EG:new award-ganta-gbarnga grid extension oversight: supervise and inspect construction of the ganta-gbarnga grid extension activity.

Ended Definitive Contract Awarded Last action

Contract number
72066919C00001
Awardee
Awarding agency
Obligated
$919,030

Award facts

Contract value 100% obligated
$919,029.98 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Not Competed · 1 offer Only One Source
Pricing
Firm Fixed Price
Place of performance
Enterprise Square, Corner of Front and, Nelson St, Monrovia, Liberia

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00011 · EG:ggge: DE-obligation of unliquidated funds. 1. Reduce the total award amount by $2,608.02 from $921,638.00 to $919,029.98; 2. Reduce the total obligated… -$2,608
Other Administrative Action P00010 · EG:ggge: DE-obligation and RE-obligation of funds. ***end of MOD 010*** $0
Other Administrative Action P00008 · EG:ggge: DE-obligation and RE-obligation of funds. ***end of MOD 008*** $0
Other Administrative Action P00009 · EG:ggge: DE-obligation and RE-obligation of funds. ***end of MOD 009*** $0
Other Administrative Action P00007 · EG:ggge: DE-obligation and RE-obligation of funds. ***end of MOD 007*** $0
Change Order P00006 · EG:ggge: equitable adjustment and extend the period of performance by three (3) months from july 23, 2021 - october 23, 2021. ***end of MOD 006*** $94,844
Supplemental Agreement for work within scope P00005 · EG:ggge: equitable adjustment and extend the period of performance by nine (9) months from october 23, 2020 to july 23,2021 $284,531
Change Order P00004 · EG:ggge: change order: to extend the construction oversight period by five (5) months $0
Funding Only Action P00003 · EG:ggge: modification to add funding for the extension of oversight of the ggge project $182,652
Change Order P00002 · EG:change order: to extend the construction oversight period by four(4) months and add back the two(2) inspection visits in months six(6) and twelve(12) of… $0
Other Administrative Action P00001 · EG:admin MOD. To change oversight from 10 to 12 months new award-ganta-gbarnga grid extension oversight: supervise and inspect construction of the ganta-gbarnga… $0
Original award $359,612
Show all 12

About this award

This is a definitive contract awarded by the U.S. Agency for International Development (USAID) to NRECA International, a non-profit organization, to supervise and inspect the construction of the Ganta-Gbarnga grid extension activity in Liberia. The contract has a firm fixed price of $919,029.98 and a completion date of May 26, 2023. The contract is not set aside for a particular business type. The primary focus of this contract is on the operation and maintenance of power generation plants and distribution grids, as well as technical assistance in the energy sector, which align with USAID's mission in Liberia.

Quick answers

Who was awarded contract 72066919C00001?

72066919C00001 was awarded to Nreca International by US Mission in Liberia (Overseas Missions) on January 31, 2019.

How much is contract 72066919C00001 worth?

The government has obligated $919,030 on 72066919C00001.

Was contract 72066919C00001 competed?

The extent of competition for 72066919C00001 was not competed. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award