Definitive Contract AG5F48C090012
Award Date 9/16/09
Potential Completion Date 12/7/09
Potential Value $49K
Funding Federal Agency
Not listed Contracting Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Not listed Set-Aside Type
Total Small Business
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Brandon, WI 53919, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
4
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Department of Defense Army Corps of Engineers awarded a $469,842.64 delivery order contract to Applied Aquatic Management, Inc., doing business as Applied Aquatic Management Inc., to perform the Natural Resources Conservation Service Westby 1 Wetlands Restoration Project in Lake Placid, Florida. The firm fixed price contract runs from May 18, 2022 through May 16, 2023 and involves sodding, seeding and fencing to restore wetlands as part of the Wetlands Reserve Program. No subcontractors were...
- Phylway Construction, L.L.C. was awarded a $5.1 million firm fixed price contract by the United States Army Corps of Engineers New Orleans District to perform site preparation work in support of coastal restoration efforts. Under the West Shore Lake Pontchartrain Site Preparation & Sand Placement Contract #2, Phylway will clear and grade land, remove stumps, and place approximately 58,505 linear feet of sand fill to an elevation of 3.0 feet in a marsh area. The contract also includes...
- The Department of the Army Corps of Engineers awarded a $4.2 million firm fixed price contract to HSG Park Joint Venture, LLC for wetland restoration work as part of the Fargo Moorhead Metropolitan Area Flood Risk Management Project. The solicitation sought bids for base scope work and optional additional demolition, excavation, and installation of temporary cover crops to restore wetlands in Drain 27 near Horace, North Dakota. As a total small business set-aside, the contract supports the...
- Rod Transport Inc., operating as Rod Construction, was awarded a $6.86 million firm fixed price contract by the U.S. Army Corps of Engineers on June 5, 2023, to execute Phase II of the Dry Creek Ecosystem Restoration Project near Healdsburg, California. The contract, designated as a HUBZone set-aside, requires construction of restoration reaches 4C, 2B, and 2A-Upstream along approximately 2.6 miles of stream and floodplain habitat downstream of Warm Springs Dam. Rod Construction, a certified SBA...
- The U.S. Department of Agriculture's Natural Resources Conservation Service Central Region awarded a $1.647 million firm fixed price delivery order contract to Tunheim Construction, LLC of St. Paul, Minnesota. The contract is for WRP Easement Construction in Minnesota and will involve wetland restoration projects through the agency's Wetlands Reserve Program. Work will be performed in St. Paul and is required to be completed by March 31, 2021. No subcontractors or set aside designations were...
- This firm fixed-price, definitive contract was awarded by the USDA Farm Production and Conservation (FPAC) Operations Branch, Acquisition Division to Wondra Construction Inc., a self-certified small disadvantaged business, for the construction and restoration of the Prince's Point wetland in Jefferson County, Wisconsin. The $6,432,425.84 contract includes the construction of four wetland management basins, shallow scrapes and islands, water control structures, and access road and bridge...
- Weeks Marine, Inc. was awarded a $15.1 million firm fixed price construction contract by the United States Department of Agriculture Natural Resources Conservation Service Southeast Region. The contract is for the South Grand Chenier Marsh Creation Project in Cameron Parish, Louisiana. Under the contract, Weeks Marine will excavate over 856,000 cubic yards of material from the Gulf of Mexico to create 386 acres of new coastal wetland marsh across two cells, with containment dikes totaling...
- The Department of the Army Corps of Engineers Engineering District New York awarded a Firm Fixed Price contract for $13,341,014.00 to Jrcruz Corp. for the construction of the Old Place Creek Wetland Site in Richmond County, Staten Island, New York. The contract, which does not have a set-aside designation, involves the restoration of approximately 15 acres of inter-tidal salt marsh and 11 acres of scrub-shrub and maritime upland habitat. The work generally includes installation of erosion and...
- This is a firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers, Walla Walla District (ENDIST Walla Walla) to L D Perry Inc., a HUBZone contractor, for the Camp Creek Environmental Restoration project at the Zumwalt Prairie Preserve in Enterprise, Oregon. The contract, valued at $220,957.00, is an American Recovery and Reinvestment Act (ARRA) project with a completion date of October 15, 2010. The contract scope involves environmental restoration work at the preserve.
- The U.S. Department of the Interior Fish and Wildlife Service Region 5 awarded a $3,056,767.00 firm-fixed-price delivery order contract to WSP USA Environment & Infrastructure Inc. for the Hurricane Sandy design and construction of marsh restoration at Reeds Beach and Supawana Meadows. This work is funded through the Disaster Relief Appropriations Act of 2013 (Hurricane Sandy relief). WSP USA Environment & Infrastructure Inc. is a for-profit engineering and professional services firm...
CONSTRUCTION OF THE LAPER/WESTRA/GAY WETLAND RESTORATION PROJECT
Posted 9/16/09
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Construction of the Laper/Westra/Gay Wetland Restoration Project | AG-5F48-S-09-0004 | Department of Agriculture National Resources Conservation Service | Award Notice 1/1 | 8/24/09, 11:06 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 1 | Change Order | $18.0k | 12/4/09 | |
| Not listed | Not listed | $31.4k | 9/16/09 |