Kimball substation stage 04
Ended Definitive Contract Awarded Last action
- Contract number
- 89503220CWA000050
- Awardee
-
Addison Construction Co UEI D4N8K3L9E824
- Awarding agency
-
Western Area Power Administration
Department of Energy
- Obligated
- $252,584
Award facts
- Opportunity
-
- Kimball Substation Stage 04 Pre-Solicitation · 89503220BWA000032 · Posted Jul 15, 2020
- Kimball Substation Stage 04 Award Notice · Posted Sep 25, 2020
- Kimball Substation Stage 04 Solicitation · Posted Jul 31, 2020
- Contract value 5% obligated
- $5,034,132.55 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 8 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Kimball, NE 69145, USA
- Legislative mandates
-
- Walsh-Healey Public Contracts Act FAR subpart 22.6
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $3,711 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $15,807 | |
| Supplemental Agreement for work within scope | $31,612 | |
| Supplemental Agreement for work within scope | $7,167 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Original award | $194,287 |
About this award
The Department of Energy Western Area Power Administration awarded a $5 million firm fixed price contract to Addison Construction Co. to upgrade the Kimball Substation in Kimball, Nebraska. The scope of work involves modernizing equipment, increasing capacity, and improving reliability through infrastructure upgrades including new transformers, breakers, switches, and associated civil, structural, and electrical work. This total small business set-aside contract was awarded under the solicitation seeking engineering and construction services to upgrade the substation located at 69145 Kimball, Nebraska between September 2022 and December 2023. The Western Area Power Administration will provide funding for improvements to the transmission and distribution of electricity through its work to support the energy grid in the western United States.
Quick answers
Who was awarded contract 89503220CWA000050?
89503220CWA000050 was awarded to Addison Construction Co by Western Area Power Administration (Department of Energy) on September 24, 2020.
How much is contract 89503220CWA000050 worth?
The government has obligated $252,584 on 89503220CWA000050. Its current value, with exercised options, is $5,034,133.
Was contract 89503220CWA000050 competed?
The extent of competition for 89503220CWA000050 was full and open competition after exclusion of sources. The government received 8 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award