This modification deobligates excess funds from the project's accounts.
Ended Definitive Contract Awarded Last action
- Contract number
- 6982AF23C000011
- Awardee
-
Taylor Jane Construction LP UEI GZZVJ9VCEMM8
- Awarding agency
-
Federal Highway Administration
Department of Transportation
- Obligated
- $1,476,046
Award facts
- Opportunity
-
- CA erfo sierra NF 05S07(1) norris creek bridge Pre-Solicitation · 6982AF22B000037 · Posted May 16, 2022
- Contract value 100% obligated
- $1,476,046.14 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 6 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Ahwahnee, CA, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | -$222,503 | |
| Supplemental Agreement for work within scope | $0 | |
| Other Administrative Action | $175,000 | |
| Change Order | $53,820 | |
| Original award | $1,469,729 |
About this award
The Federal Highway Administration awarded a $1.476 million definitive contract to Taylor Jane Construction LP for replacement of the Norris Creek Bridge in Sierra National Forest on January 23, 2023, under a total small business set-aside.
Taylor Jane Construction LP is a minority-owned, small disadvantaged, woman-owned business. Place of performance is Ahwahnee, CA. The originating solicitation, posted May 16, 2022, sought replacement of the bridge damaged by fire in 2020 with a prefabricated steel structure measuring 70 feet by 24 feet. Scope includes removal of the existing structure, excavation and embankment work, installation of approximately 8,500 cubic yards of riprap and 300 cubic yards of roadway aggregate, 200 tons of asphalt pavement, and 150 linear feet of guardrail. Work was scheduled January through September 2023. NAICS 237310; PSC D302.
In FY2023, the prime invoiced $895 thousand across 1.3 FTEs and 2,683 contractor hours at a derived government-paid rate of $333.41 per hour, self-performing all reported labor with no subcontractors. Ultimate completion date is July 25, 2025. The current modification deobligates excess funds from the project's accounts.
Quick answers
Who was awarded contract 6982AF23C000011?
6982AF23C000011 was awarded to Taylor Jane Construction LP by Federal Highway Administration (Department of Transportation) on January 23, 2023.
How much is contract 6982AF23C000011 worth?
The government has obligated $1,476,046 on 6982AF23C000011.
Was contract 6982AF23C000011 competed?
The extent of competition for 6982AF23C000011 was full and open competition after exclusion of sources. The government received 6 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award