CO flap LAR 10(1) horsetooth RES and carter lake roadway and parking lot rehabilitation the purpose is to award a construction contract for the subject project.

Ended Definitive Contract Awarded Last action

Contract number
6982AF25C000013
Awardee
Awarding agency
Obligated
$11,512,040

Award facts

Opportunity
Contract value 100% obligated
$11,512,040.00 Current and potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Fort Collins, CO 80526, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00004 · This modification is being executed to modify the elevations of final pavement surface to accommodate a client (larimer county) requested parking lot… $300,000
Supplemental Agreement for work within scope P00003 · This modification modifies special contract requirements specifications in sections 108.07 and 156.07 to allow for work on specified restricted days/periods… $0
Supplemental Agreement for work within scope P00002 · This modification removes the language from this contract that instructs the contractor to use the eebacs system for project reporting and replaces IT with… $0
Exercise an Option P00001 · CO flap LAR 10(1) horsetooth RES and carter lake the purpose for this modification is to award option x $2,807,548
Original award $8,404,493

About this award

The Federal Highway Administration awarded a $11.5 million definitive contract to FDT Water Infrastructure, LLC on February 26, 2025, under a total small business set-aside for roadway and parking lot rehabilitation at Horsetooth Reservoir and Carter Lake in Larimer County, Colorado.

FDT Water Infrastructure is an Alaskan Native Corporation-owned, SBA-certified 8(a) Program Participant. Place of performance is Fort Collins, CO. The contract is firm fixed price with an ultimate completion date of May 17, 2027.

The originating solicitation called for rehabilitation and reconstruction of parking lots and access routes, including roadway excavation, placement of rip rap and aggregate base, full depth reclamation, asphalt concrete pavement, minor concrete pavement, installation of culverts and manholes, concrete curb and sidewalk, and permanent and temporary traffic control. A modification to the original award adjusted final pavement surface elevations to accommodate a client-requested parking lot elevation modification and installation of a water treatment manhole and associated drainage appurtenances.

Quick answers

Who was awarded contract 6982AF25C000013?

6982AF25C000013 was awarded to FDT Water Infrastructure, LLC by Federal Highway Administration (Department of Transportation) on February 26, 2025.

How much is contract 6982AF25C000013 worth?

The government has obligated $11,512,040 on 6982AF25C000013.

Was contract 6982AF25C000013 competed?

The extent of competition for 6982AF25C000013 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award