Fencing, site stabilization and drainage work at bismarck substation, ND

Ended Definitive Contract Awarded Last action

Contract number
DEAC6511WC92377
Awardee
Awarding agency
Obligated
$256,473

Award facts

Opportunity
Contract value 100% obligated
$256,473.49 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237130 Power and Communication Line and Related Structures Construction
PSC
Not on record
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 4 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Bismarck, ND 58502, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A003 · Replace trap primer, reroute water piping and insulate water piping. $2,831
Supplemental Agreement for work within scope A002 · Add a new gate for an access road, install access road and provide conduit from transformer to drain sump at bismarck substation, ND $35,717
Original award $217,925

Quick answers

Who was awarded contract DEAC6511WC92377?

DEAC6511WC92377 was awarded to Anderson & Wood Construction Co Inc. by Western Area Power Administration (Department of Energy) on August 18, 2011.

How much is contract DEAC6511WC92377 worth?

The government has obligated $256,473 on DEAC6511WC92377.

Was contract DEAC6511WC92377 competed?

The extent of competition for DEAC6511WC92377 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award