Recovery, , construction of SD PRA badl 10(5), badlands loop road. 14.552 miles of 3-R rehabilitation, reconstruction, paving, and drainage.

Ended Definitive Contract Awarded Last action

Contract number
DTFH6809C00037
Awardee
Awarding agency
Obligated
$10,663,915

Award facts

Opportunity
Contract value 100% obligated
$10,663,914.92 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 7 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Rapid City, SD 57701, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action CM019 · Final deob for project closeout -$1,009,502
Additional Work (new agreement, FAR part 6 applies) CM018 · Asphalt pavement price reduction $0
Additional Work (new agreement, FAR part 6 applies) CM011 · Traffic signs $0
Additional Work (new agreement, FAR part 6 applies) CM012 · Fence & fence materials $0
Additional Work (new agreement, FAR part 6 applies) CM005 · Deletes MTV $0
Additional Work (new agreement, FAR part 6 applies) CM004 · Change of table 402-7 in library of specifications $0
Additional Work (new agreement, FAR part 6 applies) CM010 · Change in work required at doors & windows parking area. $0
Other Administrative Action CM014 · Removes F170 funds from the contract -$122,394
Other Administrative Action CM013 · Adds 15F funds to the contract $122,394
Additional Work (new agreement, FAR part 6 applies) CM007 · Cedar pass lodge parking area $0
Additional Work (new agreement, FAR part 6 applies) CM008 · Increase in asphalt paving $0
Change Order CM003 · Recovery, . Roadway construction contract -$22,072
Supplemental Agreement for work within scope CM002 · DTFH68-09-C-00037 $969
Other Administrative Action CM001 $0
Other Administrative Action 0A · Construction of SD PRA badl 10(5), badlands loop road. 14.552 miles of 3-R rehabilitation, reconstruction, paving, and drainage. $3,381,563
Original award $8,312,957
Show all 16

About this award

This is a federal contract award from the Federal Highway Administration (FHWA), a civilian agency, to Duininck Inc. for the recovery, rehabilitation, reconstruction, paving, and drainage of the Badlands Loop Road in South Dakota. The contract has a ceiling value of $10,663,914.92 and is a definitive, firm-fixed price contract. There is no set-aside designation for this award. The contract was awarded on September 1, 2009 with an ultimate completion date of April 9, 2012. The place of performance is Rapid City, South Dakota.

Quick answers

Who was awarded contract DTFH6809C00037?

DTFH6809C00037 was awarded to Duininck Inc. by Federal Highway Administration (Department of Transportation) on September 1, 2009.

How much is contract DTFH6809C00037 worth?

The government has obligated $10,663,915 on DTFH6809C00037.

Was contract DTFH6809C00037 competed?

The extent of competition for DTFH6809C00037 was full and open competition. The government received 7 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities