Definitive Contract AG82B1C100392

Award Date 9/21/10
Potential Completion Date 8/31/11
Potential Value $224K
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
Total Small Business
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Kalispell, MT 59901, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
3
Legislative Mandate
Not listed
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
<p>This is a firm-fixed-price definitive contract awarded by the Operations Center Intermountain, a civilian agency, to M.L. Albright &amp; Sons, Inc., a self-certified small disadvantaged business. The contract, worth $164,813.35, is for the TAS-RECOVERY FUNDED-CIM-08R PROJECT 17 - WILDERNESS GATEWAY BRIDGE MTNCE and has an ultimate completion date of July 1, 2011. The contract was awarded on August 12, 2010 and does not have a set-aside designation.</p>
This is a federal contract award from the Operations Center Intermountain, a civilian agency, to Timberline Contracting Inc., a self-certified small disadvantaged business. The contract is for the TAS 2010 RECOVERY FUNDS WF THOMPSON RIVER BRIDGE REPAIRS project, with a ceiling value of $89,524.00. The contract is a definitive contract with a firm fixed price, and the place of performance is Missoula, MT. The contract has a set-aside designation for total small business and a completion date of...
This is a $960,657.43 firm fixed-price definitive contract awarded by the Operations Center Intermountain, a civilian agency of the U.S. federal government, to Stone Ridge Construction, Inc., a for-profit organization that is an SBA Certified HUBZone firm. The contract was awarded on July 8, 2010 with an ultimate completion date of October 21, 2012. The contract does not have a set-aside designation. Without additional information about the original solicitation, the specific products or...
This is a firm fixed-price purchase order awarded by the U.S. Department of the Interior's Bureau of Land Management (BLM) Utah Region to Feller Enterprises, LLC for $36,845.00 to perform recovery-related North Creek Bridge repairs. The contract has a total small business set-aside designation and a performance period ending on July 31, 2010. The award was made on April 13, 2010 under the RECOVERY-NORTH CREEK BRIDGE REPAIRS major program. No additional subcontractors or prime awardees were...
<p>This is a $3,154,725.79 firm-fixed-price definitive contract awarded by the Operations Center Intermountain, a civilian agency, to W Construction LLC for capital improvement and maintenance services. The contract is funded through the American Recovery and Reinvestment Act (ARRA) and is for work on the Cascade Baer West Fork Rock Creek Road #2071 in Red Lodge, Montana. The contract does not have a set-aside designation.</p>
This is a definitive, firm fixed-price contract awarded by the Operations Center Intermountain, a civilian federal agency, to Latigo Construction Inc., a service-disabled veteran-owned small business. The contract, valued at $372,340.00, is for the TAS TAYLOR FORK AGGREGATE PLACEMENT ARRA project, which is part of the American Recovery and Reinvestment Act (ARRA) program. The work is to be performed in Bozeman, MT and has an ultimate completion date of October 1, 2009. No additional details...
<p>This is a federal contract award for $283,195.00 made by the Operations Center Intermountain, a civilian agency, to Triple Tree Inc., a for-profit organization. The contract is for native surface reconditioning of Road 500 and is funded by the agency's 2010 recovery funds under the CIM-0100-10R and CIM-0105-24R programs. The contract has a firm fixed price and is a delivery order with an ultimate completion date of October 15, 2011. The contract does not have a set-aside designation.</p>
This is a $105,600.52 Firm Fixed Price Definitive Contract awarded by the Operations Center Intermountain, a civilian agency, to Leavco Inc., a for-profit organization, for the RECOVERY: CABINET ROAD DECOMMISSIONING project. The contract has a set-aside designation for Total Small Business. The award is for a road decommissioning effort under the American Recovery and Reinvestment Act (ARRA) and is scheduled for completion by February 28, 2011. No information about major subcontractors is...
<p>This is a firm fixed-price definitive contract awarded by the Operations Center Intermountain, a civilian agency, to Big Sky Development, Inc., a self-certified small disadvantaged business. The $159,152.50 contract is for &quot;ACCESS MGMT IMPLEMENTION&quot; as part of the agency's &quot;RECOVERY FUNDS--CIM-0104-16R,CIM-0104-12&quot; program. The contract was set aside for total small business participation and has an ultimate completion date of August 15, 2011.</p>
This is a definitive, firm fixed-price federal contract awarded by the U.S. Department of Agriculture's Operations Center Intermountain to Stone Ridge Construction, Inc., a Small Business Administration (SBA) certified HUBZone firm. The contract is for the ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE program and involves the RECOVERY ROAD 250 SURFACE STABILIZATION ARRA-CIM-0105-08R PROJECT 28, with a ceiling value of $489,625.07 and an ultimate completion date of August 30, 2010. The contract was...

This is a Definitive Contract awarded by the Operations Center Intermountain, a Civilian agency, to Frontier West, LLC, a For Profit Organization and Limited Liability Company. The contract has a Firm Fixed Price pricing type and a Ceiling Value of $224,410.00. It was awarded on September 21, 2010 with an Ultimate Completion Date of August 31, 2011.

The contract is for RECOVERY: TAS::12 1102::TAS (ARRA CIM-0110-02R-14) RD. #2895 LOGAN CR. BRIDGE RECONSTRUCTION, which is part of the ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE major program. The contract is set aside for Total Small Business.