Chamblee campus bldg 108 phase II
Ended Definitive Contract Awarded Last action
- Contract number
- 75D30121C10098
- Awardee
-
Hcbeck, LTD. UEI USH2BTXJGHM4
- Awarding agency
-
CDC Pittsburgh
Centers for Disease Control and Prevention, Department of Health and Human Services
- Obligated
- $221,114,401
Award facts
- Opportunity
-
- Chamblee Campus Building 108 Pre-Solicitation · 75D30120R67995 · Posted Jan 16, 2020
- Contract value 100% obligated
- $221,114,401.00 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Y1AA Construction Of Office Buildings
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 3 offers Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Atlanta, GA 30341, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $321,119 | |
| Supplemental Agreement for work within scope | -$53,081 | |
| Supplemental Agreement for work within scope | $605,701 | |
| Supplemental Agreement for work within scope | $589,880 | |
| Supplemental Agreement for work within scope | $344,940 | |
| Other Administrative Action | -$9,662 | |
| Supplemental Agreement for work within scope | $629,221 | |
| Supplemental Agreement for work within scope | $6,008,415 | |
| Supplemental Agreement for work within scope | -$759,640 | |
| Supplemental Agreement for work within scope | $138,717 | |
| Supplemental Agreement for work within scope | $593,647 | |
| Supplemental Agreement for work within scope | $85,985 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $36,345 | |
| Supplemental Agreement for work within scope | $3,953,455 | |
| Supplemental Agreement for work within scope | $192,096 | |
| Supplemental Agreement for work within scope | $573,581 | |
| Supplemental Agreement for work within scope | $388,184 | |
| Supplemental Agreement for work within scope | $128,294 | |
| Supplemental Agreement for work within scope | $4,157,657 | |
| Supplemental Agreement for work within scope | -$14,339 | |
| Supplemental Agreement for work within scope | $430,208 | |
| Supplemental Agreement for work within scope | $526,954 | |
| Supplemental Agreement for work within scope | $85,231 | |
| Supplemental Agreement for work within scope | $161,375 | |
| Supplemental Agreement for work within scope | -$646,677 | |
| Supplemental Agreement for work within scope | $14,032 | |
| Supplemental Agreement for work within scope | $463,723 | |
| Supplemental Agreement for work within scope | $973,540 | |
| Supplemental Agreement for work within scope | $130,455 | |
| Supplemental Agreement for work within scope | -$221,077 | |
| Original award | $201,286,122 |
Show all 33
About this award
The Centers for Disease Control and Prevention (CDC) awarded a $221.1 million firm fixed price definitive contract to Hcbeck, LTD. on December 7, 2020, for the Chamblee Campus Building 108 Phase II project. The contract encompasses design-build services for construction at the CDC's Chamblee, Georgia facility, including demolition of existing structures, construction of over 138,000 square feet of new buildings, a parking deck, guardhouse, central utility plant modifications, and associated site work to support over 500 staff members. The work was originally solicited as a pre-solicitation opportunity posted in January 2020, with an estimated value range of $150–200 million and a 40-month completion schedule. The contract includes no set-aside designation and utilizes firm fixed price pricing, placing all cost risk on the contractor.
Performance is scheduled for completion by February 28, 2026, at the Chamblee, Georgia location. This project represents a significant infrastructure investment by the CDC to modernize and expand its research and office operations at the Chamblee campus, supporting the agency's mission to protect public health through updated laboratory facilities and administrative space.
Quick answers
Who was awarded contract 75D30121C10098?
75D30121C10098 was awarded to Hcbeck, LTD. by CDC Pittsburgh (Centers for Disease Control and Prevention) on December 7, 2020.
How much is contract 75D30121C10098 worth?
The government has obligated $221,114,401 on 75D30121C10098.
Was contract 75D30121C10098 competed?
The extent of competition for 75D30121C10098 was full and open competition. The government received 3 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award