Definitive Contract AG52KYC100002

Award Date 6/3/10
Potential Completion Date 10/11/11
Potential Value $473K
Federal Agency
Central Region
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Terre Haute, IN, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
5
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
<p>This is a $228,129.00 firm fixed price definitive contract awarded by the United States Department of Agriculture (USDA) to S&amp;S Trenching Inc. for the construction of two small floodwater retarding structures in the Upper Locust Creek Watershed, located in Putnam and Sullivan Counties, Missouri. The contract does not have a set-aside designation and is for Civilian agency work. The contract was awarded on July 31, 2009 with a target completion date of March 1, 2011.</p>
This is a $47,002.05 firm-fixed-price purchase order contract awarded by the U.S. Department of Agriculture to Siegler Grading &amp; Excavating LLC, a small business, for the WALWORTH COUNTY EMERGENCY WATERSHED PROTECTION PROGRAM-FLOODPLAIN EASEMENT (EWPP-FPE) CONSTRUCTION PROJECT in Walworth County, Wisconsin. The contract has a completion date of September 30, 2010. The EWPP is a USDA Natural Resources Conservation Service program that provides technical and financial assistance to help...
The federal contract AG6424C100007 was awarded by the USDA's Central Region agency to Double S Dirt Works, Inc., a woman-owned small business, for the rehabilitation of a floodwater retarding structure in Newton County, Missouri. The firm-fixed-price contract, with a ceiling value of $192,247.76, requires the contractor to perform the work per the provided contract clauses, provisions, specifications, and designs. The contract does not have a set-aside designation and has an ultimate...
This is a firm fixed price definitive contract awarded by the United States Department of Agriculture (USDA) to Keith Contracting, L.L.C., a minority-owned and small disadvantaged business, for the rehabilitation of three floodwater retarding structures in Carroll County, Missouri. The contract has a ceiling value of $305,805.50 and a completion date of April 1, 2011. The contract was set aside for a HUBZone sole source provider. The project is part of the USDA's RECOVERY, BIG CREEK HURRICANE...
This federal contract award, with a ceiling value of $240,076.20, was issued by the Central Region of the U.S. Department of Agriculture (USDA) to Hammett Excavation, Inc. The contract is for the Recovery Funded Mitigation on Caney Creek Watershed Site 3A, which involves installing two rock drop structures, fencing, and vegetating disturbed areas. The contract is a definitive, firm-fixed-price contract with a period of performance through November 3, 2010. The award did not utilize a small...
This is a $94,443.75 firm fixed-price definitive contract awarded by the U.S. Department of Agriculture's (USDA) Natural Resources Conservation Service (NRCS) to Doug Construction Koch for the construction of two Emergency Watershed Protection Program (EWPP) - Floodplain Easement wetland sites in Livingston and Linn Counties, Missouri. The project, which does not have a set-aside designation, is part of the American Recovery and Reinvestment Act (ARRA) and is expected to be completed by...
<p>This is a $366,457.00 firm fixed price definitive contract awarded by the U.S. Department of Agriculture's (USDA) Central Region to Clearwater Inc. for the recovery construction of five floodwater retarding structures in Harrison County, Missouri. The work is to be performed in accordance with the contract clauses, provisions, specifications, and designs. The contract has no set-aside designation and has an ultimate completion date of September 30, 2010.</p>
<p>This is a $139,999.09 firm fixed-price delivery order awarded by the U.S. Department of Agriculture's Central Region to Hdr-Kleinfelder, a for-profit subchapter S corporation. The contract is for MN Watershed Dam Assessments, with a performance location in Golden Valley, Minnesota. The contract does not have a set-aside designation and was awarded on August 18, 2015, with a completion date of August 18, 2016.</p>
This is a $341,579.83 firm fixed-price definitive contract awarded by the U.S. Department of Agriculture's (USDA) Region 10 - Alaska Region to S &amp; S General Contractors &amp; Equipment Rental, Inc., a small business certified as a HUBZone firm. The contract, titled &quot;SITKOH PRIORITY WATERSHED FIST PASSAGE,&quot; was awarded on July 28, 2014 with an ultimate completion date of October 31, 2015. The contract was set aside for small businesses. Without additional context about the...
This is a definitive contract awarded by the U.S. Department of Agriculture (USDA) Central Region agency to US Sitework Inc., a self-certified small disadvantaged business, for a construction project related to the Water Resources Protection (WRP) program. The fixed-price contract has a ceiling value of $148,164.25 and a completion date of September 11, 2015. The contract is not associated with a larger vehicle and does not have a set-aside designation. Based on the agency and program, this...

This is a $473,382.98 Firm Fixed Price Definitive Contract awarded by the Central Region of the United States Department of Agriculture (USDA) to S & G Excavating Inc. for the Construction of Phase 2A (Thompson Ditch from 7th Street to US Hwy 41) of the Honey Creek Watershed Protection and Flood Prevention Project. The contract does not have a set-aside designation. The work is scheduled for completion by October 11, 2011. This contract is part of the USDA's larger CONSTRUCTION OF PHASE 2A (THOMPSON DITCH FROM 7TH STREET TO US HWY 41) OF HONEY CREEK PROJECT program.