Recovery, , construction contract for roadway work on AZ\UT NPS glca-pres-1(09), glen canyon national recreation area pavement preservation arra::yes::arra

Ended Definitive Contract Awarded Last action

Contract number
DTFH6809C00043
Awardee
Awarding agency
Obligated
$3,867,516

Award facts

Opportunity
Contract value 100% obligated
$3,867,516.38 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 6 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Page, AZ 86040, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action CM015 · Final deobligation for project closeout -$21,465
Additional Work (new agreement, FAR part 6 applies) CM014 · Additional type 2 microsurfacing and intersection work $0
Change Order CM013 · Provides funding for anticipated changes to be definitized by a bilateral modification at a later date. $22,000
Additional Work (new agreement, FAR part 6 applies) CM012 · Corrective action to repair excessive bleeding $0
Additional Work (new agreement, FAR part 6 applies) CM011 · Substitutes micro-surfacing, type 2 for micro-surfacing, type 3 at specified locations $0
Additional Work (new agreement, FAR part 6 applies) CM010 · Addition of 2 loose gravel signs and stands $0
Additional Work (new agreement, FAR part 6 applies) CM009 · Remobilization due to changes in microsurfacing $0
Additional Work (new agreement, FAR part 6 applies) CM007 · Reduced payment for several microsurfaced parking lots $0
Additional Work (new agreement, FAR part 6 applies) CM008 · Additional aggregate surface course -$51
Additional Work (new agreement, FAR part 6 applies) CM006 · Decrease in quantities -$291,400
Additional Work (new agreement, FAR part 6 applies) CM005 · Eliminates work on route 5 & adds additional work on other routes $0
Additional Work (new agreement, FAR part 6 applies) CM004 · Additional haul costs for chip seal $0
Change Order CM003 · Time extension of 17 days due to late issuance of NTP $0
Change Order CM002 $0
Change Order CM001 $0
Original award $4,158,433
Show all 16

About this award

This is a $3,867,516.38 firm fixed price contract awarded by the Federal Highway Administration, a civilian agency, to Intermountain West Civil Constructors Inc., a U.S. Small Business Administration (SBA) certified HUBZone firm, for roadway construction and pavement preservation work on the Glen Canyon National Recreation Area in Arizona and Utah. The contract is associated with the AZ/UT NPS GLCA-PRES-1(09) major program and was funded through the American Recovery and Reinvestment Act (ARRA). The work is to be completed by May 4, 2012.

Quick answers

Who was awarded contract DTFH6809C00043?

DTFH6809C00043 was awarded to Intermountain West Civil Constructors Inc. by Federal Highway Administration (Department of Transportation) on September 29, 2009.

How much is contract DTFH6809C00043 worth?

The government has obligated $3,867,516 on DTFH6809C00043.

Was contract DTFH6809C00043 competed?

The extent of competition for DTFH6809C00043 was full and open competition after exclusion of sources. The government received 6 offers. It was set aside: HUBZone.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award