Definitive Contract AG569RC100021

Award Date 8/12/10
Potential Completion Date 12/21/10
Potential Value $123K
Ultimate Awardee
Not listed
PSC Category
Not listed
Federal Contract Vehicle
Set-Aside Type
HUBZone
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Medford, WI 54451, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
5
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This delivery order, awarded under the Department of Agriculture Forest Service R9-Eastern Region Roads and General Construction Multiple Award IDIQ, calls for the replacement of an existing failing stream crossing with a new larger culvert in Lily Pad Creek. Snow Country Contracting Inc., an SBA-certified HUBZone firm, will replace the culvert for $114,016.98 by May 15, 2022. The work supports the Forest Service's efforts to improve infrastructure and protect water quality in the Great Lakes...
The U.S. Department of Agriculture Forest Service awarded a $219,160 firm fixed price delivery order to Ketchikan Ready-Mix & Quarry, Inc. to remove and dispose of an existing corrugated metal pipe on Road 3036 at milepost 0.27 in Coffman Cove, Alaska and replace it with a 55-foot structural plate arch culvert composed of a corrugated metal arch and concrete footings. The contractor will also restore the streambed upstream and downstream. There was no set-aside designation for this award...
This is a firm fixed-price federal contract awarded by the U.S. Department of Agriculture Forest Service to M R Construction, a small disadvantaged and HUBZone certified business, to replace a culvert on Forest Service road 40N39 that crosses Kelly Gulch in the Klamath National Forest near Etna, California. The contract, valued at $475,417.50, involves installing a 15-foot span by 6-foot 7-inch rise multi-plate arch culvert with a simulated streambed to allow for aquatic organism passage. This...
The U.S. Federal Highway Administration (FHWA) awarded a $3,448,512.00 firm fixed-price contract to D & L Construction Co Inc., a veteran-owned small business, for the replacement of the Sourdough Creek Campground Bridge located 25 miles north of Glennallen, Alaska. The project involves constructing a new approximately 100-foot long precast concrete bridge, reconstructing the bridge approaches, and installing a temporary bypass bridge during construction. This contract does not have a...
The Bureau of Land Management Oregon-Washington awarded a $272,560 firm fixed price contract to Billeter Marine LLC for the removal of an existing 42-inch diameter corrugated metal pipe and replacement with a 70-foot long by 18-foot wide galvanized steel bridge. The solicitation sought proposals to perform clearing, grubbing, constructing a stream bypass, dewatering, excavating bedrock, building geosynthetic soil abutments, placing eco-block foundations, and restoring the roadway. This total...
The United States Department of Agriculture Forest Service awarded a $804,530 firm fixed price delivery order contract to Rock-N-Road Construction Inc. to perform back loop aquatic organism passage construction work in Petersburg, Alaska. The work consists of removing an existing culvert on Road 3030110 at milepost 0.28 and replacing it with a 49 foot steel bridge and constructing a new simulated streambed, as well as removing an existing culvert on Road 30 and constructing the required...
The United States Department of Agriculture Forest Service, Northern Region awarded a $315,080 firm fixed price delivery order contract to Stone Ridge Construction, Inc. The project is located on Forest Road No. 282 at milepost 10.00 at the crossing of the North Fork of Little Joe Creek in Trout Creek, Montana. Improvements consist of but are not limited to the removal and salvage of the existing multi-plate steel plate arch culvert and concrete structure. The period of performance is from...
Rickabaugh Construction LLC was awarded a $242,000 firm fixed price delivery order against the Department of the Interior Bureau of Land Management's Horizontal Repair and Construction Services Multiple Award Task Order Contract (MATOC) to complete the Sandy Creek Culvert Replacement project in North Bend, Oregon. Under this delivery order issued by the BLM Oregon-Washington office, Rickabaugh Construction will replace an existing culvert as part of the agency's infrastructure maintenance and...
<p>This is a $600,499.24 firm fixed price definitive contract awarded by the Operations Center Northwest, a civilian federal agency, to Laskey-Clifton Corporation, a U.S. Small Business Administration certified HUBZone firm. The contract is for the removal of a culvert and replacement with a concrete voided slab on piles bridge, as well as utility work, on the Eel Creek Bridge in Florence, Oregon. The contract has an ultimate completion date of August 19, 2011.</p>
This is a definitive contract with a firm fixed price of $140,412.00 awarded by the U.S. Department of Agriculture Forest Service's Pacific Northwest Region (Region 6) to Henderson Logging, Inc., a for-profit subchapter S corporation based in Wallowa, Oregon. The contract is for the Sage Creek Culvert Replacement project on the Wallowa-Whitman National Forest. The work requires the removal and disposal of an existing 48-inch culvert structure and the installation of a 14-foot span bottomless...

SAILOR CREEK CULVERT REPLACEMENT

Posted 8/12/10, 12:00 AM