North cody MOI 954 switch replacement - western area power administration (wapa) rocky mountain region has a requirement with the principlal components of work to include replacing one (1) 115-KV,…

Active Definitive Contract Awarded

Contract number
89503225CWA000122
Awardee
Awarding agency
Obligated
$521,721

Award facts

Opportunity
Contract value 100% obligated
$521,721.00 Current and potential, with all options
Completion date 54% complete
Current and potential, with all options
Contracting staff
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Cody, WY 82414, USA

Award details come from SAM.gov/FPDS.

About this award

The Western Area Power Administration (WAPA), Rocky Mountain Region, awarded a $521,721 firm fixed-price definitive contract to Addison Construction Co on September 16, 2025, for the replacement of one 115-kilovolt, 1,200-ampere motor-operated interrupter (MOI) with ground blades and pre-insertion inductor at the North Cody facility in Cody, Wyoming. The contract, which carries no set-aside designation, requires the contractor to provide all labor, materials, tools, equipment, and transportation necessary for the equipment replacement utilizing the existing support structure. Completion is scheduled for September 30, 2027. This procurement supports WAPA's mission to maintain and modernize electrical transmission infrastructure across its 15-state service territory in the Western United States.

Addison Construction Co, a Wyoming-based small business subchapter S corporation, is well-positioned to execute this electrical infrastructure work given its extensive portfolio of federal contracts with WAPA spanning complex substation upgrades, circuit breaker replacements, and power transmission equipment installations. The company's demonstrated expertise in electrical infrastructure construction and consistent track record with WAPA—including previous contract values ranging from approximately $17,000 to $6.6 million—reflects its capability to manage specialized electrical equipment replacement projects. No major subcontractors were identified in the award documentation.

Description

North cody MOI 954 switch replacement - western area power administration (wapa) rocky mountain region has a requirement with the principlal components of work to include replacing one (1) 115-KV, 1200-AMP motor-operated interrupter (also referred to

Quick answers

Who was awarded contract 89503225CWA000122?

89503225CWA000122 was awarded to Addison Construction Co by Western Area Power Administration (Department of Energy) on September 16, 2025.

How much is contract 89503225CWA000122 worth?

The government has obligated $521,721 on 89503225CWA000122.

Was contract 89503225CWA000122 competed?

The extent of competition for 89503225CWA000122 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award