Outfall 200 mercury treatment facility (OF200 MTF)
Ended Definitive Contract Awarded Last action
- Contract number
- 89303319CEM000041
- Awardee
-
Aptim-North Wind Construction JV LLC UEI HTAJUAEEXEM4
- Awarding agency
-
Office of Environmental Management
Department of Energy
- Obligated
- $142,017,409
Award facts
- Opportunity
-
- Outfall 200 Mercury Treatment Facility (OF200 MTF) Request for Proposal Special Notice · 89303318REM000002 · Posted Mar 23, 2018
- Outfall 200 Mercury Treatment Facility (OF200 MTF) Award Notice · Posted Nov 30, 2017
- Contract value 96% obligated
- $148,323,187.04 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 2 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Oak Ridge, TN 37830, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $4,940,530 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | -$5,000,000 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $13,945,000 | |
| Supplemental Agreement for work within scope | $1,970,060 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $5,071,064 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $8,370,679 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $0 | |
| Definitize Change Order | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $7,546,601 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Definitize Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $5,933,500 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Definitize Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Funding Only Action | $22,585,629 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Definitize Change Order | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Change Order | $0 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
This is a federal contract award from the U.S. Department of Energy's Office of Environmental Management to construct the Outfall 200 Mercury Treatment Facility (OF200 MTF) in Oak Ridge, Tennessee. The $148,323,187.04 firm-fixed-price contract was awarded to Aptim-North Wind Construction JV LLC as the prime contractor. The project involves the design and construction of a new mercury treatment facility at the Y-12 National Security Complex. Notable subcontractors include TJ Wies Contracting Inc., Ivet Environmental, Inc., Apollo Sheet Metal Inc., and Griffin Dewatering, LLC, which are providing specialized construction, environmental, and remediation services. This appears to be a critical infrastructure project aimed at addressing mercury contamination in the region.
Quick answers
Who was awarded contract 89303319CEM000041?
89303319CEM000041 was awarded to Aptim-North Wind Construction JV LLC by Office of Environmental Management (Department of Energy) on December 4, 2018.
How much is contract 89303319CEM000041 worth?
The government has obligated $142,017,409 on 89303319CEM000041. Its current value, with exercised options, is $148,323,187.
Was contract 89303319CEM000041 competed?
The extent of competition for 89303319CEM000041 was full and open competition. The government received 2 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award