- The Department of Transportation Federal Highway Administration awarded a $6,846,385.18 firm fixed-price delivery order to Pine Bluffs Gravel & Excavating, Inc. (doing business as Cornhusker Concrete), a for-profit subchapter S corporation, for roadway reconditioning and the addition of aggregate surface course for Minuteman missile access roads in Colorado. The delivery order was issued under the FHA Roadwork Architect Engineering IDIQ 2016-2021 contract vehicle. No small business set-aside...
- The Federal Highway Administration awarded a $5.98 million Firm Fixed Price Definitive Contract to Pine Bluffs Gravel & Excavating, Inc. (doing business as Cornhusker Concrete) on March 6, 2026, for the Minuteman Missile Access Construction Contract. The contract, designated as a Total Small Business set-aside, requires road construction and re-graveling services across multiple miles of existing gravel roads in Colorado, Nebraska, and Wyoming, with work performance centered at Francis E....
- This is a firm-fixed-price delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency, to Pine Bluffs Gravel & Excavating, Inc. (PBGE), doing business as Cornhusker Concrete. The $3,425,738.00 contract is for the reconditioning and/or resurfacing of existing gravel roads providing access to Minuteman missile sites. The award is not associated with a set-aside program. PBGE, a for-profit subchapter S corporation, has received over $18 million in prime federal...
- This is a firm fixed-price delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency, to Pine Bluffs Gravel & Excavating, Inc. (PBGE), doing business as Cornhusker Concrete. The contract, valued at $1,936,612.74, is for road construction and reconditioning services related to access roads for Minuteman missile sites. The delivery order was issued against the FHWA's Roadwork Architect Engineering IDIQ contract, a multi-year, multiple-award contract vehicle. The...
- Pine Bluffs Gravel & Excavating, Inc., operating as Cornhusker Concrete, was awarded an $8.65 million firm fixed-price contract by the Federal Highway Administration on March 12, 2025, for roadway reconditioning and aggregate surface course installation on Minuteman Missile Access Roads. The contract is designated as a Total Small Business set-aside and carries an ultimate completion date of September 20, 2025. Work will be performed in Pine Bluffs, Wyoming, and involves adding four inches...
- Pine Bluffs Gravel & Excavating, Inc., doing business as Cornhusker Concrete, was awarded a $5.7 million firm fixed price delivery order against the Federal Highway Administration's 2016-2021 Roadwork Architect Engineering IDIQ. The order is for CLIN 0001 to fund improvements to the access road for the Minuteman missile program, a key Department of Transportation initiative. Work will involve upgrading approximately 83 miles of roadway in Greeley, Colorado over a six-month period...
- <p>This is a delivery order awarded to Pine Bluffs Gravel & Excavating, Inc. (dba Cornhusker Concrete), a for-profit subchapter S corporation, by the Department of Transportation Federal Highway Administration. The $3,549,953.71 contract is for the resurfacing of gravel roads providing access to Minuteman missile sites under the FHA Roadwork Architect Engineering IDIQ 2016-2021 contract. The work is being performed in Pine Bluffs, Wyoming and does not have a set-aside designation.</p>
- This is a $6,573,999.56 firm fixed price definitive contract awarded by the Federal Highway Administration, a civilian agency, to Iron Mike Construction LLC, a Service-Disabled Veteran-Owned Small Business (SDVOSB), for the construction of access roads for the MINUTEMAN MISSILE program. The contract was set aside for SDVOSB firms and has an ultimate completion date of December 16, 2022. Iron Mike Construction, a general contractor based in Denver, has extensive experience executing...
- This is a firm fixed price delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency within the U.S. Department of Transportation, to American Civil Constructors LLC (DBA ACC Mountain West), a minority-owned and Hispanic-American-owned construction company. The $4,001,376 contract is for the reconditioning and/or resurfacing of existing gravel roads related to the Minuteman Missile access road, with a completion date of October 16, 2015. This work is part of the...
- This is a $1,705,477.70 firm fixed-price delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency, to Pine Bluffs Gravel & Excavating, Inc. (PBGE), doing business as Cornhusker Concrete. The contract is for the recovery, construction, and reconditioning of 16.3 miles of aggregate surface course for the Wyoming Bureau of Land Management (BLM) project 2302(1), the Hudson Atlantic Road. There is no set-aside designation for this award. PBGE is a for-profit,...
This is a $6,629,498.98 firm-fixed-price contract awarded by the Federal Highway Administration (part of the U.S. Department of Transportation) to Pine Bluffs Gravel & Excavating, Inc., doing business as Cornhusker Concrete, for the CO OMAD 300(68) Minuteman Missile Access Road Construction project. The contract involves reconditioning and regraveling 94.24 miles of existing aggregate surface roads across Colorado, Wyoming, and Nebraska that provide access to Minuteman missile transportation. This contract was set aside for small businesses. The original solicitation was issued as a pre-solicitation notice to determine interest from qualified small business prime contractors, including HUBZone, woman-owned, 8(a), and service-disabled veteran-owned small businesses, to potentially set aside the full and open competition. The contract has a completion date of November 6, 2023.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
CO OMAD 300(68) Minuteman Missile Access Road | 6982AF23B000009 | Department of Transportation Federal Highway Administration | Pre-Solicitation 2/4 | 3/28/23, 12:24 PM | |
CO OMAD 300(68) Minuteman Missile Access Road | 6982AF23SS0012 | Department of Transportation Federal Highway Administration | Pre-Solicitation 1/4 | 1/17/23, 11:36 AM | |
CO OMAD 300(68) MINUTEMAN MISSILE ACCESS ROADS | 6982AF23C000040 | Department of Transportation Federal Highway Administration | Award Notice 4/4 | 6/13/23, 10:59 AM | |
CO OMAD 300(68) Minuteman Missile Access Road | 6982AF23B000009 | Department of Transportation Federal Highway Administration | Solicitation 3/4 | 4/14/23, 3:10 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00003 | Close Out | ($62k) | 9/11/24 | |
| P00002 | Supplemental Agreement for work within scope | $0 | 8/7/24 | |
| P00001 | Supplemental Agreement for work within scope | $0 | 11/6/23 | |
| Not listed | Not listed | $6.7m | 6/9/23 |