Springfield autotransformer no. 3 relocation to new madrid
Ended Definitive Contract Awarded Last action
- Contract number
- 89503625CSW000082
- Awardee
-
Southwest Electric CO. UEI E9YJZH4KZ789
- Awarding agency
-
Southeastern Power Administration
Department of Energy
- Obligated
- $0
Award facts
- Opportunity
-
- Springfield autotransformer no. 3 relocation to new madrid Solicitation · 89503625RSW000046 · Posted Dec 23, 2024
- Contract value 0% obligated
- $504,220.20 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 3 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Springfield, MO 65807, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Original award | $0 |
About this award
The Southeastern Power Administration (DOE) awarded a Definitive Contract to Southwest Electric CO. on May 5, 2025, for the relocation of Springfield Autotransformer No. 3 from the Springfield 161 kilovolt Substation to the New Madrid Substation. This project involves the safe and efficient movement of a 161/69 kilovolt electrical transformer with 48/64/80 megavolt-ampere capacity, requiring specialized expertise in high-voltage electrical equipment relocation and infrastructure maintenance. The contract carries a ceiling value of $504,220.20 and is structured as a Firm Fixed Price Definitive Contract designated as a Total Small Business set-aside, ensuring that the work is performed by a qualified small business entity. The place of performance is Springfield, Missouri.
The original solicitation was posted by the Southeastern Power Administration on December 23, 2024, with proposals due April 10, 2025, allowing bidders substantial preparation time to develop comprehensive technical proposals. The work falls under the Power and Communication Line and Related Structures Construction NAICS code 237130. A bilateral modification extended the period of performance from August 14, 2025, to September 18, 2025, adjusting the project timeline to accommodate the complexity of relocating this critical electrical infrastructure component. This contract represents the Department of Energy's investment in maintaining and upgrading the southeastern electrical grid through specialized equipment relocation services.
Quick answers
Who was awarded contract 89503625CSW000082?
89503625CSW000082 was awarded to Southwest Electric CO. by Southeastern Power Administration (Department of Energy) on May 5, 2025.
How much is contract 89503625CSW000082 worth?
The government has obligated $0 on 89503625CSW000082. Its current value, with exercised options, is $504,220.
Was contract 89503625CSW000082 competed?
The extent of competition for 89503625CSW000082 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award