This contract modification increases the not-to-exceed ceiling value from $600 million to $800 million for the Waste Treatment Plant High-Level Waste Facility, Design Completion Period Phase 1A. This is a cost-plus-incentive-fee definitive contract awarded by the U.S. Department of Energy's Office of Environmental Management to Bechtel National, Inc., a subsidiary of Bechtel Corporation. The contract supports the design completion for the waste treatment facility, with a revised ultimate completion date of July 18, 2025. The contract was originally awarded on December 15, 2000 and does not have a set-aside designation.