$33,613,559

Award facts

Opportunity
Contract value 100% obligated
$33,645,591.78 Current and potential, with all options
Completion date 97% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 6 offers Sealed Bid
Pricing
Firm Fixed Price
Place of performance
Davenport, CA 95017, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00019 · This contract modification (CM) adds items that fall within current scope of work. A total of $241,265.74 will be added to the contract amount. There will 30… $241,266
Supplemental Agreement for work within scope P00018 · This modification adds quantities and payment associated with the owner requests and unforeseen conditions at the yellowbank parking lot. $138,741
Supplemental Agreement for work within scope P00017 · This contract modification (CM) adds a pay item for removal of trash and off-haul from previously unknown dump sites along the construction site. There is no… $178,683
Additional Work (new agreement, FAR part 6 applies) P00016 · This contract modification (CM) adds a pay item for railroad crossing panel work and $39,612.49 to the contract amount. There is no change to the contract… $39,612
Supplemental Agreement for work within scope P00015 · This modification adds pay item X2691 (66601-0000), contract modification work (county sewer line requests), and increases funding. The contract completion date… $15,245
Supplemental Agreement for work within scope P00014 · CA flap SCR T5(1) monterey BAY sanctuary scenic trail $74,652
Supplemental Agreement for work within scope P00011 · The purpose of this contract modification (CM) is to add an updated electrical panel and lift station. $238,801
Supplemental Agreement for work within scope P00010 · The purpose of this contract modification (CM) is to modify work and extend the period of performance by 45 days. $91,485
Supplemental Agreement for work within scope P00009 · The purpose of this contract modification (CM) is remove and add items to modify work. There will be no effect on the net contract value nor the period of… $0
Supplemental Agreement for work within scope P00008 · The purpose of this contract modification (CM) is to increase the contract amount by $288,852.80 and modify work items. $288,853
Supplemental Agreement for work within scope P00007 · The purpose of this contract modification (CM) is to provide funding to update temporary seeding to permanent seeding. This modification adds the following… $149,742
Supplemental Agreement for work within scope P00006 · Remove and replace (or abandon according to section 203) the existing culvert at station 260+40 with a 36INCH hdpe pipe. Complete the work at station 260 + 40… $0
Supplemental Agreement for work within scope P00005 · This contract modification (CM) will relocate the existing 6.5-inch fiberglass irrigation water line shown on sheet U14 of the construction plan set, with an… $0
Supplemental Agreement for work within scope P00004 · CA flap SCR T5(1) monterey BAY sanctuary scenic trail this zero-dollar contract modification expands the material parameters for reinforced soil slope backfill. $0
Supplemental Agreement for work within scope P00003 $0
Supplemental Agreement for work within scope P00002 $49,285
Supplemental Agreement for work within scope P00001 · CA flap SCR T5(1) monterey BAY sanctuary scenic trail this contract modification provides funding for biological monitoring and performing garter snake… $48,500
Original award $32,058,694
Show all 18

About this award

The Federal Highway Administration awarded a definitive firm-fixed-price contract to Joseph J. Albanese, Inc. for the CA FLAP SCR T5(1) Monterey Bay Sanctuary Scenic Trail Construction on April 25, 2024, with a ceiling value of $33,645,591.78 and no set-aside applied.

The originating solicitation, posted June 27, 2023, solicited construction of a new 12-foot-wide paved trail with 2-foot gravel shoulders for approximately 7.5 miles, reconstruction and improvement of two existing parking facilities, installation of 6-inch PVC waterline and fence along the trail, and construction of reinforced soil slopes, rockery walls, new pipe culverts, and pipe culvert extensions. A recent contract modification added $241,265.74 in scope items and extended the period of performance by 30 days, moving the ultimate completion date to November 30, 2026. Place of performance is Davenport, CA.

Quick answers

Who was awarded contract 6982AF24C000016?

6982AF24C000016 was awarded to Joseph J. Albanese, Inc. by Federal Highway Administration (Department of Transportation) on April 25, 2024.

How much is contract 6982AF24C000016 worth?

The government has obligated $33,613,559 on 6982AF24C000016. Its current value, with exercised options, is $33,645,592.

Was contract 6982AF24C000016 competed?

The extent of competition for 6982AF24C000016 was full and open competition. The government received 6 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award