Clin 00001 - K200 funds flap funds partial CN, total: schedule a: $3,027,000 option X: $156,000 clin 00002 - K740 funds match from FS fltp funds. Partial CN, total: schedule a: $3,027,000 option X:…
Ended Definitive Contract Awarded Last action
- Contract number
- 6982AF20C000023
- Awardee
-
R.s. Bennett Construction Company, Inc. UEI PENGGW3UY663
- Awarding agency
-
Federal Highway Administration
Department of Transportation
- Obligated
- $989,714
Award facts
- Opportunity
-
- WY FLAP 30400(1) Gros Ventre Road Pre-Solicitation · 6982AF19B000011 · Posted Apr 15, 2020
- WY FLAP 30400(1) Gros Ventre Road Award Notice · Posted Jun 11, 2020
- Contract value 100% obligated
- $989,714.24 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 5 offers Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Teton Village, WY, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Terminate for Default | -$1,961,377 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $49,825 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $2,601 | |
| Original award | $2,898,666 |
About this award
The Department of Transportation Federal Highway Administration awarded a $989,714 firm fixed price definitive contract to R.S. Bennett Construction Company, Inc. to provide construction services for safety improvements along 3.75 miles of Gros Ventre Road in Teton Village, Wyoming. The solicitation sought minor widening, resurfacing, drainage work and optional paving of pull-offs and parking lots as specified in the Wyoming FLAP 30400(1) Gros Ventre Road project. Seven contractors submitted bids ranging from $2.7 million to $3.7 million, with the selected awardee providing the lowest priced technically acceptable proposal. No set-aside designation applied. Performance will take place over one construction season to resurface the roadway and conduct specified excavation work totaling approximately 3,100 cubic yards along Gros Ventre Road in Teton Village.
Description
Clin 00001 - K200 funds flap funds partial CN, total: schedule a: $3,027,000 option X: $156,000 clin 00002 - K740 funds match from FS fltp funds. Partial CN, total: schedule a: $3,027,000 option X: $156,000 WY flap 30400(1) gros ventre road
Quick answers
Who was awarded contract 6982AF20C000023?
6982AF20C000023 was awarded to R.s. Bennett Construction Company, Inc. by Federal Highway Administration (Department of Transportation) on June 11, 2020.
How much is contract 6982AF20C000023 worth?
The government has obligated $989,714 on 6982AF20C000023.
Was contract 6982AF20C000023 competed?
The extent of competition for 6982AF20C000023 was full and open competition. The government received 5 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award