Definitive Contract AG82B1C100308
Award Date 7/26/10
Potential Completion Date 11/12/10
Potential Value $304K
Federal Agency
Ultimate Awardee
Not listed NAICS Category
PSC Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
HUBZone
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Grangeville, ID 83530, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
2
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a federal contract award for $118,999.64 to Roadtech Inc., a for-profit manufacturer, by the Operations Center Intermountain, a civilian agency of the U.S. government. The contract is for the resurfacing of Road 202 under the ARRA (American Recovery and Reinvestment Act) Forest Wide BMPs (Best Management Practices) program, which falls under the ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE major program code. The contract has a Firm Fixed Price pricing type and a definitive contract type,...
- This is a definitive, firm fixed-price federal contract awarded by the U.S. Department of Agriculture's Operations Center Intermountain to Stone Ridge Construction, Inc., a Small Business Administration (SBA) certified HUBZone firm. The contract is for the ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE program and involves the RECOVERY ROAD 250 SURFACE STABILIZATION ARRA-CIM-0105-08R PROJECT 28, with a ceiling value of $489,625.07 and an ultimate completion date of August 30, 2010. The contract was...
- <p>This is a federal contract awarded by the Operations Center Southwest, a civilian agency, to A & S Paving, Inc., a minority-owned, small disadvantaged business. The $484,502.57 Firm Fixed Price contract is for an ARRA (American Recovery and Reinvestment Act) project to crush, haul, and place aggregate surfacing material for approximately 12 miles of National Forest System Road 150. The contract was set aside for small businesses and has a completion date of February 23, 2011.</p>
- This is a federal contract awarded by the Operations Center Northwest, a civilian agency, to Belsaas & Smith Construction Inc., a for-profit Subchapter S Corporation, to perform the RECOVERY ROAD 9737 RESURFACING project. The contract, which has a Ceiling Value of $179,039.77, consists of resurfacing 2.14 miles of Forest Road with crushed aggregate, including reconditioning the existing roadway and ditches. The contract is a Definitive Contract with a Firm Fixed Price pricing type, and has a...
- <p>This is a $1,230,718.50 firm fixed-price definitive contract awarded by the Operations Center Intermountain, a civilian agency, to Sweat, Robert (doing business as Sweat) for the Big Creek Project - Roadside Hazard Tree Removal. The contract is funded through the American Recovery and Reinvestment Act (ARRA) for Wildland Fire Management. This 8(a) sole source contract has an ultimate completion date of October 15, 2009.</p>
- This is a Firm Fixed Price Delivery Order contract awarded by the U.S. Department of Agriculture (USDA) to Colorado River Materials, Inc., a Certified HUBZone Small Business, for road maintenance and repair services in Marana, Arizona. The contract has a ceiling value of $467,007.11 and is funded through the American Recovery and Reinvestment Act (ARRA) under the ROAD MAINTENANCE, IDIQ, SUPPLIES AND SERVICES major program code. The contract was set aside for Total Small Business participation...
- This is a $48,794.00 firm fixed price definitive contract awarded by the U.S. Department of Agriculture's Operations Center Intermountain to R & R Conner, Inc., a for-profit subchapter S corporation. The contract is for ARRA-FS CAPITAL IMPROVEMENT AND MAINTENANCE and does not have a set-aside designation. The contract's ultimate completion date is June 6, 2011. The contract is for GRAVEL STOCKPILES, ITEMS FOR AG-82B1-S-10-0003 under the TAS RECOVERY CIM-0103-14R ARRA program. No major...
- This is a firm fixed-price definitive contract awarded by the USDA Forest Service to Mark Agee Excavation LLC, a HUBZone small business, to perform road decommissioning work on the Recovery Red Pines Road as part of the American Recovery and Reinvestment Act (ARRA) Capital Improvement and Maintenance program. The contract has a ceiling value of $199,940.05 and a completion date of December 2, 2011. Mark Agee Excavation is a veteran-owned excavation services provider that has previously...
- This is a federal contract award by the Operations Center Southwest, a civilian agency, to Bertagnolli Paving, a SBA-certified HUBZone firm. The $188,397.93 firm-fixed-price contract is for stormproofing forest system roads on the 860-25 and 860-35 systems, including construction or maintenance of drainage structures, surface stabilization, aggregate placement, realignment, and boulder placement. The contract has a completion date of July 20, 2011 and was awarded on July 22, 2010. This...
- This is a firm fixed-price purchase order contract awarded by the Operations Center Southwest, a civilian federal agency, to K.C. Equipment, Inc., a woman-owned small business. The contract, valued at $162,177.00, is for a road maintenance project that includes paving, chipseal, and surfacing work under the American Recovery and Reinvestment Act (ARRA) program. The contract has a period of performance ending on September 2, 2010 and was awarded on December 22, 2009. The contract is designated as...
This is a firm fixed-price definitive contract awarded by the United States Forest Service, a civilian agency, to Acme Asphalt Industries Inc., a for-profit subchapter S corporation, for the Recovery Coolwater Road Reconstruction project under the American Recovery and Reinvestment Act (ARRA) Capital Improvement and Maintenance program. The contract has a ceiling value of $303,676.95 and a completion date of November 12, 2010. The contract was set aside for the HUBZone program.
Generated 4/2/25, 10:14 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
RECOVERY:: COOLWATER ROAD RE-CONSTRUCTION PROJECT PHASE II | AG-82B1-S-10-0412 | Department of Agriculture Forest Service Washington Office Economic Recovery Operations Center Intermountain | Award Notice 1/1 | 5/19/10, 7:21 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 2 | Close Out | ($7k) | 4/4/12 | |
| 1 | Supplemental Agreement for work within scope | $1.5k | 9/20/10 | |
| Not listed | Not listed | $309.5k | 7/26/10 |