The work on section line road includes aggregate surface reconditioning and widening. All roads include drainage improvements and other miscellaneous work.

Quick answers

Who was awarded contract DTFH7109C00018?

DTFH7109C00018 was awarded to Superior Asphalt, Inc. by Federal Highway Administration (Department of Transportation) on June 29, 2009.

How much is contract DTFH7109C00018 worth?

The government has obligated $4,638,751 on DTFH7109C00018.

Was contract DTFH7109C00018 competed?

The extent of competition for DTFH7109C00018 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award